Matters ▸ Attachment
Committee Report - Finance - 10-7-15 — File 200062
Finance Committee
Page 1 of 7
Printed 10/9/2015
October 7, 2015
REPORT OF THE FINANCE COMMITTEE
Attendee Name
Title
Status
Arrived
Tony Lafuente
Chair
Present
Maryann M. Heuston
Vice Chair
Present
Katjana Ballantyne
Ward Seven Alderman
Present
John M. Connolly
Alderman At Large
Present
William A. White Jr.
Alderman At Large
Present
Matthew McLaughlin
Ward One Alderman
Present
Robert J. McWatters
Ward Three Alderman
Absent
Mark Niedergang
Ward Five Alderman
Present
Rebekah L. Gewirtz
Ward Six Alderman
Absent
Dennis M. Sullivan
Alderman At Large
Present
Mary Jo Rossetti
Alderman at Large
Present
Others present: Michael Glavin - OSPCD, George Proakis - OSPCD, Brad Rosen - OSPCD, Rob
King - Capital Projects, William Roche - Personnel, Deputy Chief Paul Trant - SPD, Peter
Forcellese, Jr. - Treasurer, Ed Bean - Finance, Omar Boukili - Mayor's Office, Charles Sillari -
Clerk of Committees
The meeting took place in the Committee Room and was called to order at 6:00 PM by
Alderman Lafuente and adjourned at 8:00 PM
Document List:
·
Development Projects by year
·
Cedar Street sewer repairs
·
Debt service info (199729)
·
Comprehensive Facilities assessment
1.
Approval of the September 21, 2015 Minutes
RESULT:
ACCEPTED
195734: That the Administration provide this Board with a breakdown of special events
(festivals, concerts, road races, etc.), indicating if they are/were city sponsored and/or
Finance Committee
Page 2 of 7
Printed 10/9/2015
privately sponsored, and including city expenditures for each.
RESULT:
WORK COMPLETED
196588: That the Recreation Superintendent appear before this Board to provide an
update of all expenditures for the current fiscal year.
RESULT:
WORK COMPLETED
197339: Requesting that the City-owned portion of 163 Glen Street be declared available
for disposition.
RESULT:
KEPT IN COMMITTEE
197880: That the Director of Finance and the Chief Assessor provide a 5-year projection of
new commercial office and new commercial retail revenues.
RESULT:
WORK COMPLETED
197976: That the Director of Capital Projects present to this Board, no later than January
22, 2015, a 5- and 10-year plan for the use, development and sale of City buildings.
RESULT:
WORK COMPLETED
198023: Finance Director responding to #197850 re: grants and donations that require this
Board's approval.
RESULT:
WORK COMPLETED
198091: That the Director of the SPCD (ISD) and the Director of Personnel appear before
this Board to explain why health inspectors earn the same amount, or more than, building
inspectors when they do not need to be licensed and building inspectors do.
RESULT:
WORK COMPLETED
198093: That the Director of SPCD (ISD) and the Director of Personnel appear before this
Board to explain how gained sick time is dealt with and how employees can take that time
off.
Mr. Roche discussed the issue of employee sick time and stated that he cannot act for the school
side of the city.
Finance Committee
Page 3 of 7
Printed 10/9/2015
Alderman Niedergang’s motion, that the City Solicitor draft an ordinance to allow city
employees working less than 20 hours per week to earn sick time; AND BE IT FURTHER
ORDERED That the Director of Personnel provide information relative to the cost of said
proposal, was approved.
RESULT:
WORK COMPLETED
198126: Requesting an appropriation of $225,000 and authorization to borrow $225,000 in
a bond for Phase One services for a Citywide Wayfinding Program.
RESULT:
PLACED ON FILE
198423: Senator Jehlen responding to #198182 re: the senior property tax deferral.
RESULT:
WORK COMPLETED
198643: That the Director of Recreation and the Finance Director update this Board and
its Committee on Youth Services about any outstanding invoices for the Veterans Rink in
FY14 and FY15.
RESULT:
WORK COMPLETED
199134: That the Administration include a full time arborist position in the upcoming
FY16 budget.
RESULT:
WORK COMPLETED
199247: That the Director of SPCD provide this Board with written responses to certain
requests for residential and commercial data since 2010.
Mr. Proakis distributed information regarding development projects completed by year. Alderman
Rossetti requested that years 2014 and 2015 be split. Alderman White inquired about the status of
the North Point project.
Alderman White's motion, that the Executive Director of the Office of Strategic Planning and
Community Development consult with the new management team at North Point and report back
to the Board of Aldermen regarding their plans, was approved.
RESULT:
KEPT IN COMMITTEE
199279: That the Director of Finance report to this Board which engineering consultants
have been retained for which projects from January through May, 2015, and provide
copies of all such invoices to this Board by June 11.
Finance Committee
Page 4 of 7
Printed 10/9/2015
RESULT:
WORK COMPLETED
199414: That the Administration, with the Fire and Police Departments, compile a report,
by July 31, 2015, of "needed assistance" calls made by each tax-exempt facility over the
past 2 years. (2nd request)
RESULT:
KEPT IN COMMITTEE
199425: That the City Auditor prepare a list of all no bid contracts for goods and services
in excess of $25,000 currently in force.
RESULT:
WORK COMPLETED
199465: Finance Director responding to #199279 re: Engineering consultants and invoices,
Jan-May, 2015.
RESULT:
WORK COMPLETED
199562: City Auditor responding to #199425 re: a list of exempt, non-publicly bid
contracts.
RESULT:
WORK COMPLETED
199642: Requesting an appropriation of $470,000 from the Capital Stabilization Fund to
fund a comprehensive citywide Mobility Plan.
Alderman Niedergang expressed his feeling that this study is needed, even if the GLX does not
happen, and that it would make a huge difference in peoples' lives. Alderman Heuston wants the
Board of Aldermen to have input.
RESULT:
KEPT IN COMMITTEE
199717: That the Director of Personnel inform this Board whether the new sick-leave law
approved by voters last November applies to all City employees, and if not, who is
excluded, and whether there are plans to address this exclusion.
RESULT:
WORK COMPLETED
199729: Requesting an appropriation and authorization to borrow $5,197,500 in a bond for
sewer repairs to Cedar St.
Mr. King discussed the need for making these repairs and requirements for developers. Mr.
Forcellese distributed information on the city’s debt service and Mr. Bean spoke about reserve
funds for needed improvements.
Finance Committee
Page 5 of 7
Printed 10/9/2015
Alderman White’s motion, that the City Engineer provide the Board of Aldermen with a copy
of the storm water policy and written discussion of the 4 to 1 plan, was approved.
Alderman White’s motion, that the City Treasurer provide the Board of Aldermen with a
water/sewer Enterprise Fund balance sheet and with water and sewer rates from the 15 largest
communities, population wise, was approved.
RESULT:
APPROVED
199730: Requesting an appropriation and authorization to borrow $2,227,500 in a bond for
water repairs to Cedar St.
See 199729 for discussion.
RESULT:
APPROVED
199750: Chief Fire Engineer responding to #199414 re: needed-assistance calls to tax-
exempt facilities.
RESULT:
KEPT IN COMMITTEE
199888: Requesting an appropriation and authorization to borrow $262,000 for Phase 1 of
the Building Assessment/Preventive Maintenance Plan.
Mr. King discussed the Brown and Kennedy Schools and the Recreation building being assessed
in the first phase. Alderman Rossetti inquired about the various phases and the master plan.
This item was approved, conditioned on Alderman White’s request that a copy of the bond
to be provided to the Board of Aldermen before its regular meeting on October 8, 2015.
RESULT:
APPROVED WITH CONDITIONS
199889: Requesting acceptance of an 18 month lease of the West Somerville Police
Substation and office space at 1114 Broadway.
The rent is increased by $300 per month. All other terms remain the same.
RESULT:
APPROVED
199890: Requesting an appropriation of $142,036 From the Capital Stabilization Fund to
purchase 4 police vehicles.
RESULT:
PLACED ON FILE
Finance Committee
Page 6 of 7
Printed 10/9/2015
199891: Requesting approval for the Inspectional Services Weights & Measures Division to
use FY16 funds to pay a FY15 invoice of $434.77.
RESULT:
APPROVED
199892: Requesting the acceptance of a grant of $2,500 from Mass Creative for the Arts
Council to support organization and advocacy.
RESULT:
APPROVED
199893: Requesting acceptance of a grant of $1,792.72 from the Mass DEP for recycling
outreach and materials.
RESULT:
APPROVED
199897: Director of Personnel responding to #199656 re: employee vacancies.
Alderman Rossetti requested that an update be provided.
RESULT:
KEPT IN COMMITTEE
199898: Director of Personnel responding to #199717 re: employee sick leave.
RESULT:
WORK COMPLETED
199922: Requesting approval to pay an FY12 invoice of $45,000 in the DPW using FY16
appropriations.
RESULT:
KEPT IN COMMITTEE
199995: Requesting a transfer of $85,000 from SPCD's Economic Development
Professional and Technical Services Account to its Planning and Zoning Professional and
Technical Services Account for additional zoning impact analysis studies.
Alderman Rossetti was recused from all discussion and action on this item.
RESULT:
APPROVED
199996: Requesting the acceptance of a grant of $34,200 from the MA Cultural Council for
the Arts Council's Local Cultural Council grant program.
RESULT:
APPROVED
199997: Requesting the acceptance of a grant of $12,500 from the MA Department of
Finance Committee
Page 7 of 7
Printed 10/9/2015
Energy Resources for the Office of Sustainability and Environment's assessment of
community shared solar.
RESULT:
APPROVED