Matters ▸ Attachment
SPS eRate Submission - 20221003 — File 22-1925
CITY OF SOMERVILLE, MASSACHUSETTS
INFORMATION TECHNOLOGY
KATJANA BALLANTYNE
MAYOR
DAVID B. GOODRIDGE
2015
CHIEF INFORMATION OFFICER
Somerville City Hall 93 Highland Avenue, Somerville Massachusetts 02143
[phone removed] x3266 Office dgoodridge@somervillema.gov (781)254-9198 Cell
To:
City Council
From: David Goodridge, CIO
Re:
eRate Appropriation
Date:
November 08, 2022
The project will replace all aged SPS network equipment with supported non end of life equipment at all schools except
Somerville High School. This will bring our network infrastructure in line with the entirety of network equipment across
the whole city.
There are no additional costs or revenues associated with this equipment. Operationally, it allows a focus on similar
equipment which helps with cybersecurity risk and operational efficiency by centralizing the management of the
infrastructure.
The equipment will upgrade the SPS network infrastructure in line with the municipal network. This allows for an up to
date, consistent, and resilient network design that will allow for significant bandwidth increases for SPS. The upgrade
enhances safety as more network services are added such as building controls, access control, cameras, and lighting.
There are federal mandates on cybersecurity as well. This is a fiscally responsible project as we take advantage of eRate
funding which will cover about half of the cost of the project. With this consistent design, it will allow us to utilize
another ARPA project to allow configuration and monitoring of all network equipment across the entire city network.
Useful life is dependent on the pace of technology. We envision this equipment to be in place for at least 5-7 years.
Cost based on proposal submissions from the eRate bidding process. eRate eligible total is $704,360.44. eRate 80%
responsibility total = $563,488.35. eRate 20% City responsibility total = $140,872.09.
Vendor selected proposal total for all school equipment = $988,438.45.
Total for this project = Difference between vendor total and eRate eligible total = $284,078.01 PLUS eRate City 20% =
$140,872.09.
Project Final Total = $424,950.10.
CITY OF SOMERVILLE, MASSACHUSETTS
INFORMATION TECHNOLOGY
KATJANA BALLANTYNE
MAYOR
DAVID B. GOODRIDGE
2015
CHIEF INFORMATION OFFICER
Somerville City Hall 93 Highland Avenue, Somerville Massachusetts 02143
[phone removed] x3266 Office dgoodridge@somervillema.gov (781)254-9198 Cell
RATINGS
------------------------------------
Public Health and Safety - 5 rating
Emergency planning applications such as card access, cameras, shooter detection
External Obligations - 3 rating
Cybersecurity mandates to keep equipment updated and secure
Fiscal Prudence - 5 rating
eRate funding usage paying for 1/2 of the cost
City Services - 5 rating
Whole SPS district upgraded to resilient infrastructure
Equity - 0 rating
Strategic Plans - 3 rating
Positioned to handle future strategic plans requiring technology
Approved By:____________________________________
Date:______________________