Matters ▸ Attachment
Committee Report - PUPW- 9-22-16 — File 202127
Public Utilities and Public Works Committee
Page 1 of 15
Printed 9/22/2016
September 21, 2016
REPORT OF THE PUBLIC UTILITIES AND PUBLIC WORKS COMMITTEE
Attendee Name
Title
Status
Arrived
Robert J. McWatters
Chair
Present
Tony Lafuente
Vice Chair
Present
Lance L. Davis
Ward Six Alderman
Present
Also in attendance: Alderman McLaughlin, Alderman Niedergang, Rick Willette - DPW, Stan
Koty - DPW, Tim Snyder - Mayor’s Office, Rositha Durham - Clerk of Committees.
The meeting took place in the Committee Room and was called to order at 6:30 PM by
Alderman McWatters and adjourned at 7:15 PM.
Approval of the March 15, 2016 Minutes
RESULT:
ACCEPTED
195521: That the Commissioner of Public Works and the Director of SPCD (ISD)
implement a plan to address trash and code violations each May and September, when
student moves have the greatest impact on the City.
RESULT:
KEPT IN COMMITTEE
195528: That this Board’s Committee on Public Utilities and Works explore Boston’s Code
Ordinance CBC 9-1.3, which requires private rental units to be registered on an annual
basis and inspections to be conducted for non-exempt units on a 5-year cycle.
RESULT:
KEPT IN COMMITTEE
196186: That the Commissioner of Public Works report to this Board whether it is possible
to have the Public Schools open when there is a declared snow emergency, and, if it is
possible, to also report the plan for teacher and staff parking, since school parking lots are
used then for resident parking.
Public Utilities and Public Works Committee
Page 2 of 15
Printed 9/22/2016
The question was asked if it is possible to have schools open during snow emergencies since
school lots are used for resident parking during those times. Mr. Koty spoke about road safety
and teachers who do not live in the area. Alderman Niedergang stated that several parents have
been asking him about this matter for approximately 10 years. It was asked if the city could
separate the school from the snow emergencies at the interest of the school. The school
superintendant is interested and will be working on this matter. Mr. Koty said that some may
think the snow emergency stays in effect longer than necessary, however, there are many
students who walk to school and the city must think about safety first. The city purchased 4
additional Bobcats last year that are used to help make the sidewalks safer. There is nothing
stated that the schools must be cancelled during snow emergencies. Mr. Snyder stated the city is
looking into what other protocols could be followed relative to snow emergencies and school
closings. There will be follow up conversations on this matter and the committee would like to
hear about other municipalities who may suggest that residents find other parking locations
during snow emergencies, to free up school parking lots. Chairman McWatters suggested
formulating a policy going forward with the school superintendant and DPW commissioner to
find alternative parking locations. Mr. Snyder will meet with the commissioner and
superintendant to publish the policy online. Mr. Koty pointed out that snow operations are
already posted on the city’s website, explaining why a snow emergency is handled in a certain
way. Everyone has access to this policy and it includes clearing walkways and crossing guard
stations.
RESULT:
KEPT IN COMMITTEE
196302: That the Commissioner of Public Works report to this Board on the performance
of the contractor who maintains the street lights, the terms of the contract and deliverables,
and the process to ensure that street lights are maintained and operable.
RESULT:
KEPT IN COMMITTEE
196378: That the Director of SPCD and/or the Commissioner of Public Works notify
property owners along lower Broadway of the five year moratorium on renovations to
private sewer systems and encourage them to make appropriate plans.
RESULT:
KEPT IN COMMITTEE
196608: That the Commissioner of Public Works notify the appropriate utility regarding
the double pole on Perkins Street.
RESULT:
KEPT IN COMMITTEE
196621: That the Commissioner of Public Works contact the appropriate utility and cable
vendors to address the low hanging wires on Allen Street.
Public Utilities and Public Works Committee
Page 3 of 15
Printed 9/22/2016
RESULT:
KEPT IN COMMITTEE
196770: That the Commissioner of Public Works contact the appropriate utility company
regarding the removal of double poles on Perkins Street, Glen Street, Cutter Street,
Kennison Avenue and Garfield Street.
RESULT:
KEPT IN COMMITTEE
196785: That the Commissioner of Public Works explain the policy regarding the height of
utility wires suspended from poles, and the protocols in place to ensure adherence to the
policy.
RESULT:
KEPT IN COMMITTEE
196913: That the Commissioner of Public Works clean the banks of the Mystic River along
Assembly Row and ensure that a regular cleaning schedule is put in place.
RESULT:
KEPT IN COMMITTEE
196970: That the Commissioner of Public Works contact the appropriate utility companies
to remove the double pole at the corner of Willow and Kidder Avenues.
RESULT:
KEPT IN COMMITTEE
196983: That the Administration dedicate certain public buildings for community use.
RESULT:
KEPT IN COMMITTEE
197233: That the Commissioner of Public Works direct Verizon to remove unused utility
boxes from the side lawn of the West Somerville Neighborhood School, and from the north
side of the grounds of the Powderhouse Community School.
RESULT:
KEPT IN COMMITTEE
197238: That the City Engineer review drainage on Shore Drive, especially with storm
water runoff during heavy rains, particularly at the corner of Shore Drive and Putnam
Street, as well as the impact of development at Assembly Square on the sewer outflow line.
RESULT:
KEPT IN COMMITTEE
197277: That the Commissioner of Public Works notify the appropriate utility companies
to remove the double pole on Cambria Street.
Public Utilities and Public Works Committee
Page 4 of 15
Printed 9/22/2016
RESULT:
KEPT IN COMMITTEE
197428: That the Commissioner of Public Works repair the depression in the roadway in
the east bound lane on Broadway just past its intersection with School Street.
RESULT:
KEPT IN COMMITTEE
197429: That the Commissioner of Public Works repair the depression in the roadway on
Mt. Pleasant Street, just after its intersection with Broadway.
RESULT:
KEPT IN COMMITTEE
197465: That the Commissioner of Public Works notify the appropriate utility company to
realign the utility pole in front of 47 Oliver Street.
RESULT:
KEPT IN COMMITTEE
197472: That the Commissioner of Public Works contact NStar about removing the double
pole at 72 Curtis Street. (2nd request.)
RESULT:
KEPT IN COMMITTEE
197489: That the Commissioner of Public Works report to this Board about how utilities
inform residents about work on their streets, utility poles or power lines.
RESULT:
KEPT IN COMMITTEE
197625: That NStar Electric report to this Board on its preparations to insure sufficient
power for the redevelopment of Union Square.
RESULT:
KEPT IN COMMITTEE
197694: That the Commissioner of Public Works assess the adequacy of street lighting
along Chester, Fitchburg and Poplar Streets, install additional lighting where needed and
repair street lights which are not working on those streets.
RESULT:
KEPT IN COMMITTEE
197724: That the Director of SPCD and the Commissioner of Public Works report to this
Board on the development, staffing and cost of a program to maintain street trees and keep
tree wells clean and weed-free, and/or a program to assist and inspire residents to do so.
Public Utilities and Public Works Committee
Page 5 of 15
Printed 9/22/2016
RESULT:
KEPT IN COMMITTEE
197756: That the Administration report to this Board on its plan to implement the Tree
Advisory Committee that is required by Ordinance 12-100, the Tree Preservation
Ordinance.
RESULT:
KEPT IN COMMITTEE
197773: That the Commissioner of Public Works devise a strategy to address instances of
low hanging utility/cable wires throughout Somerville.
RESULT:
KEPT IN COMMITTEE
197917: That the Commissioner of Public Works direct all utility companies to clean up
their lines throughout the city.
RESULT:
KEPT IN COMMITTEE
198088: That the Commissioner of Public Works investigate and report back on installing
solar powered kiosks in our parks and playgrounds to communicate youth and family
activities in our city.
RESULT:
KEPT IN COMMITTEE
198109: That the Commissioner of Public Works notify the appropriate utility company to
remove the double pole in front of 46 Elmwood Street.
RESULT:
KEPT IN COMMITTEE
198213: That the Commissioner of Public Works remove the rotting 10 foot high tree base
that is being used to anchor a telephone pole in front of 11 Barton Street.
RESULT:
KEPT IN COMMITTEE
198386: That the Commissioner of Public Works update the Ward 5 Alderman on repairs
to prevent pedestrians from tripping in the crosswalks at Linden Avenue on the south side
of Summer Street, Aberdeen Road by Highland Avenue, and Hall Street by Cherry Street.
RESULT:
KEPT IN COMMITTEE
198444: That the Director of SPCD (ISD) report to this Board on the process for issuing
citations during snowstorms to private plowing and shoveling contractors who are plowing
Public Utilities and Public Works Committee
Page 6 of 15
Printed 9/22/2016
snow into the street or onto neighbors' sidewalks.
RESULT:
KEPT IN COMMITTEE
199295: That the Director of SPCD discuss capitalizing on street repaving to bury utilities,
beautify the city, and reduce the threat of power outages due to rain/snow/ice storms.
RESULT:
KEPT IN COMMITTEE
199369: That the Commissioner of Public Works immediately assess the stability of the
listing utility pole at 6 Windsor Road and act expeditiously to remediate the double pole.
RESULT:
KEPT IN COMMITTEE
199547: That the Commissioner of Public Works and the Director of SPCD work with
Eversource to remove the unsafe telephone poles secured to rotting trees on Woods Street
at North Street, and on Barton Street at Broadway.
RESULT:
KEPT IN COMMITTEE
199869: That the Administration inform the Clark Street neighbors about the TV pipe
testing which should have been performed in 2014.
RESULT:
KEPT IN COMMITTEE
199955: That the Director of SPCD (Transportation) consider installing a bollard at the top
of the stairs at the Community Path Extension by Lowell Street, to prevent people from
accidentally tumbling down the stairs.
RESULT:
KEPT IN COMMITTEE
199956: That the Commissioner of Public Works determine if the lighting at the
Community Path Extension ramp and stairs by the Lowell Street bridge is sufficient, and if
not, install more.
RESULT:
KEPT IN COMMITTEE
200136: That the Commissioner of Public Works fix the broken pedestrian warning signal
for the exit from the Magoun Square CVS onto Medford Street.
RESULT:
KEPT IN COMMITTEE
200149: That the Commissioner of Public Works plant grass in front of the East Branch
Public Utilities and Public Works Committee
Page 7 of 15
Printed 9/22/2016
Library.
RESULT:
KEPT IN COMMITTEE
200150: That the Commissioner of Public Works repair the broken street lights on
Broadway, from Fellsway West to Grant Street.
RESULT:
KEPT IN COMMITTEE
200151: That the Commissioner of Public Works repair the broken street lights at 10
Wheatland Street.
RESULT:
KEPT IN COMMITTEE
200223: That the Commissioner of Public Works create clearly defined lines along Walnut
Street, by Pearl Street and Broadway, to eliminate two lane traffic problems.
RESULT:
KEPT IN COMMITTEE
200266: That the Commissioner of Public Works repaint the faded NO CYCLING markers
on sidewalks and install NO BIKE RIDING – PLEASE WALK YOUR BIKE signs in
central business districts.
RESULT:
KEPT IN COMMITTEE
200276: That the Commissioner of Public Works repair the clock in the Argenziano School
cafeteria which has been broken for the last 5 years.
RESULT:
KEPT IN COMMITTEE
200440: That the Director of Constituent Services appear before this Board’s Committee
on Public Utilities and Works with a written report on streetlamp repairs citywide.
RESULT:
KEPT IN COMMITTEE
200528: That the Commissioner of Public Works provide this Board with a timeline for
repair of the backstop behind the large baseball diamond at Trum Field, by Broadway and
Charles E. Ryan Road.
RESULT:
KEPT IN COMMITTEE
200529: That the Commissioner of Public Works make needed repairs to Trum Field in
time for the spring baseball season.
Public Utilities and Public Works Committee
Page 8 of 15
Printed 9/22/2016
RESULT:
KEPT IN COMMITTEE
200637: That the Director of SPCD provide all Ward Aldermen with the 2016 street paving
plan for all Wards.
RESULT:
KEPT IN COMMITTEE
200645: That the Commissioner of Public Works explain to this Board how to find out
when a particular street is scheduled to be re-paved.
RESULT:
KEPT IN COMMITTEE
200680: That the Commissioner of Public Works appear before the Committee on Public
Utilities and Works to address the assistance the City can provide for a city tree root that is
growing into the basement of the home at 25 Meacham Street.
RESULT:
KEPT IN COMMITTEE
200695: That the Director of Capital Projects and the Disability Coordinator appear before
the Committee on Public Utilities and Works to discuss ADA issues and construction
defects at the East Somerville Community School.
RESULT:
WORK COMPLETED
200747: That the Commissioner of Public Works consider using pet safe salt on city
walkways.
RESULT:
KEPT IN COMMITTEE
200748: That the Commissioner of Public Works address the icing on Assembly Row
sidewalks.
RESULT:
KEPT IN COMMITTEE
200772: That the Commissioner of Public Works consider installing cigarette butt disposal
boxes in public areas citywide.
RESULT:
KEPT IN COMMITTEE
200773: That the Commissioner of Public Works describe to this Board, the rationale for
treating multi-unit residences the same as single family residences for purposes of volume-
based escalation of water rates.
Public Utilities and Public Works Committee
Page 9 of 15
Printed 9/22/2016
RESULT:
KEPT IN COMMITTEE
200874: That the Director of Capital Projects advise the Ward 7 Alderman of the start date
and schedule for sewer/relining on Powderhouse Blvd.
RESULT:
KEPT IN COMMITTEE
200882: That the Commissioner of Public Works and the Supervisor of Inspectional
Services report to this Board on the repair of the sidewalk that is collapsing on Vernon
Street, and what precautions are being taken for public safety.
RESULT:
KEPT IN COMMITTEE
201007: That the Commissioner of Public Works and the Director of SPCD consider
replacing the unused concrete bus shelter at Broadway and Cedar Street with a garden,
small park or sitting area, and report back by 5/12/16.
Alderman Niedergang requested that someone look at this unused bus shelter and come up with a
plan for cleaning or updating it. The administration will look into the matter.
RESULT:
KEPT IN COMMITTEE
201010: That the Commissioner of Public Works replace the decorative lamppost that is
missing from the stump at Old Magoun’s Saloon in Magoun Square. (2nd request)
RESULT:
KEPT IN COMMITTEE
201011: That the Commissioner of Public Works replace the 3 missing yellow bollards on
the east side of the Lowell Street bridge at the Community Path Extension ramp. (2nd
request)
RESULT:
KEPT IN COMMITTEE
201012: That the Director of SPCD install pigeon spikes underneath the Lowell Street
bridge, above the Community Path Extension. (4th request)
RESULT:
KEPT IN COMMITTEE
201133: That the Commissioner of Public Works contact the appropriate utility to address
the low hanging wire on Lincoln Avenue.
RESULT:
KEPT IN COMMITTEE
Public Utilities and Public Works Committee
Page 10 of 15
Printed 9/22/2016
201144: That the Commissioner of Public Works repair the disintegrating sidewalk at the
entrance to the parking lot on Central Street used by the Cambridge Health Alliance, or
require them to fix it if it is their responsibility.
RESULT:
KEPT IN COMMITTEE
201270: That the Commissioner of Public Works inform this Board of the options to adjust
new LED street lighting, and the process to request such adjustments.
RESULT:
KEPT IN COMMITTEE
201303: That the Director of Engineering and/or the Supervisor of Inspectional Services
provide address numbers to the properties on Chestnut Street and notify the property
owners to display them on their buildings to facilitate identifying them.
RESULT:
KEPT IN COMMITTEE
201319: That the Commissioner of Public Works remove trash from the north side of the
Cambridge Health Alliance parking lot off Central Street and behind Junction Park, and
post NO DUMPING signs there.
RESULT:
KEPT IN COMMITTEE
201423: That the Commissioner of Public Works address the leaning utility pole at the East
Somerville Community School on Glen Street.
RESULT:
KEPT IN COMMITTEE
201473: That the Commissioner of Public Works and/or the City Solicitor report to this
Board on efforts to make the Albion Street sidewalk contractor repair the sidewalks or
refund the City, and that the Commissioner of Public Works have the sidewalks repaired
and report to this Board on when that will happen.
RESULT:
KEPT IN COMMITTEE
201499: That the Commissioner of Public Works clean the Community Path between
Cedar and Lowell Streets, and consider erecting a barrier to prevent erosion from the hill
alongside the path.
RESULT:
KEPT IN COMMITTEE
201504: That the Commissioner of Public Works consider installing an additional street
lamp near 27, 31 and 33 Winslow Avenue.
Public Utilities and Public Works Committee
Page 11 of 15
Printed 9/22/2016
RESULT:
KEPT IN COMMITTEE
201586: That the Director of SPCD and the Commissioner of Public Works consider
creating shade at Grimmons Park and designing future parks with appropriate shade as
well.
RESULT:
KEPT IN COMMITTEE
201612: That the Commissioner of Public Works trim all foliage blocking memorial
dedication signs, traffic signals, and parking regulation signs.
RESULT:
KEPT IN COMMITTEE
201618: That the Director of Engineering explain to this Board how to find out when a
particular street is scheduled to be re-paved, or provide the city’s street paving list. (3rd
request)
RESULT:
KEPT IN COMMITTEE
201691: That the Commissioner of Public Works evaluate the low-hanging lines (from
multiple poles) behind 52 Powder House Blvd.
RESULT:
KEPT IN COMMITTEE
201712: That the Commissioner of Public Works repair the brick walkway between
Holland Street and College Avenue in Davis Square Plaza.
RESULT:
KEPT IN COMMITTEE
201713: That the Commissioner of Public Works inspect the damaged wall at 93 Pearson
Road and take action to remedy the situation.
RESULT:
KEPT IN COMMITTEE
201701: That the Commissioner of Public Works replace the 3 raised sidewalk panels at 61
Dartmouth Street. (2nd request)
RESULT:
KEPT IN COMMITTEE
201767: That the Superintendent of Inspectional Services direct Healey School staff to keep
the grounds clean and properly dispose of trash, due to increased rodent activity around
the school.
Public Utilities and Public Works Committee
Page 12 of 15
Printed 9/22/2016
RESULT:
KEPT IN COMMITTEE
201771: That the Commissioner of Public Works remove all brush from the Mystic River
along Shore Drive.
RESULT:
KEPT IN COMMITTEE
201778: That the Commissioner of Public Works direct Eversource to immediately remove
the heavy plant overgrowth at the transfer station at Willow Avenue and Whipple Street.
RESULT:
KEPT IN COMMITTEE
201795: That the Commissioner of Public Works clean the Sacramento Street ramp that
runs beneath the railroad tracks and confirm the regular maintenance schedule previously
agreed to.
RESULT:
KEPT IN COMMITTEE
201797: That the Director of Engineering add Porter Street, between Summer and Elm
Streets, to the 5-year paving plan, and include the streets off the west side of Porter Street,
especially Carver Street.
RESULT:
KEPT IN COMMITTEE
201826: That the Commissioner of Public Works replace the black hot topped sidewalk at
985-987 Broadway with concrete and explain why Eversource claims they are not allowed
to use concrete when replacing an opened sidewalk.
RESULT:
KEPT IN COMMITTEE
201830: That the Commissioner of Public Works cut down the rotting 12 foot stump at 7
Barton Street.
RESULT:
KEPT IN COMMITTEE
201906: That the Commissioner of Public Works direct the contractor who recently did
work on Porter Street to repair and resurface the sink hole that is beginning to develop on
Summer and Porter Streets.
RESULT:
KEPT IN COMMITTEE
201908: That the Commissioner of Public Works replace the sidewalk panels from
Public Utilities and Public Works Committee
Page 13 of 15
Printed 9/22/2016
Properzi Manner to Bow Street as they have become a public safety hazard.
RESULT:
KEPT IN COMMITTEE
202029: That the Director of SPCD, the Director of Capital Planning, and the City
Engineer create a timeline from September 2016 to September 2019 for streetscape
reconstruction projects in Ward 2 and post the timeline on the city’s website with continual
updates as changes occur.
RESULT:
KEPT IN COMMITTEE
202032: That the City Engineer and the Director of SPCD report back to the Ward 2
Alderman on repairing the sidewalk on the Dane Street bridge and the wooden slats on the
Webster Avenue/Newton Street Bridge, and on communications with the responsible State
agencies.
RESULT:
KEPT IN COMMITTEE
202034: That the Director of SPCD add Avon Street to the paving list.
RESULT:
KEPT IN COMMITTEE
202082: That the Commissioner of Public Works, the Superintendent of Inspectional
Services and the City Engineer report to this Board, the process for obtaining permission
for a curb cut, including provisions made to ensure that the city’s ordinances are followed.
RESULT:
KEPT IN COMMITTEE
202096: That the Commissioner of Public Works and the Chief of Police report to this
Board whether their departments bring claims against, or cite, motorists who damage city
trees.
Resident Eileen Schofield was in attendance regarding the damaged trees. It was stated that if
there is a police report, then the tree would be replaced. Alderman McLaughlin spoke about 2 or
3 other incidents involving damaged trees. Chairman McWatters asked the Administration to
look into dump trucks that are going down streets before 7:00 AM and after 7:00 PM. Alderman
Lafuente asked that the Administration have the police send an email to the members of the
committee regarding incidents involving trees and to include any follow up on this matter.
RESULT:
WORK COMPLETED
200192: DPW Commissioner responding to various Board Orders submitted 9/24/15.
Public Utilities and Public Works Committee
Page 14 of 15
Printed 9/22/2016
RESULT:
KEPT IN COMMITTEE
200560: Traffic and Parking Director submitting responses to various Board Orders
submitted 11/24/15.
RESULT:
KEPT IN COMMITTEE
200759: DPW Commissioner responding to various Board Orders submitted 1/14/16.
RESULT:
KEPT IN COMMITTEE
200760: DPW Commissioner responding to various Board Orders submitted 1/28/16.
RESULT:
KEPT IN COMMITTEE
200853: DPW Commissioner responding to various Board Orders submitted 2/11/16 and
2/25/16.
RESULT:
KEPT IN COMMITTEE
200989: DPW Commissioner responding to various Board Orders submitted 3/10/16.
RESULT:
KEPT IN COMMITTEE
201198: DPW Commissioner responding to various Board Orders submitted 3/24/16.
RESULT:
KEPT IN COMMITTEE
201345: DPW Commissioner responding to various Board Orders submitted 4/14/16.
RESULT:
KEPT IN COMMITTEE
201445: DPW Commissioner responding to various Board Orders submitted 4/28/16.
RESULT:
KEPT IN COMMITTEE
201571: DPW Commissioner responding to various Board Orders submitted 5/12/16.
RESULT:
KEPT IN COMMITTEE
201572: DPW Commissioner responding to supplemental Board Orders submitted 5/12/16.
Public Utilities and Public Works Committee
Page 15 of 15
Printed 9/22/2016
RESULT:
KEPT IN COMMITTEE
201573: DPW Commissioner responding to various Board Orders submitted this evening.
RESULT:
KEPT IN COMMITTEE
201750: DPW Commissioner responding to various Board Orders submitted 6/9/16.
RESULT:
KEPT IN COMMITTEE
201815: DPW Commissioner responding to various Board Orders submitted 6/23/16.
RESULT:
KEPT IN COMMITTEE