Committee Report - PUPW - 10-24-17 — File 204495
Public Utilities and Public Works Committee
Page 1 of 4
Printed 10/26/2017
October 24, 2017
REPORT OF THE PUBLIC UTILITIES AND PUBLIC WORKS COMMITTEE
Attendee Name
Title
Status
Arrived
Robert J. McWatters
Chair
Present
Tony Lafuente
Vice Chair
Absent
Lance L. Davis
Ward Six Alderman
Late
Maryann M. Heuston
Ward Two Alderman
Present
Mary Jo Rossetti
Alderman at Large
Present
Others present: Alderman William White, Alderman Dennis Sullivan, Stan Koty - DPW, Jackie
Rossetti - Communications, Brad Rawson - OSPCD, Rich Raiche - Engineering, Paul Maloy -
MassDOT, Paul Stedman - MassDOT, Rositha Durham - Clerk of Committees.
The meeting took place in the Committee Room and was called to order at 6:30 PM and
adjourned at 7:50 PM.
President White appointed Aldermen Heuston and Rossetti to the committee for this meeting only, to
effectuate a quorum.
Approval of the April 5, 2017 Minutes
RESULT:
ACCEPTED
204263: That the Commissioner of Public Works request that the appropriate utility
company address the low hanging wires on Mt. Vernon and Washington Streets.
Mr. Koty informed the committee that letters were sent to the utility company and that the city
has not yet received a response. Mr. Koty will request that representatives from that utility
company appear before the committee.
RESULT:
KEPT IN COMMITTEE
203983: That the Mayor report to this Board by August 31, 2017 on ways to improve the
poor communications from Eversource to residents around gas meter replacement, street
construction, and other utility work. (2nd request)
Public Utilities and Public Works Committee
Page 2 of 4
Printed 10/26/2017
RESULT:
KEPT IN COMMITTEE
204361: That MA DOT, Newport Construction and all other parties with knowledge of the
cutting down of trees on Beacon Street on October 6, without any public notice, appear
before this Board at its next regular meeting to respond to concerns about the surprise tree
removal.
Mr. Rawson, Mr. Maloy and Mr. Stedman addressed this item. Members questioned what the
city knew about the cutting down of the trees. Members were told that there was a signed
contract that gave the contractor authorization to remove the trees.
The committee was told that 17 trees were removed in May and one tree was removed in
October and one in November due to unforeseen circumstances. MassDOT representatives said
that they walked the site with the tree warden to review the plans of the work to be done. The
utility work took place on Washington Street (to Cambridge) and was wrapped up a little quicker
than expected. Newport Construction came to MassDOT requesting to get started on the next
phase of the project. There were bi-weekly construction meetings and the message was to delay
and defer work until the spring of 2018. At a later date, Newport provided a 3-week look ahead
schedule showing no tree work and no work in the southern area of Somerville.
Alderman Davis inquired about the meeting on September 20th when the decision was made not
to go forward with the project and asked Mr. Rawson what would have been the communication
plan if the trees were to be removed. Mr. Rawson replied that there would have been community
engagement, including emails blasts, from January through March. Alderman Davis also asked
at what point was Northern Tree informed about the revised schedule to remove the trees and he
asked for a document to provide greater details on who told Northern to take down the trees.
MassDOT representatives said they will confirm whether Newport Construction gave Northern
the approval to remove the trees. MassDOT said that Newport reached out to them and they
followed up with the city regarding the work. The September 20th meeting was not a scheduled
bi-weekly meeting, (when minutes are usually taken by DCR), adding that there was a
breakdown in communication with the contractor.
Alderman Heuston mentioned pieces of wood with nails protruding from them that were left out
by the contractor on the northern side of Somerville. She went on to say that streets were not
swept, dirt blows into peoples’ windows, there's no signage saying where to cross the street,
people had to walk in the street and bike lanes and there is no safe passage for people and baby
carriages. Alderman Heuston said that the city needs to hire someone to oversee the Beacon
Street project, noting that she originally made this request at a Planning Board meeting. Mr.
Rawson said that city staff are at construction sites constantly. She also mentioned the loophole
(re: notification) in the tree ordinance, that was discussed in the Legislative Matters Committee
meeting and asked if closing the loophole would apply to MassDOT projects. Alderman
Heuston stated her concern with the lack of notifications on the street about the project and the
holding of parking spaces for the project’s trucks and commented on the communications from
the Administration that MassDOT and the Administration are reviewing recourse options
regarding the trees and that the Administration would work with the BOA to enhance the tree
Public Utilities and Public Works Committee
Page 3 of 4
Printed 10/26/2017
ordinance.
Chairman McWatters stated that not having a police detail on the project was a failure on
everyone's part and he asked if the contractor will be allowed to continue with this project.
MassDOT representatives said the removal of the trees wasn’t supposed to happen until the
spring and that the contractor didn’t violate any laws. MassDOT said that Newport forgot to call
off the contractor after the September 20th meeting and the MassDOT resident engineer had no
idea the trees were being removed. Phone calls started coming in from the city on Thursday and
on Friday, MassDOT shut down the contractor.
Alderman Heuston asked Mr. Rawson to provide an accounting of the trees scheduled to be
removed in 2014 and 2015. Alderman White would like the Administration review the plans to
see how they changed and how many trees were scheduled to be removed. Both Aldermen
White and Heuston asked about the difference of the 75% plan and 100% plan, who was alerted
to the change and what was the rational of the change of plans. There was also a discussion
about trees being preserved, raising a question about when that changed.
Resident Adam Pordereny asked if the trees were going to be removed anyway and if the city
knew that they were being removed. He raised a question about the tree stumps and their
removal pointing out that they could create a dangerous situation should they become covered
with snow. Resident Tori Antonio asked about the tree replacement fund and how much would
go into that fund.
MassDOT said there are 198 replacement trees scheduled as part of the project.
RESULT:
KEPT IN COMMITTEE
204362: That the Director of SPCD work with Mass DOT to cease all work on the Beacon
Street reconstruction project until a full report on the removal of trees from the street is
received and presented to this Board and until city staff is assigned day to day
responsibility for oversight.
RESULT:
KEPT IN COMMITTEE
204363: The Administration assign or hire city staff to oversee the daily operations of
contractor and utility company activity for the Beacon Street reconstruction project, and
adopt a policy of such oversight for every state funded street reconstruction project going
forward.
The committee would like to hear from the Administration on their plans to handle future
projects.
RESULT:
KEPT IN COMMITTEE
204365: That the Director of SPCD estimate for this Board the cost to move overhead wires
Public Utilities and Public Works Committee
Page 4 of 4
Printed 10/26/2017
underground on Beacon Street from Washington to Hampshire Streets, identify potential
funding sources, and discuss the feasibility and impact of such an endeavor on the current
Beacon Street project.
Alderman Heuston requested this estimate and said that it should have been considered as part of
the Beacon Street project. The original request came from a resident and Alderman Heuston
believes that other residents will want the information, as well.
RESULT:
KEPT IN COMMITTEE
203413: DPW Commissioner responding to various Board Orders submitted 4/27/17.
RESULT:
WORK COMPLETED
203813: DPW Commissioner responding to various Board Orders submitted 5/25/17.
RESULT:
WORK COMPLETED
204188: DPW Commissioner responding to various Board Orders submitted 7/13/17.
RESULT:
WORK COMPLETED
204288: DPW Commissioner responding to various Board Orders submitted 8/24/17.
RESULT:
WORK COMPLETED
204335: DPW Commissioner responding to various Board Orders submitted 9/28/17.
RESULT:
WORK COMPLETED
204423: Chris Dwan submitting comments re: the October 6 Beacon Street tree removal.
RESULT:
WORK COMPLETED
204445: City Engineer submitting responding to #203496 re: Pitman Street pavement.
RESULT:
WORK COMPLETED
Handout:
•
Tree removal summary - (with 204361)