Matters ▸ Attachment
Grace Baptist CPC Funding Recommendation — File 207286
COMMUNITY PRESERVATION COMMITTEE FY19 FUNDING RECOMMENDATION FOR
GRACE BAPTIST CHURCH, SOMERVILLE HISPANIC ASSOCIATION FOR COMMUNITY DEVELOPMENT
PROJECT DESCRIPTION
The Somerville Hispanic Association for Community Development will repair the existing slate roof
surfaces and related flashing and brick masonry. SHA4CD will also create a new accessible ramp from
the sidewalk to the building.
ELIGIBILITY
Historic resources: The Somerville Hispanic Association for Community Development operates out of the
historic Grace Baptist Church, a local historic district.
RECOMMENDED FUNDING
On December 11, 2018 by a vote of 6-0 the Community Preservation Committee recommended
appropriating $500,000 for this project, $184,215 from the historic resources reserve budget and
$315,785 from the budgeted reserve, to the control of the Somerville Hispanic Association for
Community Development for the overall purposes summarized in this document.
Project Budget
Expenses
Amount
Study
$0
Soft costs
$83,100
Construction
$554,000
Total $637,100
Sources
CPA historic resources funds- requested
$637,100
Other sources
$0
Total $637,100
JOSEPH A. CURTATONE
MAYOR
CITY OF SOMERVILLE, MASSACHUSETTS
COMMUNITY PRESERVATION COMMITTEE
ALIGNMENT WITH FY19 COMMUNITY PRESERVATION PLAN
The Grace Baptist Church building is home to the SHA4CD food pantry, a bilingual day care that accepts
vouchers, and a family homeless shelter. SHA4CD received a $50,000 grant from the Massachusetts
Historic Commission during the first phase of the project and is seeking a second grant for the second
phase.
FUNDING CONDITIONS
1. Execution and recording of a perpetual historic preservation restriction that would be held by
the Somerville Historic Preservation Commission.
2. The Somerville Hispanic Association for Community Development will post a permanent sign
noting CPA funding for the restoration of the Grace Baptist Church building.
MEASURES OF SUCCESS
The goals of the project are to:
1. Repair the roofing slate and associated flashing to keep water from damaging the structure and
finishes within the building
2. Provide full accessibility to all major areas of the building (long term goal)
Achievement of these goals will be measured through:
1. Properly installed new roof and flashing systems
2. New accessible sidewalk
The full proposal is available at: https://www.somervillema.gov/departments/community-
preservation-act/2019-cpa-projects