Appendix D - Proposed Public Safety Building and Fire Department (Engine 3) β File 207344
90 Washington Street
July 10, 2018
Proposed Public Safety Building
and Fire Department (Engine 3)
1. Introduction: Rob King
2. Space needs assessment: Weston & Sampson
3. Site selection: Weston & Sampson
4. Site acquisition: Eileen McGettigan & Tom
Galligani
5. Finances: Rob King
6. Next steps: Rob King
Agenda
1. Introduction
β Inadequate space for current and future needs
β Inadequate space for police vehicles on the site
β Inefficient adjacencies
β Severe flooding potential:
β’ police and fire vehicles
β’ building generator
β’ flooding led to the relocation of Engine 3
β Inefficient building envelope
β Inadequate parking
β Scheduling and security conflicts
The Need (Existing Challenges):
The Need (Existing Challenges):
The Need (Existing Challenges):
The Need (Existing Challenges):
The Need (Existing Challenges):
The Need (Existing Challenges):
The Need (Existing Challenges):
The Need (Existing Challenges):
The Need (Existing Challenges):
The Need (Existing Challenges):
2. SPACE NEEDS
ASSESSMENT
Programming Process:
1. Documented existing facility to
quantify existing program and
identify deficiencies
2. Conducted staff interviews to
identify current and future needs
3. Developed room programming
sketches
4. Assembled comprehensive space
needs assessment
Space needs assessment
Office and office support
Detention facilities
Training / shared community space
Police
Size (SF)
Public / Community Access
12,200
Police Administration
7,900
Staff Support / Training
14,500
Police Operations
19,800
Detention / Detention Support
8,800
Vehicle Storage / Maintenance
14,800
Subtotal Police:
78,000
Fire Department Engine 3
6,500
Total Building Program:
84,500
Space needs assessment
Programming Process:
1. Utilizing the space needs assessment, developed
generic conceptual site layouts to define the
minimum building footprint for site selection
2. Reviewed 3-story and 4-story schemes
3. Identified minimum building footprint range of
18,000 to 30,000 square feet (varies based on
number of stories)
Space needs assessment
3. SITE SELECTION
1.
City developed an initial list of potential sites
2. Conducted an initial site screening:
β’
Size
β’
Allowable development size
β’
Ownership
β’
Zoning
β’
Permitting challenges
β’
Environmental restrictions
3.
Identified six (6) potential sites capable of meeting
basic programming and site requirements
4. Developed a detailed site selection matrix to rank
the sites
Site selection
Conducted a detailed site selection analysis based on criteria
developed in coordination with the City:
Site selection
β’ Cost of Development (20 points)
β’ Location (15 points)
β’ Physical Features (15 points)
β’ Zoning Consistency (10 points)
β’ Environmental Impacts (10 points)
β’ Infrastructure (5 points)
β’ Permitting (5 points)
β’ Traffic Impacts (5 points)
Estimated to be
Most Critical
Estimated to be
Less Critical
Evaluated and ranked each site
Site selection
Evaluated and ranked each site
Site selection
Final Site Rankings:
Rank Site No. / Address
Percent Score (raw score)
1
Site 6 (90 Washington Street)
74% (63 out of 85)
2
Site 2 (17 McGrath Hwy)
68% (58 out of 85)
3
Site 3 (185 Somerville Ave)
67% (57 out of 85)
4
Site 4 (501 Mystic Valley Pkwy) 66% (56 out of 85)
5
Site 5 (526 Somerville Ave)
61% (52 out of 85)
6
Site 1 (17 Inner Belt Rd)
59% (50 out of 85)
Recommended Location:
β’ Site is of adequate size.
β’ Site can accommodate
Engine 3.
β’ Engine 3 response times
would provide 92% less
than 5 minutes.
β’ Good orientation for
visibility and connection
to Washington Street.
90 Washington Street Benefits:
4. SITE ACQUISITION
Recommended Location:
90 Washington
Capuano School
Future T Station
Cobble Hill Apartments
Site Boundaries
Aerial Image
Site Photos
Site Photos
Eminent domain
β’ Enabled by MGL c. 40 Section 14
β Allowed by 2/3 vote of Board of Aldermen
β Required appropriation of funding
β Must be for a public purpose
β Cannot pay more than 125% of the average of the last
three yearsβ assessed value
Municipal property acquisition process
β’ Process regulated by MGL C. 79
β Conduct appraisal
β BOA vote to appropriate and take
β Record Order of Taking within 30 days of vote
β Notice of taking to owner
β Pay Pro Tanto within 60 days of recording
Eminent Domain Process
β’ Date of appraisal: March 15, 2018
β’ Completed by Mark S. Reenstierna
of T.H. Reenstierna, LLC
β’ MA Certified General Real Estate Appraiser #3803
Appraisal
5. FINANCES
β’ Two items currently held in the FY18-FY27 Capital
Investment Plan (CIP) Project List:
β Acquisition of 90 Washington St.: $8.745 million
β’ Added as a Critical Project to the June 2018 CIP
β Construction of new public safety building
β’ Has been included as a Critical Project since the
creation of the CIP Project List in November 2016
β’ CIP estimate for construction: $36 million (costs will
escalate)
Current funding request:
6. Next Steps
1. Order of Taking for 90 Washington St. (Agenda
Item 206003)
2. $8.745 million bond authorization & appropriation
request to purchase 90 Washington St. (Agenda
Item 206004)
3. $1.86 million bond authorization & appropriation
request for Owners Project Manager (OPM) &
project management services for new public safety
building (Agenda Item 206005)
Items currently before the BOA
Procure Ownerβs
Project Manager
Services
Form Building
Committee
Procure Design
Services
Design/Development
Construction
Procurement
Construction
If BOA approves items, next steps are . . .
Timeline:
β’ Design estimated to take one year.
β’ Construction estimated to take 18-24 months.