Outline
2
A. Project Background
B. A Little About UCH-TIF
C. Documents Being Discussed Tonight
A. Project Background
3
A.1. Project Background: Project Site
4
Vacant Since 2007
A.2. Project Background: Winter Hill Neighborhood Plan (2016)
5
299 Broadway a/k/a Temple Square has been imagined as a redevelopment site with 200+ units of housing,
at least 20% of those affordable, and additional green space since the 2016 Winter Hill Neighborhood Plan
2016 Concept Plan for
redeveloping
βTemple Squareβ
A.3. Project Background: Winter Hill Urban Renewal Plan (2020)
6
2020 Concept Plan for redevelopment of βTemple Squareβ
from the Winter Hill Urban Renewal Plan carried the same concepts forward with small changes
A.4. Project Background: Developing Partnerships
7
Spring 2021
β
Winter Hill Urban
Renewal Plan is
approved by City Council
β
Property owner for the
Star Market grants
development option to
Mark Development
2021: Moved ahead with
fulfilling Community
Involvement goals
β
2 preliminary community
meetings with Mark
Development
β
3 permitting
neighborhood meetings
with Mark Development
β
Setting up a Civic
Advisory Committee for
ongoing local feedback
A.5. Project Background: Developing Partnerships Continued
8
!
Mid-stage environmental study
of the site revealed asbestos
contamination that prevents
underground parking
Option 1
Build above
ground
parking
garage
Option 2
Build a
highrise
Option 3
Build more
affordable
housing
Financeable options β¦
Spring 2022 - Mark Development
brings in Beacon Communities, a
specialist in affordable housing
development as a project partner
A.6. Project Background: Current Site Plan
9
2022 Site Plan
submitted to the ZBA
maintains key site
layout goals
β
288 Units
β
132 Affordable Units
β’
17 units @ 80% AMI
β’
99 units @ 60% AMI
β’
16 units @ 30% AMI
β
Community green space
β
Pedestrian right-of-way
through center
Current Submitted
Proposal
$22.8M Acquisition
~ 300 Units
~ 50% Affordable
0.0 spaces/unit
$13M - $20M Deficit
Revised Mark/Beacon
Proposal
$22.8M Acquisition
~ 300 Units
~ 40% Affordable
0.0 spaces/unit
No Deficit
Original Mark Development
Proposal
$22.8M Acquisition
~ 300 Units
~ 20% Affordable
0.5 spaces/unit
$18M Deficit
A.7. Project Background: Evolution of Project Proposals
10
A.8. Project Background: Current Financial Gap
11
Rising Construction Costs &
Increased Interest Rates:
Costs Associated with
Increased Affordability:
$9M - $16M
$4M
Total Estimated Deficit:
$13M - $ 20M
Estimated Cost Escalation
B. A little about
Urban Center Housing β Tax Increment Financing
(UCH-TIF)
12
B. About UCH-TIF
A statutory program operated by the Department of Housing & Community Development (DHCD) that
authorizes cities and towns to promote housing and commercial development through real estate tax
exemptions on all or part of the increased value of improved real estate for up to 20 years.
13
UCH-TIF Requires:
β
The area of benefits to be a primarily
commercial district
β
New development to be primarily
residential
β
New units to satisfy certain affordability
thresholds
β
15% at or below 80% AMI; or
β
25% at or below 110% AMI; or
β
Meet existing inclusionary zoning
requirements
B. About UCH-TIF
β
A financing tool to help close the gap in
affordable projects struggling to get
underway due to rising interest rates and
escalated construction costs
β
An opportunity to redevelop the
decadent Temple Square site; and
β
Meet the goals of the Winter Hill
Neighborhood Plan and Urban Renewal Plan
β
Restore Winter Hill as a main street
destination
β
Create significant affordable housing
opportunities and new jobs
β
Increase future tax revenue
14
Temple Square
C. Documents Being Discussed Tonight
15
C. Documents Being Discussed Tonight
1.
Draft UCH-TIF Zone and Plan
2.
The draft negotiated Agreement to
be signed between the City of
Somerville and 299 Broadway
Property Owner LLC
3.
Memo from Abramson & Associates
16
C. Documents Being Discussed Tonight
17
Appendix A: Draft Zone and Plan
β’
First 30 pages are the draft zone and
plan
β’
Following 300+ pages are appendices
Key Elements:
Zone β which properties can receive tax
increment financing
Plan β explains the goals for applying this
financing tool to this area
Form of Agreement β a template agreement
that could be used to start discussion
on any property in the zone
Appendix A: Draft Zone and Plan
β’
First 30 pages are the draft zone and
plan
β’
Following 300+ pages are appendices
Key Elements:
Zone β which properties can receive tax
increment financing
Plan β explains the goals for applying this
financing tool to this area
Form of Agreement β a template agreement
that could be used to start discussion
on any property in the zone
C. Documents Being Discussed Tonight
18
Appendix B: Draft Negotiated Agreement
Agreement between City of Somerville and 299
Broadway Property Owner LLC
Parties Involved:
β’
299 Broadway Property Owner LLC
β’
Mark Development
β’
Beacon Communities w/ minority stake partner Rise Together
β’
City of Somerville
β’
Department of Housing and Community Development
C. Documents Being Discussed Tonight
19
Appendix B: Draft Negotiated Agreement
Terms of the Tax Exemption (Section 6)
β’
100% exemption on the increment for 20 years
β’
Construction cannot commence for either building until
Low Income Housing Tax Credit funds are secured
β’
Starting point for the 20 years is when the first building
reaches 92% occupancy, and the second building has
a vertical building permit
β’
Requirement to review these terms again before the
first building receives a building permit
C. Documents Being Discussed Tonight
20
Appendix B: Draft Negotiated Agreement
Revisiting the exemption percentage and period
(Section 6.4)
β’
Prior to the first building receiving a vertical building
permit, the UCH-TIF must be reviewed again with the City
Council
β’ Confirm that 100% for 20 years is still
appropriate OR revise the terms
City will retain consultants once again to review the
development teamβs numbers and look for reasonableness &
work with the City Council on priorities if terms are revised
C. Documents Being Discussed Tonight
21
Appendix C: Memo from Abramson & Associates
Abramson & Associates, at the direction of OSPCD, has evaluated the
preliminary pro forma information provided by Mark Development and
Beacon Communities
Key Findings:
β’ Assumptions are in the range of reasonableness for this early stage
β’ For this stage, the maximum exemption (100% of the increment for
20 years) is necessary
β’ Conservatively β additional subsidy may be needed
β’ Optimistically β there may be room to renegotiate at construction
C. Documents Being Discussed Tonight
22
Thank you!