Matters ▸ Attachment
Marka CPC Funding Recommendation — File 208406
COMMUNITY PRESERVATION COMMITTEE FY20 FUNDING RECOMMENDATION FOR
EMERGENCY FUNDING REQUEST FOR POWDERHOUSE SCHOOL PARK, MARKA
PROJECT DESCRIPTION
Marka is creating a new public park on the site of the former Powderhouse School.
ELIGIBILITY
Recreational Land: Marka is rehabilitating land that was formerly part of the Powerhouse Schoolyard
and creating a new public park.
RECOMMENDED FUNDING
On May 22, 2019 by a vote of 6-0 the Community Preservation Committee recommended appropriating
$122,00 for this project, $61,000 from the open space/recreational land reserve budget and $61,000
from the budgeted reserve, to the control of Marka for the overall purposes summarized in this
document.
Project Budget
Recommended funding amount:
Expenses
Amount
Study
$0
Soft costs
$0
Construction
$754,700
Total $754,700
Sources
CPA open space/recreational land funds- requested
$122,000
Marka
$635,700
Total $754,700
JOSEPH A. CURTATONE
MAYOR
CITY OF SOMERVILLE, MASSACHUSETTS
COMMUNITY PRESERVATION COMMITTEE
ALIGNMENT WITH FY20 COMMUNITY PRESERVATION PLAN
The Community Preservation Plan prioritizes improving existing open space according to need.
FUNDING CONDITIONS
1. Upon commencement of the Project and as appropriate, the Marka agrees to post a sign stating
that the Project was funded through the City of Somerville’s Community Preservation Act
program.
2. Marka will complete the project as presented to the Community Preservation Committee on
May 22, 2019 without any reduction to the scope.
3. CPA funds will only go towards CPA eligible aspects of the project.
MEASURES OF SUCCESS
The goal of this project is to provide a new public park on the site of the former Powderhouse
Schoolyard.
Success will be measured through timely completion of the park project.
The full proposal is available at: https://www.somervillema.gov/cpa