20230306 SCS Appropriation Budget Memo — File 23-0325
CITY OF SOMERVILLE, MASSACHUSETTS
KATJANA BALLANTYNE
MAYOR
DEPARTMENT of INFRASTRUCTURE & ASSET MANAGEMENT
RICHARD E. RAICHE, PE, PMP
MELISSA WOODS, AICP
DIRECTOR OF INFRASTRUCTURE & ASSET MANAGEMENT
DIRECTOR OF CAPITAL PROJECTS
Page 1 of 1
Department of Public Works Building, First Floor • 1 Franey Road • Somerville, Massachusetts 02145
[phone removed], Ext. 5123 Fax: [phone removed] www.somervillema.gov
March 6, 2023
In development of the request to appropriate $827,000.00 from the Unreserved Fund Balance ("Free
Cash") to the Capital Stabilization Fund, and authorize expending the same amount, for the purpose of
funding the site preparation, construction, and fit out of a safe consumption site, Capital Projects submits
the following as anticipated preliminary costs for the project:
Designer Services
$200,000
Site Preparation
$292,000
Modular Delivery & Removal
$30,000
Modular Rental
$90,000
(Note: $2,482 per month at 36 months)
Furniture
$50,000
Contingency & Escalation
$165,000