Matters ▸ Attachment
CC Pavement Supplemental 2019Nov26 Full Size — File 209273
FY2020 Supplemental
Paving Request
City Council Special Meeting
Mayor Joseph A. Curtatone
Richard E. Raiche, PE, PMP
Director of Infrastructure & Asset Management
26 November 2019
Pavement & Sidewalk
Management Plan
Analysis of program performance
2
Pavement Condition Index survey
• Re-surveyed
central Somerville
• NEW for FY2020:
Added private
ways to database
3
PCI informs rehabilitation
4
$3.00
$18.53
$150.92
$0.00
$20.00
$40.00
$60.00
$80.00
$100.00
$120.00
$140.00
$160.00
Crack Sealing
Pavement
Patching
Mill & Overlay
with Sidewalks
& Ramps
Rehabilitation cost per square yard
(Construction cost only, excluding engineering,
police & administration)
Miles: Mill & overlay with sidewalks & ramps
• Current
approach,
production, and
backlog implies
a 50 year
horizon pave
current miles
requiring
paving
5
0
0.5
1
1.5
2
2014
2015
2016
2017
2018
2019
2020
Miles completed per contract
Do Nothing
(100 - 88)
Preventative
Maintenance
(87 - 47)
Full
Construction
(46 - 0)
Total
Public
16.3
29.3
46.5
92.1
Private
3.5
3.9
6.7
14.2
Total
19.9
33.2
53.2
106.3
Dollars: Mill & overlay with sidewalks & ramps
• Current
funding and
backlog
implies a 50-
plus year
horizon to
fund
identified
needs
6
Preventative
Maintenance
(87 – 47)
Full Construction
(46 - 0)
Total
Public
$6,660,869
$189,666,293
$196,327,162
Private
$1,089,614
$23,501,894
$24,591,509
Total
$7,750,483
$213,168,188
$220,918,671
$0
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
$160,000,000
$180,000,000
$200,000,000
Public
Private
Cost and time breakdown
• Sidewalks & ADA ramps required for full-width repaving
• Sidewalks = 60- to 65-percent of total cost, months to complete
• Roadway = 35- to 40-percent of total cost, days to complete
7
High-level conclusions
• Prioritization logically ranks streets
• Current approach, funding, and backlog yield untenable
time period for attaining acceptable pavement condition
• Increasing funding and construction by a factor of 5 or 10
is unaffordable and logistically impossible
• Costs and complexity of sidewalk construction drive the
equation
• Architectural Access Board (and our own inclusionary goals)
require sidewalks with full-width repaving
We need to approach PMP & SMP differently
8
New approach
• Decouple sidewalks from pavement prioritization
• Maintain overall funding level for sidewalks, but target
pedestrian priority areas
• NEW: Engineering worked with broad range of departments to
develop sidewalk prioritization
• Mill & overlay automobile and bike travel lanes only
• Continue investment in preventative maintenance
9
Example funding
10
City Funds $3,730,000 Note: showing in 2020$ for comparison, annual
request will be escalated 4%
Chapter 90 $1,200,000
Total $4,930,000
Preventative Maintenance
$900,000
Sidewalk Only $2,500,000
Mill & Overlay Travel Lane Only $1,530,000
Better production with new approach
• Preliminary,
conservative
evaluation of
costs to prove
concept
• $0.7 to $0.8M per
mile compared to
$4M
• 20% of full width
• Goals achievable
in 10 to 20 years
11
Full width &
sidewalks
Travel lanes only
Public
$189,666,293
$35,799,222
Private
$23,483,439
$5,764,575
Total
$213,149,732
$41,563,797
$0
$20,000,000
$40,000,000
$60,000,000
$80,000,000
$100,000,000
$120,000,000
$140,000,000
$160,000,000
$180,000,000
$200,000,000
Public
Private
Cost breakdown on average
• Sidewalk = 60-percent
• Parking zone = 20-percent
• Travel lanes = 20-percent
12
Additional considerations
• Parking lanes will remain in poor condition; however:
• Curb lines likely to change in future as a result of the parking study,
bike prioritization, mobility conclusions, green stormwater
infrastructure needs, urban forestry, etc.
• Water, sewer, drain and gas utility work likely to require full-depth
reconstruction of many streets
• Therefore deferring investment on the curb line and parking zone
makes sense
• Improves bike safety
• Boston and Cambridge have started similar “partial
paving” programs
13
Elm Street, Tremont Street, Cambridge
14
Revised Pavement &
Sidewalk Management Plan
The road to a better program
15
Prioritization
Travel lanes for vehicles & bicycles
Sidewalks for pedestrian routes
16
Pavement prioritization algorithm
17
NPR = (0.40 * (100-PCI)) + (0.50 * FCP) + (0.30 * PCP) + (0.10 * ADT)
Network Priority Ranking (NPR)
• Pavement Condition Index (PCI)
• Functional Classification Priority (FCP)
• Pavement Classification Priority (PCP)
• Average Daily Traffic (ADT)
Functional Classification
FCP Value
Equivalent ADT
ADT Factor
AR ‐ Arterial
90
20,000
100
MA ‐ Minor Arterial
80
15,000
75
CO ‐ Collector
70
8,000
40
RT ‐ Residential Local
50
2,500
15
RE ‐ Residential Dead End
40
500
5
Sidewalk management program algorithm
Network Priority Ranking (NPR)
• Sidewalk Condition Index (SCI)
• Route Classification Priority (RCP)
18
NPR = (0.40 * (100-SCI)) + (0.60 * RCP)
Route Classification
RCP Value
4 – Business District
100
3 – Transit Corridor
95
2 – Dense Neighborhood
85
1 – Side Street
75
0 – Calm Street
65
Road & Sidewalk Selection
Building annual construction contracts
19
Workflow
20
Calculate
pavement priority &
Sidewalk priority
• If priority street is also a
priority pedestrian route,
coordinate with Mobility
for design objectives
Prepare full-width
bid package
• Estimate total cost
Prepare sidewalk
bid package
• Target total ADA goal
Prepare travel lane
bid package
• Maximize total
length for annual
funding
ID # 209273 – Requesting a supplemental
appropriation of $500,000 to the Engineering
Division Capital Outlay Street Repairs
Account in order to perform mill and overlay
paving of the travel way in prioritized streets.
Agenda Item 5
21
Supplement FY2020 Construction
• $3.73M bond approved by City Council 24 Oct 2017
• Mill & overlay with sidewalk reconstruction
• Holland Street, College Ave from Davis to Powder House
• College Ave from Powder House to City line – add-alternative
• Note: These routes are also priority sidewalk routes
• Sidewalk & ADA ramp construction package
• Add $500,000 capital outlay for travel lane only mill & overlay
• Top priority vehicle route / non-priority pedestrian route:
• Inner Belt Road
• Note: Mix of bond and capital outlay is a typical strategy
22
Provisional Future Plan
23
FY2021 intended use & status
• Mill & overlay with sidewalk
• Pearl Street
• Coordination: Water complete, gas CY2020, Sewer & Mobility needed
• Sidewalks & ramps
• Various locations
• Mill & overlay travel lane only
• North Street
• Utility & Mobility coordination needed
24
Long-range priorities
• Mill & overlay with sidewalk
• Elm Street
• Broadway (Powder House to Arlington)
• School Street (Medford to Highland)
• Cross Street (Broadway to Auburn)
• Newton Street
• Mill & overlay travel lane only
• Summer Street (Willow to Cedar)
• School Street (Highland to Somerville)
• Cameron Avenue
• Mount Vernon Street
• Stickney Avenue
25
FY2020 Supplemental
Paving Request
City Council Special Meeting
Mayor Joseph A. Curtatone
Richard E. Raiche, PE, PMP
Director of Infrastructure & Asset Management
26 November 2019