Matters ▸ Attachment
FY20 EPH CPC Funding Recommendation — File 209310
COMMUNITY PRESERVATION COMMITTEE FY20 FUNDING RECOMMENDATION FOR
INSTALLATION OF AN ADDRESSABLE FIRE ALARM SYSTEM,
ELIZABETH PEABODY HOUSE ASSOCIATION
PROJECT DESCRIPTION
The Elizabeth Peabody House Association will install an addressable fire alarm system for their building
at 277 Broadway.
ELIGIBILITY
Historic resources: The Elizabeth Peabody House Association operates out of the former Broadway
Methodist Episcopal Church, which was determined to be historically significant by the Somerville
Historic Preservation Commission.
RECOMMENDED FUNDING
On November 19, 2019 by a vote of 9-0 the Community Preservation Committee recommended
appropriating $38,000 for this project from the historic resources budget to the control of the Elizabeth
Peabody House Association for the overall purposes summarized in this document.
Project Budget
Recommended funding amount:
Expenses
Amount
Study
$0
Soft costs
$0
Construction
$38,000
Total $38,000
Sources
CPA historic resources funds- requested
$38,000
Elizabeth Peabody House Association funds
$0
Total $38,000
JOSEPH A. CURTATONE
MAYOR
CITY OF SOMERVILLE, MASSACHUSETTS
COMMUNITY PRESERVATION COMMITTEE
ALIGNMENT WITH FY20 COMMUNITY PRESERVATION PLAN
The Elizabeth Peabody House Association provides child care and other social services to low-income
families, including immigrants. This project will allow the Association to protect their historic building in
case of fire.
FUNDING CONDITIONS
1. Execution and recording of the historic preservation restriction required under the FY18 CPA
grant.
2. The Elizabeth Peabody House Association will post a permanent sign noting CPA funding for the
restoration of their building.
MEASURES OF SUCCESS
The goals of this project are to:
•
Fully remove the old, current alarm system
•
Replace it with a new addressable system
•
Pass inspection by Somerville Fire Department
The success of the project will be measured by:
•
All out-of-date pieces of the system are no longer installed in the building
•
All elements of the new system are in place and functional. Tests of the new system will be run
upon installment to ensure that all pieces are in working order and up to safety codes.
•
Somerville Fire Department performs final inspection
The full proposal is available at: https://www.somervillema.gov/departments/community-
preservation-act/2020-cpa-projects