FY20 CPC Funding Recommendation Central Hill Park — File 209307
COMMUNITY PRESERVATION COMMITTEE RECOMMENDATION FOR
FY20 AWARD FOR CENTRAL HILL CAMPUS PHASE I, PUBLIC SPACE AND URBAN FORESTRY
DIVISION
PROJECT DESCRIPTION
Central Hill Park is Somerville’s oldest park (1870) and one of its largest (6.58 acres), located on Highland
Avenue between Walnut and School Streets. It is a key element in Somerville’s “civic center on the hill,”
which includes City Hall, Somerville High School, and Somerville Public Library’s main branch.
The Public Space and Urban Forestry Division will complete the first phase of renovating Central Hill
Park, which is the east side of the Central Hill Park property along Highland Avenue between Walnut and
Putnam Streets. The remaining phases of the Central Hill Campus will be fully designed and constructed
as part of the City Hall, 1895 building, and Library renovation planning efforts.
ELIGIBILITY
Open space/recreation land: This project will rehabilitate an existing park.
RECOMMENDED FUNDING
On November 19, 2019 by a vote of 9-0 the Community Preservation Committee recommended
appropriating $300,000 for the Central Hill Campus Phase 1 project from the open space budget to the
control of The City of Somerville for the overall purposes of first phase renovation of the Central Hill
Park.
Project Budget
Recommended funding amount:
Expenses
Amount
Study
$0
Soft costs
$0
Construction
$4,732,870
Total $4,732,870
Sources
CPA open space/recreation land funds- requested
$300,000
PARC GRANT
$400,000
CITY OF SOMERVILLE
$4,032,870
Total $ 4,732,870
JOSEPH A. CURTATONE
MAYOR
CITY OF SOMERVILLE, MASSACHUSETTS
COMMUNITY PRESERVATION COMMITTEE
ALIGNMENT WITH FY20 COMMUNITY PRESERVATION PLAN
The Community Preservation Plan prioritizes rehabilitating existing recreational land according to need
and creatively and coherently combine multiple uses that meet community need.
FUNDING CONDITIONS
1. Upon commencement of the Project and as appropriate, the City of Somerville agrees to post a
sign stating that the Project was funded through the City of Somerville’s Community
Preservation Act program.
MEASURES OF SUCCESS
The goals of this project are to:
•
Achieve a historically appropriate and unified sense of space
•
Improve accessibility within the campus
•
Respectfully incorporate and relocate numerous war memorials
•
Integrate the Central Library into the civic experience
•
Systematically mitigate stormwater impacts
•
Utilize landscape and urban design elements and wayfinding to enhance the visitor experience
Success of this project will be measured by the following:
1. Install site elements with materials appropriate to the historic context of the buildings
2. Deliver new walkways that meet or exceed accessibility standards
3. Install war memorials as directed by the Veterans Committee
4. Support exterior learning moments and library events across the Central Hill Park and
Playground
5. Measure stormwater quality and quantity
6. Guide and teach users successfully