Capital Investment Plan FY2023 City Council Item ID# 23-0271 Katjana Ballantyne, Mayor Richard E. Raiche, Director of Infrastructure & Asset Management Edward Bean, Director of Finance Michael Mastrobuoni, Budget Director 9 March 2023
Table of Contents • Chapter One – Orientation • Chapter Two – Evolution • Chapter Three – Considerations • Chapter Four – FY2023 Capital Investment Plan • Chapter Five – The Plan & Implementation 2
Orientation Background and table setting for Item ID# 23-0271 3 Chapter One
Capital investments – the companion to the operating budget, equally vital to the delivery of city services 4
City Council authorizes borrowing and accepts grants/loans for each capital investment 5
Capital Investment Plan (CIP) – Regularly updated statement of intent for major, non-recurring expenditures 6
Former CIP spreadsheets – outdated in both form and content 7
Current FY-2023 CIP – Updated investments & new ClearGov portal 8
Opportunity for involvement in the continued evolution of Somerville’s Capital Investment Plan 9
Evolution Ecosystem changes that influence Capital Investments 10 Topics Financial capacity Suite of municipal services Equity Climate change & sustainability Mobility & streetscape Data transparency Chapter Two
Financial capacity 11 Chapter Two Evolution
Tax base expansion 12 0 5,000,000,000 10,000,000,000 15,000,000,000 20,000,000,000 25,000,000,000 Assessed Value Residential Commercial/Industrial
Infrastructure backlog 13 0 20,000 40,000 60,000 80,000 100,000 Municipal Building Square Footage by Year Built / Renovated - (351,000 s.f. total)
Suite of municipal services 14 Chapter Two Evolution
Services expansion 15 FY2013 - $184.9M FY2023 - $307.6M
Equity 16 Chapter Two Evolution
Changing the built environment & technology to promote equity for all 17
Climate change & sustainability 18 Chapter Two Evolution
Changing the built environment to reduce carbon emissions & provide resiliency 19
Mobility & streetscape 20 Chapter Two Evolution
Reprioritization of right-of-way space 21
Data transparency 22 Chapter Two Evolution
Increased engagement 23
Considerations Practical limitations that morph an infinite wish list into a finite CIP 24 Topics Definition of solutions Cost forecasts Prioritization Financial analysis Adaptability Planning horizon Chapter Three
Definition of solutions 25 Chapter Three Considerations
Project lifecycle
Aggregation of investments 27
Cost forecasts 28 Chapter Three Considerations
Adjusting for escalation & standardizing soft costs Construction Escalation Design Added Scope Contingency 29
Prioritization 30 Chapter Three Considerations
Public Health & Safety: Is the project necessary to protect public health and safety? 31
External Obligations: Is the project required to comply with external statutory requirements? 32
Fiscal Prudence: Does the project leverage outside dollars, activate development, or reduce City operating costs? 33
City Services: Does the project enable or enhance the City’s ability to deliver municipal services? 34
Equity: Does the project promote equity for historically underserved residents? 35
Strategic Planning: Does the project advance the goals of accepted strategic plans including SomerVision, Climate Forward, and Vision Zero? 36
Evaluation criteria & application 37
Financial analysis 38 Chapter Three Considerations
Funding sources & eligibility 39
Financial Model: Basics & Assumptions 40
Financial Model: Measures of Fiscal Health 41 Secondary Metrics and Goals Paygo budget of 1.5% of prior year revenue OPEB appropriation >5% of health insurance premium Debt to Expenditure Ratio Debt Service should not take up too much of our operating budget expenditures Target: 8% Currently 4.3% Operating Reserves [Unassigned fund balance] + [general stabilization fund balance] should grow with the operating budget Target: 10-15% PY Revenue Currently 14.26% Operating Budget Surplus Future years should have a projected surplus in order to cushion us from variations (risk mitigation - economic) Target: >3% Historically above
Adaptability 42 Chapter Three Considerations
Continual evolution and adaptation 43
Planning horizon 44 Chapter Three Considerations
5-year plan 45
The FY2023 Capital Investment Plan Enough with the generalizations… what’s actually in the plan?!?! 46 Topics Buildings Parks & Open Space Streetscapes Vehicles, Equipment & Real Estate Chapter Four
Buildings 47 Chapter Four FY23 CIP
Recurring Annual Building Improvements 48
Assembly Square Fire Station Fit Out 49
Fire Station Rehabilitation Program 50
Building Master Plan - 1895 Building • https://www.somervillema.gov/buildingmasterplan 51
Community Center including teen space 52
Pre-K thru 8 School Buildings 53 • Enrollment Study • 2022 –2023 • Gap Analysis & Cost Estimates • 2023 • Feasibility Study & Community Process • 2023 – 2025 • Design & Construction • Starting Fall 2024
Investments not in the FY23 CIP but in the queue for future CIP updates* • Building Master Plan – City Hall • Building Master Plan – Edgerly Building • 1 Franey Road Building & ADA Improvements • 90 Washington Street / Public Safety Building • Armory Renovation & Rehabilitation 54 * non-exhaustive listing
Parks & Open Space 55 Chapter Four FY23 CIP
WestSNS, Healey & Brown Schoolyards 56
Somerville Junction Park 57
Dilboy Auxiliary Fields 58
ArtFarm 59
Central Hill Phase 1B – Restoration of Veterans Monuments 60
217 Somerville Avenue Open Space 61
• Blessing of the Bay • Kennedy School - Front Schoolyard • Osgood Park • Central Hill Campus Phase 2, 3 & 4 62 Investments not in the FY23 CIP but in the queue for future CIP updates* * non-exhaustive listing
Streetscapes 63 Chapter Four FY23 CIP
Annual Resurfacing, Sidewalks & ADA 64
Clarendon Hill & PHAB 65
SAUSI & Spring Hill Sewer Separation – General Fund Portion 66
Highland Avenue Streetscape 67
West Broadway Vision Zero 68
Boynton Yards 69
• Union Square Plaza & Streetscape • Davis Square Streetscape s • Gilman Square Streetscape s • SHS Gilman Square Elevator 70 Investments not in the FY23 CIP but in the queue for future CIP updates* * non-exhaustive listing
Vehicles, Equipment & Real Estate Chapter Four FY23 CIP
Investments • Recurring - DPW Vehicles • Recurring - Fire Apparatus Replacement • ERATE SPS Network Infrastructure Upgrade • Public Safety Radio Infrastructure 72
• Snow melters or storage space • DPW Yard 3 • School building WiFi, cell phone extenders 73 Investments not in the FY23 CIP but in the queue for future CIP updates* * non-exhaustive listing
Water & Sewer 74
Separate for Enterprise Funds 75
The Plan & Execution 76 Topics ClearGov Next steps Chapter Five
ClearGov 77 Chapter Five The Plan & Execution
ClearGov Budget Portal – About 78 Annual Operating Budget Capital Investment Plan
ClearGov Budget Portal – Plans 79
ClearGov Budget Portal – Projects 80
Next Steps 81
Somerville leads the way 82
Free cash to stabilization 83
Evolution & adaptability 84
Capital Investment Plan FY2023 City Council Item ID# 23-0271 Katjana Ballantyne, Mayor Richard E. Raiche, Director of Infrastructure & Asset Management Edward Bean, Director of Finance Michael Mastrobuoni, Budget Director 9 March 2023