Committee Report - PUPW - 2-3-20 — File 209690
Public Utilities and Public Works Committee
Page 1 of 6
Printed 2/6/2020
February 3, 2020
REPORT OF THE PUBLIC UTILITIES AND PUBLIC WORKS COMMITTEE
Attendee Name
Title
Status
Arrived
Jesse Clingan
Chair
Present
William A. White Jr.
Vice Chair
Present
Katjana Ballantyne
Ward Seven City Councilor
Present
Others present: Ann Connor-Mayor’s office, Steve MacEachern-DPW and Nick Antanavica-
ISD. Representatives from Water and Sewer department were not available to attend tonight to
respond to agenda items.
The meeting was held in the Committee Room and was called to order at 6:03 p.m. by
Chairperson Clingan and adjourned at 7:20 p.m.
Approval of the November 20, 2019 Minutes
RESULT:
ACCEPTED
204552: That the Director of Capital Projects or the Director of SPCD update this Board
about the transportation management and parking plans for both the construction and the
post-construction phases of the new High School.
RESULT:
KEPT IN COMMITTEE
205059: That the Administration present the information described herein about the
Brown School's physical plant and planned and completed renovations, to this Board, to
the School Committee, and to the Brown School community.
Councilor-at-Large White asked Mr. MacEachern for a follow up who has not had a chance to
speak with Mr. Raiche. Ms. Connor will resubmit a memo that had been previously submitted to
the committee in response to this request.
RESULT:
KEPT IN COMMITTEE
206959: That the Administration deem Newport Construction and Northern Tree to be
“not considered responsible bidders or offerors” for 5 years, reflecting their performance
Public Utilities and Public Works Committee
Page 2 of 6
Printed 2/6/2020
on the Beacon St Reconstruction.
Ms. Connor read through previous minutes stating that Councilor Scott was to send Ms.
Pappenheim some case laws to review. The chair will follow up with Councilor Scott on this
matter.
RESULT:
KEPT IN COMMITTEE
208578: That the Director of Water and Sewer provide a quarterly update regarding the
number and location of emergency sewer and water repairs.
RESULT:
KEPT IN COMMITTEE
208579: That the Director of Water and Sewer provide a quarterly update regarding the
progress filling vacancies in those departments.
RESULT:
KEPT IN COMMITTEE
208580: That the Director of Water and Sewer provide a quarterly update regarding any
maintenance requests being deferred for lack of resources.
RESULT:
KEPT IN COMMITTEE
208840: That the Director of SPCD provide this Council with an updated project schedule
for the Beacon Street reconstruction project including the current timeline and project
milestones being monitored.
The chair will follow up with Councilor Scott on this item.
RESULT:
KEPT IN COMMITTEE
208963: 28 residents commenting on the completion of the reconstruction of Beacon Street,
and next steps.
RESULT:
PLACED ON FILE
208995: That the Chief of Police and the Chief Fire Engineer provide an update on
upcoming and past meetings with Spectra Energy (now Enbridge) related to the Algonquin
Gas Transmission line and the J2 loop and any communications on risks and safety
procedures related to those pipelines.
The committee asked who the state notifies in the case of gas leaks. It was suggested that Mr.
Raiche come back to the committee to help explain the process.
RESULT:
KEPT IN COMMITTEE
209048: That the Director of Infrastructure and Asset Management, the Chief Fire
Engineer, the Chief of Police and other necessary departments advise this Council of the
Public Utilities and Public Works Committee
Page 3 of 6
Printed 2/6/2020
impacts of any further development along Alewife Brook Parkway on the Algonquin Gas
Transmission Pipeline running along Alewife Brook.
RESULT:
KEPT IN COMMITTEE
209076: That the Administration inform this Council how, if it all, the city may recoup
from utility companies its costs for a public safety response to gas leaks.
Ms. Connor will follow up with Councilor-at-Large Hirsch on this matter and provide a written
response from the City Solicitor’s office.
RESULT:
KEPT IN COMMITTEE
209079: That the Director of Infrastructure and Asset Management or another
representative of the Administration report to each Councilor by November 1, 2019, on the
placement of concrete for electrical equipment at the Brown School, and what alternate
locations could be less impactful on the school's limited physical space.
RESULT:
WORK COMPLETED
209191: That the Director of Inspectional Services and/or the Director of Engineering
report to this Council how the construction of driveways with pervious surfaces is
inspected to ensure that the subsurface has been correctly installed so precipitation is
absorbed.
Mr. Antanavica stated that the installation of driveways is inspected by city engineering. ISD
plans the installation details and works to insure proper amount of materials is used so it drains
when raining. The committee asked for Mr. Raiche to attend the committee to address this item.
RESULT:
KEPT IN COMMITTEE
209286: That the Director of Engineering and the Commissioner of Public Works repave
the crosswalk on Aberdeen Road at Highland Avenue, as it remains a tripping hazard for
pedestrians.
Mr. MacEachern stated the work will be completed in the spring 2020. He has spoken to the
contractor and it is a simple grind out to level the crosswalk.
RESULT:
WORK COMPLETED
209299: That the Commissioner of Public Works report to the Committee on Public
Utilities and Public Works about DPW monitoring of utility pole complaints to determine
whether the utilities follow through on them.
Mr. MacEachern stated there is a new person at Eversource. He and someone from the city’s
engineering group will go over to address these concerns with Eversource. It was stated there
are a number of issues included with the poles that includes leaning and double poles.
Public Utilities and Public Works Committee
Page 4 of 6
Printed 2/6/2020
RESULT:
KEPT IN COMMITTEE
209300: That the Chief of Police and the Chief Fire Engineer provide a written response to
the Committee on Public Utilities and Public Works by November 26, 2019, on meetings
with Spectra Energy/Enbridge about the Algonquin Gas transmission line and the J2 loop,
and on any communications about risks and safety procedures.
RESULT:
KEPT IN COMMITTEE
209345: That the Commissioner of Public Works repaint the "No-Cycling" decals on
business district sidewalks.
Mr. MacEachern stated DPW will stencil the decal on the streets in the spring.
RESULT:
WORK COMPLETED
209348: That the Director of Infrastructure and Asset Management advise this Council
what can be done immediately to lessen the continual flooding of Alewife Brook Pkwy when
it rains.
RESULT:
KEPT IN COMMITTEE
209349: 18 residents requesting that the MBTA bus stop that was at 95 Beacon St and has
been moved to 97 Beacon St, be returned to 95 Beacon St.
RESULT:
PLACED ON FILE
209386: The the Director of Inspectional services enforce current snow clearance
regulations on business and residential properties, with follow-through as snow melts and
re-freezes during each snow event.
Mr. Antanavica suggested using door knockers to make businesses and residents aware of
violations if snow is not cleared. He stated that mailing out violations can take three days before
an owner receives the notices.
RESULT:
WORK COMPLETED
209387: That the Commissioner of Public Works address the gaps in snow removal at
corners and intersections.
Mr. MacEachern stated the city is looking to purchase equipment to help clear snow from
handicap, sidewalks and bike lanes. The current equipment snaps covers when doing bike lanes.
The new equipment will be more durable.
RESULT:
WORK COMPLETED
209388: That the Commissioner of Public Works clear snow from sidewalks and
Public Utilities and Public Works Committee
Page 5 of 6
Printed 2/6/2020
crosswalks in at least the squares, arterial roads, and bus routes.
Councilor Ballantyne requested that Raymond Avenue be cleared, behind West Somerville
Neighborhood School to make it easier for students walking to school. It was also requested for
more people to shovel at the Winter Hill Innovation School stairs area.
RESULT:
WORK COMPLETED
209389: That the Director of SPCD and the Commissioner of Public Works commit to
provide a year-round safe pedestrian environment.
RESULT:
WORK COMPLETED
209390: That the Director of SPCD replace the missing street signs off North Street, and
replace the smaller signs with clearly visible signs on poles.
The committee would like this item referred to the Committee on Traffic and Parking.
RESULT:
DISCHARGED W/NO RECOMMENDATION
209422: That the Commissioner of Public Works move the right turn arrow signal at the
corner of Broadway and Temple Street to a more visible location.
RESULT:
WORK COMPLETED
209424: That the Commissioner of Public Works remove the abandoned newspaper boxes
that are in front of the Winter Hill Post Office.
Councilor White's motion that the Superintendent of Inspectional Services provide the
Committee on Public Utilities and Public Works with information as to whether the newspaper
boxes throughout the city are permitted or not, was approved.
RESULT:
KEPT IN COMMITTEE
209425: That the Commissioner of Public Works place a trash receptacle in front of the
Winter Hill Post Office.
RESULT:
WORK COMPLETED
209427: That the Commissioner of Public Works trim the tree at 116 Sycamore Street.
RESULT:
WORK COMPLETED
209443: That the Commissioner of Public Works and the Director of Health and Human
Services discuss the city’s road salting policy and residents' concerns about environmental
impacts, health impacts and the expense of "over-salting."
Public Utilities and Public Works Committee
Page 6 of 6
Printed 2/6/2020
Mr. MacEachern talked about sensible spreader equipment that will not repeat over the same
area to avoid over-salting. This new equipment will help to control the speed of the spinner and
spreading. Additionally, a vendor would like to donate equipment to the city to make its own
brine. Mr. MacEachern stated that the City of Cambridge is investing $1.5M to create its own
plant to create salt mixture. Councilor Ballantyne asked Ms. Connor to find out from Mr.
Sellers-Garcia the type of salt to use to create a brine.
The committee would like this item referred to the Committee on Open Space, Environment and Energy.
RESULT:
DISCHARGED W/NO RECOMMENDATION
209466: That the Director of Infrastructure and Asset Management update the Ward 6
Councilor on alternative locations for electrical equipment in the Brown School green
space.
RESULT:
KEPT IN COMMITTEE
209610: That the City Engineer and Commissioner of Public Works inspect the sidewalk
on the east side of Cedar Street for all instances of spalling, and report to this Council 1)
what caused it, 2) how the City will correct it, and 3) what measures the City will take
against the contractor, if it was caused by improper installation.
Mr. MacEachern stated that Engineering is overseeing this request and will notify the contractor.
RESULT:
KEPT IN COMMITTEE