Matters ▸ Attachment
2020-9-21 Legal Memorandum To City Council from Outside Counsel - Public[12380808v1] — File 210645
1
12380808.1
TO:
City of Somerville City Council
CC:
Francis X. Wright, Jr., Esq.
FROM:
Gareth I. Orsmond
DATE:
September 21, 2020
RE:
Conway Park – Administrative Settlement Agreement and Order on Consent
for Removal Action, CERCLA Docket No. 01-2020-0054 (the “AOC”)
Legal Background
Following negotiations, the City of Somerville (the “City”) and the U.S. Environmental Protection
Agency (“EPA”) entered into the above-captioned AOC. The U.S. Department of Justice reviewed
and approved the AOC. The AOC is effective as of August 26, 2020.
The AOC governs aspects of the Conway Park cleanup. Ordinarily, Conway Park would be
regulated under state hazardous waste law1 and, due to the presence of polychlorinated biphenyls
(PCBs), a federal act known as TSCA.2 Because the City has entered into the AOC, however,
certain activities will be regulated under CERCLA as well.3 CERCLA authorizes EPA to use
federal funds for time-critical cleanup actions where conditions present an imminent and
substantial endangerment. EPA can only access these funds if it enters into an AOC. The AOC
settles some claims that EPA has against the City, but it is not a comprehensive settlement of all
possible claims. For claims not settled by the AOC, the City has a liability defense because it owns
Conway Park as a result of a tax taking completed in 1943.4 It may have other defenses as well.
The AOC acknowledges that the City does not admit liability or waive its defenses. ¶4.5
The AOC is a prerequisite for EPA performing work with an estimated value of $3 million without
recovering these costs from the City (the “EPA Lead Work”).6 If the EPA were to do all of the
work contemplated by the AOC on its own, EPA’s estimated cost would be $7.8 million, which it
could then seek to recover from the City. The EPA Lead Work includes excavating, transporting,
disposing of, and backfilling certain areas where PCB contamination is high. The EPA Lead work
is complete when the site is considered clean at 18” below the surface, which would allow the City
to fill the site and install artificial turf or take other action to complete the cleanup. The AOC does
not prohibit the City from excavating another 18” to a level of 36” below the surface if it chooses
to install grass instead.
1 Massachusetts General Laws Chapter 21E and the Massachusetts Contingency Plan, 310 CMR 40.0000.
2 The Toxic Substances Control Act, 15 U.S.C. §2601, et seq.
3 The Comprehensive Environmental Response, Compensation and Liability Act, 42 U.S.C. §9601, et seq.
4 CERCLA §§ 101(20)(D) and 101(35)(A) exempt a municipality from liability arising from the involuntarily
acquisition of property, which includes takings for failure to pay taxes. However, a municipality may compromise
its defense if it contributes to or exacerbates the contamination after taking title.
5 Citations such as “¶4” refer to the numbered paragraph of the AOC.
6 To perform work valued at over $2 million, EPA must determine that there is an immediate risk to public health.
EPA made this determination.
2
12380808.1
Major Terms and Conditions
The AOC adheres to an EPA-published form. Much of the language is not negotiable. We were
able to negotiate some key areas, such as stipulated penalties, indemnification obligations, and
insurance requirements. The AOC’s material terms include the following:
The City is responsible for certain lead work (the “City Work”). The City Work includes
site preparation and control (e.g., creating access roads, site security). It also includes
excavating, transporting, and disposing of contaminated soils and backfilling areas where
these activities are not completed by EPA as EPA Lead Work. ¶29. The City must retain
contractors to perform the City Work, and EPA may disapprove a contractor. ¶25.
The City must prepare various plans – which the AOC calls “Deliverables” – for EPA
approval. ¶¶31-37. The Deliverables include a removal work plan describing and setting a
schedule for the City Work. October 5, 2020 is the due date for the work plan and some
other Deliverables.
The City must provide access for EPA and its contractors and must not use the site in a
manner that poses a risk to the public.
The City must provide EPA and the Commonwealth with reports and other information
relating to site activities upon request, excluding privileged or protected information.
The City must pay EPA’s “future response costs.” These are largely oversight costs relating
to the City Work or subsequent site closure activities. EPA states that its oversight costs
will be modest. If the City disputes a cost, it can submit the matter for dispute resolution
by a higher branch of EPA.
In certain instances, the City is excused from performance by force majeure events beyond
its control. EPA retains some discretion to determine what constitutes force majeure.
If the City fails to pay future response action costs or submit a Deliverable on time, the
City must pay EPA a stipulated penalty of $250/day for the first 14 days of delinquency,
$500/day for days 15 through 30, and $800/day from day 31 on.
If the City fails to complete the City Work and EPA takes over the cleanup, the City must
pay EPA a stipulated penalty of $750,000. A work takeover only occurs if the City stops
doing the City Work, is seriously or repeatedly deficient or late in performing the City
Work, or is implementing the City Work in a manner that endangers human health or the
environment. The City has a 30-day cure period before EPA can take over the City Work
and claim the penalty.
The City may submit EPA’s stipulated penalty assessments for dispute resolution by a
higher branch of EPA.
EPA covenants not to sue the City for the City Work, for future response action costs, and
for the EPA Lead Work up to $3 million. Aside from these matters, EPA reserves its rights
against the City, but the City reserves its defenses.
The City covenants not to sue EPA or its contractors with respect to the City Work, the
EPA Lead Work, future response costs, and the AOC, subject to limited exceptions.
3
12380808.1
The City must indemnify and hold harmless EPA and its contractors and representatives
for claims caused by negligent or wrongful acts or omissions by the City or persons acting
on its behalf, but this obligation is subject to the protections granted municipalities by the
Massachusetts Tort Claims Act and other state laws.
The City must require that its contractors and subcontractors meet minimum insurance
requirements, but the City itself can remain self-insured and does not need to meet these
same requirements.