CityCouncilUpdate_SchoolSlides_111220 Final — File 210902

File 210902·16 pages·📄 Original PDF (city portal)·sha256 f8894069f474…
School Building Improvement and Occupancy Plan 12 November 2020
Community updates ●School Town Halls ○July 29th ○August 5th ○September 21st ○October 29th ●School Committee meetings ●Technical report posted: ○ www.somerville.k12.ma.us/back-school-2020
Building & Ventilation Achieve “Low Risk” Score Internal Factors
Building Assessments - Risk Management 4 June - July Risk Identification Evaluate all buildings and individual spaces for COVID-19 transmission potential Risk Reduction Potential Identify all possible mitigation measures & resulting transmission reduction Aug Strategy Development Prepare preliminary designs, cost & schedule estimates Sept - Oct Implementation & Phased Opening Complete procurement & construction required to attain thresholds, and open spaces Group ONE schools Oct - Nov Ongoing Improvements Complete additional construction for remaining schools and to improve operations 2021 Space Planning Identify buildings & spaces that cannot attain thresholds Sept Space Planning Identify buildings & spaces that cannot attain thresholds before December 2020 Oct
Understanding Primary Airborne Audit Risk Assessment - Scoring System 5 1.00 1.99 2.00 2.99 3.00 4.00 Low Risk Moderate Risk High Risk Air handling consistent with ASHRAE guidelines for aerosol spread prevention Some air handling, but not to reliable levels for aerosol spread prevention Little to no air handling, allowing aerosol concentration 1.00 to 1.99 = Assessment score for opening a building / space for student use
Building Assessments - Deemed Unsafe During Pandemic 6 Existing Potential Building Score Risk Score Risk Building system summary Brown 3.67 High Risk 2.01 Moderate Risk No ventilation or central HVAC system. Only ventilation is via operable windows. Existing in space cooling units do not include any filtration. Edgerly (CTE, NWFC) 3.08 High Risk 2.14 Moderate Risk No ventilation or central HVAC system. Only ventilation is via operable windows. Existing High School (1895, 1929) 3.42 High Risk N/A High Risk No ventilation or central HVAC system. Only ventilation is via operable windows. 1 = Low Risk/ASHRAE guidelines 4 = High Risk 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Space & Implementation Planning - Aligning building mitigation with academic need Unavailable Buildings ● Old SHS, Edgerly CTE & NWFC classrooms, Brown School ● Students will be placed in alternative spaces based on SPS in-person phasing schedule ● Renovations to Edgerly and Brown will be evaluated along with municipal buildings starting in early 2021 7 Eligible Buildings ● Evaluated mitigation logistics and best use of each building ● IAM estimated difficulty/schedule for each building ● Work must be completed on a per-building basis ● Buildings will open in phases as mitigation work brings buildings to Low Risk range ● SPS determined how priority students could occupy each building Students may not be returning to their original school this year. Students will be brought back into available spaces as buildings are ready, based on the SPS phased hybrid in-person plan.
Building Assessments-Group ONE Schools 8 Existing Potential Building Score Risk Score Risk Building system summary Argenziano 2.09 Moderate Risk 1.2 Low Risk Has good central air system to work with to increase filtration and/or ventilation but does not currently have any humidification. Capuano 2.57 Moderate Risk 1.29 Low Risk Has good central air system to work with to increase filtration and/or ventilation but does not currently have any humidification. West Somerville 2.53 Moderate Risk 1.52 Low Risk Includes both central system and single zone systems that can be modified to increase filtration and/or ventilation but there is no existing humidification. 1 = Low Risk/ASHRAE guidelines 4 = High Risk 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Building Assessments-Group TWO Schools 9 Existing Potential Building Score Risk Score Risk Building system summary East Somerville 2.32 Moderate Risk 1.75 Low Risk Has good central air system to work with to increase filtration and/or ventilation but does not currently have any humidification. High School Mods 2.02 Moderate Risk 1.49 Low Risk Each room served by ventilation units that include filtration and that can be improved. 1 = Low Risk/ASHRAE guidelines 4 = High Risk 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Building Assessments - Group THREE Schools 10 Existing Potential Building Score Risk Score Risk Building system summary Healey 2.32 Moderate Risk 1.56 Low Risk Has good single zone systems in place that can be modified to increase filtration and/or ventilation but there is no existing humidification. Kennedy School 2.69 Moderate Risk 1.36 Low Risk Most spaces are served by systems that include filtration and ventilation, which can be improved. Corridors have minimal airflow. No humidification. Winter Hill 2.46 Moderate Risk 1.45 Low Risk Most spaces are served by systems that include filtration and ventilation, which can be improved but there is no humidification. Airflow pattern in classrooms can be improved as well. 1.0 1.5 2.0 2.5 3.0 3.5 4.0
Building Assessments - New High School 11 Existing Potential Building Score Risk Score Risk Building system summary New High School (2020) N/A N/A 1.2 Low Risk New centralized system 1.0 1.5 2.0 2.5 3.0 3.5 4.0
12 School Grouping In-Person Phase Sequence In-Person Education Target Start Date Argenziano, Capuano, West Somerville Phases 2A & 2B: All SPED High Needs, ELL Levels 1 & 2 (K-8) Phase 3A: Pre-K & K Early December 2020 New Somerville High School Phases 2A & 2B Cont.: ELL Levels 1 & 2 (9-12) Next Wave/Full Circle, CTE Seniors Early January 2021 High School Mods, East Somerville Phases 3B: Grades 1 & 2 Grades 3-12 TBD Late January 2021 Healey, Kennedy, Winter Hill Phases 4+ TBD - March/April 2021
Building Improvement Details ● Centralized air handling systems (based on physical constraints) ○ Increase outside air percentage ○ Increase filtration from MERV-8 to MERV-11, 13, or 14 ○ Add in-line UV disinfection units ○ Add in-line humidification units ○ Update electrical and plumbing systems as needed ○ Rebalance and recommission the systems ● Separate areas ○ Portable HEPA filters ○ Portable humidifiers ● Nurse’s stations / Wellness rooms ○ Isolate air handling from centralized systems ○ Provide new exhaust vents to roof ● Monitoring ○ Carbon dioxide (CO2) meters
Compressed Timeline
Current status & funding request ● Group 1 & Group 2 ○ Quotes reviewed, ready to award immediately ○ Need to proceed immediately to achieve occupancy dates ● Group 3 ○ Quotes received, anticipate award next week ● Budget = $7.5M (Quotes + 20% contingency) ○ $3M CARES Act (must be expended by 31 Dec 2020, no City Council action) ○ $3M COVID-19 Stabilization fund (Agenda Item 39, ID # 23755) ○ $1.5M Facility Construction & Renovation Stabilization Fund (Agenda Item 40, ID # 23756)