Copy of Dilboy Stadium FY21 CIP Request updated 8 25 20 (Template) (003) — File 210941
Project Title:
Project Address:
Department:
Project Mgr.:
Email:
New Project or Modification:
Department Priority:
Rank your project(s) in order of priority from your point of view. If you propose four projects, rank them 1, 2, 3, 4, with 1 being the highest, and so forth.
Project Description/Scope of Work:
Justification:
Relationship to Other Projects:
Category: Please check all appropriate boxes
Architectural/Engineering Feasibility Study
Architectural/Engineering Construction Document Services & Construction Admin
Building Alteration/Repair/Renovation/Addition/New Construction
Building Improvements (non-construction)
Purchase of Equipment (incl. vehicles, office equipment, hardware, etc.)
Information Technology Systems/Platforms (e.g. cloud based, internet based, etc.)
Street/Sidewalk/Monument Improvements
Water Improvements
Sewer Improvements
Land Development
Land Acquisition
Land Disposition
Parks and Open Space
Other:
Operational Impact:
Reduce Cost (greater than 5%)
Reduce Cost (less than 5%)
Cost Unchanged
Increase Cost (less than 5%)
Increase Cost (greater than 5%)
110 Alewife Brook Parkway
FORM A - DESIGN & CONSTRUCTION
CAPITAL IMROVEMENT PROJECT (CIP) REQUEST - FY21
Arn Franzen
afranzen@somervillema.gov
The new synthetic turf field and the drainage imporvements at Dilboy Stadium will require additional and regular care and maintenance
by the Parks and Recreation Field Operations staff, and the DPW.
Dilboy Stadium - Design and Construction
Recent studies document that recreational programming needs for the City's youth are unmet because of a critical shortage of large
recreation fields, and the Dilboy Stadium Field is the only full size recreation field in the City. As such it provides essential recreation space
for Somerville Youth and community athletes. The existing field is completely worn out, long overdue for replacement, and is unsafe for
users.
Replacemenmt of the existing synthetic turf field and running track inside Dilboy Stadium. Layout will be similar to the existing.
Improvents will include organic infill at the synthetic turf field and drainage system improvements to protect Alewife Brook. A contract for
design services is in place now and that firm has provided the construction estimate included below.
Parks and Recreation & PSUF
The need for additional quality recreation fields for Somerville youth is well documented and included in the 2016 Fields Master Plan. The
stadium and the auxillary field renovation are included in the CIP.
Recreation Field
What impact will this project have on operational costs?
X
Design and Construction Project Funding
Total Estimated Cost
Prior Years
Funding
FY 21
FY 22
FY 23
FY 24
FY 25
Capital Costs:
Feasibility Study
$ -
- - - - -
Land Acquisition/Appraisal
$ -
- - - - -
Environmental Remediation/LSP
$ -
- - - - -
Demolition & Site Clearance
$ -
- - - -
Owner's Proj. Mgr./Clerk of the Works
$ -
- - - - -
Designer Services (SD through CA)
$ 67,500
- - -
Construction
$ 1,326,005
1,326,005
- - -
Insurance (builder's risk, addtl. Polices)
$ -
- - - -
Furniture & Equipment (FFE)
$ -
- - - - -
Police Details
$ -
- - - - -
Contingency
$ 265,201
265,201
- - -
Other:
$ -
- - - - -
Other:
$ -
- - - - -
Total:
$ 1,658,706
$ 1,591,206 $ - $ - $ - $ -
Please provide suggested sources. This section will be finalized jointly by Finance and the Department.
Funding Sources:
Prior Years
Funding
FY 21
FY 22
FY 23
FY 24
FY 25
Stabilization Fund
$ -
- - - - -
GO Bonds
$ 1,591,206
1,591,206 - - - -
Retained Earnings
$ 67,500
- - - - -
General Fund
$ -
- - - - -
Special Assmnt.
$ -
- - - - -
Ch. 90
$ -
- - - -
Grants
$ -
- - - - -
Receipts Reserved
$ -
- - - - -
Other:
$ -
- - - - -
Other:
$ -
- - - - -
Total:
$ 1,658,706
$ 1,591,206 $ - $ - $ - $ -
Evaluation Committee Use Only:
Reviewed and Approved By:
Version
Requesting Department
Date
Draft
Auditing
Date
Revised
Purchasing
Date
Accepted
Final Approval
We have an existing contract for design services and those values are included above. The construction costs are budgetary estimates only, and the final costs
could be less. Note that CDBG and CPA funds cannot be used for the Synthetic Turf portions of this design.
-
-
-
-
-
67,500
-
-
-
-
-
-
67,500
-
-
-
$ 67,500
-
-
$ 67,500
-
-
-
-
-