Lead Line Service Replacement_Capital Program Request Sheet_FY22 CIP — File 212361
Project Title:
Project Address:
Department:
Project Mgr.:
Email:
New Project or Modification:
Department Priority:
Rank your project(s) in order of priority from your point of view. If you propose four projects, rank them 1, 2, 3, 4, with 1 being the highest, and so forth.
Project Description/Scope of Work:
Justification:
Relationship to Other Projects:
Category: Please check all appropriate boxes
Architectural/Engineering Feasibility Study
Architectural/Engineering Construction Document Services & Construction Admin
Building Alteration/Repair/Renovation/Addition/New Construction
Building Improvements (non-construction)
Purchase of Equipment (incl. vehicles, office equipment, hardware, etc.)
Information Technology Systems/Platforms (e.g. cloud based, internet based, etc.)
Street/Sidewalk/Monument Improvements
Water Improvements
Sewer Improvements
Land Development
Land Acquisition
Land Disposition
Parks and Open Space
Other
Operational Impact:
What impact will this project have on operational costs?
Reduce Cost (greater than 5%)
Reduce Cost (less than 5%)
Cost Unchanged
Increase Cost (less than 5%)
Increase Cost (greater than 5%)
Various
FORM A - DESIGN & CONSTRUCTION
CAPITAL IMROVEMENT PROJECT (CIP) REQUEST - FY22
Jonathan Smith
jsmith@somervillema.gov
None.
Lead Line Service Replacement (recurring)
Required by administrative order issued by DEP that requires the City to replace 44 lead service lines to private property per year and for
overall public health interest. This critical project addresses and improves water quality for residents not limited but included children,
who are disproptionately affected by lead exposure.
Design, construction, and field oversight of annual recurring lead line service replacement program. The program consists of removing lead
service lines and replacement with copper service lines at from the water main to the meter connection on private properties. Service is
replaced by excavating earth from the water mains located within both rights of way and private property. Annual program includes initial
design services; engineering services during construction; and all labor, matierials, and equipment necessary to complete replacement of
service lines.
IAM - Engineering
None.
Necessary
Modification to Existing Project
First
Design and Construction Project Funding
Total Estimated Cost
Prior Years
Funding
FY 22
FY 23
FY 24
FY 25
FY 26
Capital Costs:
Feasibility Study
$ -
Land Acquisition/Appraisal
$ -
$ - $ - $ - $ - $ - $ -
Environmental Remediation/LSP
$ -
Demolition & Site Clearance
$ -
$ - $ - $ - $ - $ - $ -
Owner's Proj. Mgr./Clerk of the Works
$ -
Designer Services (SD)
$ 170,000
$ 170,000.00
Designer Services (CA)
$ 178,999
$ 178,999.00
Construction
$ 1,319,774
$ - $ 1,319,774.00
$ - $ - $ - $ -
Insurance (builder's risk, addtl. Polices)
$ -
$ - $ -
$ - $ - $ -
Furniture & Equipment (FFE)
$ -
Police Details
$ 109,400
$ - $ 109,400.00
$ - $ - $ - $ -
Contingency
$ 131,827
$ 131,827.00
Other (Specify)
$ -
$ - $ - $ - $ - $ - $ -
Other (Specify)
$ -
$ - $ - $ - $ - $ - $ -
Total:
$ 1,910,000 $ - $ 1,910,000 $ - $ - $ - $ -
Please provide suggested sources. This section will be finalized jointly by Finance and the Department.
Funding Sources:
Prior Years
Funding
FY 22
FY 23
FY 24
FY 25
FY 26
Stabilization Fund
$ - $ - $ - $ - $ - $ - $ -
GO Bonds
$ 1,910,000 - 1,910,000 - - - -
Retained Earnings
$ -
General Fund
$ -
Special Assmnt.
$ - - - - - - -
Ch. 90
$ -
Grants
$ - - - - - - -
Receipts Reserved
$ -
Other (Specify)
$ - - - - - - -
Other (Specify)
$ - - - - - - -
Total:
$ 1,910,000 $ - $ 1,910,000 $ - $ - $ - $ -
Evaluation Committee Use Only:
Reviewed and Approved By:
Version
Requesting Department
Date
Draft
Auditing
Date
Revised
Purchasing
Date
Accepted
Final Approval
Recurring annual program on Water CIP. Request combines FY21 and FY22 Water CIP requests for recurring Lead Line Service Program, $1,060,000 and
$850,000, respectively