Matters ▸ Attachment
Copy of Street Sidewalk Repairs_Capital Program Request Sheet_FY22 CIP (003) — File 212516
Project Title:
Project Address:
Department:
Project Mgr.:
Email:
New Project or Modification:
Department Priority:
Rank your project(s) in order of priority from your point of view. If you propose four projects, rank them 1, 2, 3, 4, with 1 being the highest, and so forth.
Project Description/Scope of Work:
Justification:
Relationship to Other Projects:
Category: Please check all appropriate boxes
Architectural/Engineering Feasibility Study
Architectural/Engineering Construction Document Services & Construction Admin
Building Alteration/Repair/Renovation/Addition/New Construction
Building Improvements (non-construction)
Purchase of Equipment (incl. vehicles, office equipment, hardware, etc.)
Information Technology Systems/Platforms (e.g. cloud based, internet based, etc.)
Street/Sidewalk/Monument Improvements
Water Improvements
Sewer Improvements
Land Development
Land Acquisition
Land Disposition
Parks and Open Space
Other
Operational Impact:
What impact will this project have on operational costs?
Reduce Cost (greater than 5%)
Reduce Cost (less than 5%)
Cost Unchanged
Increase Cost (less than 5%)
Increase Cost (greater than 5%)
Various
FORM A - DESIGN & CONSTRUCTION
CAPITAL IMROVEMENT PROJECT (CIP) REQUEST - FY22
Brian Postlewaite
bpostlewaite@somervillema.gov
FY22 Street & Sidewalk Repairs & ADA Improvements
Annual street design and reconstruction is required to repair and maintain miles of streets, sidewalks, and ADA ramps throughout the
city. Annual project supplemented by Chapter 90 funds.
Design and reconstruction of streets, sidewalks, and ADA-accessible ramps on various public roads throughout the city. Work includes
design, engineering services during construction, excavation, gravel borrow, grading, manhole adjustments, drainage inlet
reconstruction, curb removal and resetting, curb extensions, median islands, installation of MAAB/ADA compliant curb cuts, crosswalk
lines, stop lines, double yellow lines, white lines, colored lane markings and other work as necessary.
IAM - Engineering
Necessary
New Project
First
Design and Construction Project Funding
Total Estimated Cost
Prior Years
Funding
FY 22
FY 23
FY 24
FY 25
FY 26
Capital Costs:
Feasibility Study
$ -
Land Acquisition/Appraisal
$ - - - - - - -
Environmental Remediation/LSP
$ -
Demolition & Site Clearance
$ - - - - - - -
Owner's Proj. Mgr./Clerk of the Works
$ -
Designer Services (SD through CA)
$ 250,000
250,000
Construction
$ 4,940,000 - 4,940,000
- -
Insurance (builder's risk, addtl. Polices)
$ - -
- -
Furniture & Equipment (FFE)
$ -
Police Details
$ 150,000 - 150,000
- -
Contingency
$ -
Other (Specify)
$ - - - - - - -
Other (Specify)
$ - - - - - - -
Total:
$ 5,340,000 $ - $ 5,340,000 $ - $ - $ - $ -
Please provide suggested sources. This section will be finalized jointly by Finance and the Department.
Funding Sources:
Prior Years
Funding
FY 22
FY 23
FY 24
FY 25
FY 26
Stabilization Fund
$ 500,000 $ - $ 500,000 $ - $ - $ - $ -
GO Bonds
$ 3,604,801 - 3,604,801
- -
Retained Earnings
$ -
General Fund
$ -
Special Assmnt.
$ - - - - - - -
Ch. 90
$ 1,235,199
1,235,199
Grants
$ - - - - - - -
Receipts Reserved
$ -
Other (Specify)
$ - - - - - - -
Other (Specify)
$ - - - - - - -
Total:
$ 5,340,000 $ - $ 5,340,000 $ - $ - $ - $ -
Evaluation Committee Use Only:
Reviewed and Approved By:
Version
Requesting Department
Date
Draft
Auditing
Date
Revised
Purchasing
Date
Accepted
Final Approval
Cost estimate provided by DCI, project consultant. Bonded project supplemented by $1,235,199 FY22 allocation of MDOT Chapter 90 funds and $500,000 from
street reconstruction stabilization.