Copy of Poplar Street Pump Station _Pump House and Facilities Pre-Con_Capital Program Request Sheet_FY22 — File 212549
Project Title:
Project Address:
Department:
Project Mgr.:
Email:
New Project or Modification:
Department Priority:
Rank your project(s) in order of priority from your point of view. If you propose four projects, rank them 1, 2, 3, 4, with 1 being the highest, and so forth.
Project Description/Scope of Work:
Justification:
Relationship to Other Projects:
Category: Please check all appropriate boxes
Architectural/Engineering Feasibility Study
Architectural/Engineering Construction Document Services & Construction Admin
Building Alteration/Repair/Renovation/Addition/New Construction
Building Improvements (non-construction)
Purchase of Equipment (incl. vehicles, office equipment, hardware, etc.)
Information Technology Systems/Platforms (e.g. cloud based, internet based, etc.)
Street/Sidewalk/Monument Improvements
Water Improvements
Sewer Improvements
Land Development
Land Acquisition
Land Disposition
Parks and Open Space
Other
Operational Impact:
What impact will this project have on operational costs?
Reduce Cost (greater than 5%)
Reduce Cost (less than 5%)
Cost Unchanged
Increase Cost (less than 5%)
Increase Cost (greater than 5%)
Various
FORM A - DESIGN & PRE-CONSTRUCTION
CAPITAL IMROVEMENT PROJECT (CIP) REQUEST - FY22 - Pump House & Facilities
Jonathan Smith
jsmith@somervillema.gov
The Pump Station and associated facilities will improve the Water and Sewer Department’s management of catch basin grit, as well as
serve as a nerve center for stormwater management through system monitoring equipment and infrastructure controls.
Poplar Street Pump Station Project - Pump House & Facilities
The Pump Station will serve as a restoration of a century-old drainage pathway for the greater Union Square area, taking advantage of
excess capacity in the GLX drainage system, redirecting stormwater flow from the MWRA system to a stormwater storage tank and 50MGD
pump array designed to optimize the flood-reduction and I/I offset benefits of the GLX connection.
Project includes final design services for the Poplar Street Pump Station, 4 million-gallon stormwater storage tank, catchbasin grit
handling, odor control, connection to the Somerville Avenue Utility and Streetscape Improvements box culvert, and connection to the
MBTA GLX drainage system. Project includes OPM services and CM@Risk for preconstruction services including construction feasibility
analysis, scope management, proposing cost-effective construction alternatives, and validating applicability of selected design elements.
IAM - Engineering
The Pump Station relates to the SAUSI project, Spring Hill Sewer Separation project and future system improvements, allowing for
diversion of stormwater flows to the proposed facilities. The overall site development at 10 Poplar Street supports the longer term
Brickbottom Vision Planning, serving as a community hub and transit-oriented public space.
Necessary
New Project
First
Design and Construction Project Funding
Total Estimated Cost
Prior Years
Funding
FY 22
FY 23
FY 24
FY 25
FY26
Capital Costs:
Feasibility Study
Land Acquisition/Appraisal
$ - - - - - - -
Environmental Remediation/LSP
$ -
Demolition & Site Clearance
$ - - - - - - -
Owner's Proj. Mgr./Clerk of the Works
$ 531,408 231,408 300,000
Designer Services (Design Phase)
$ 4,151,265 2,351,265 1,800,000
Designer Services (ESDC)
-
Construction
-
-
Insurance (builder's risk, addtl. Polices)
- -
-
Furniture & Equipment (FFE)
-
-
Police Details
- -
-
Contingency
-
-
Other (Specify)
$ 1,200,000 - 1,200,000 - - - -
Other (Specify)
$ - - - - - - -
Total:
$ 5,882,673 $ 2,582,673 $ 3,300,000 $ - $ - $ - $ -
Please provide suggested sources. This section will be finalized jointly by Finance and the Department.
Funding Sources:
Prior Years
Funding
FY 21
FY 22
FY 23
FY 24
FY25
Stabilization Fund
$ -
GO Bonds - GF
$ - - -
-
GO Bonds - Sewer
$ 5,882,673 2,582,673 3,300,000
-
GO Bonds - Water
-
Retained Earnings
$ -
General Fund
$ -
Special Assmnt.
$ - - - - - - -
Ch. 90
$ -
Grants
$ - - - - - - -
Receipts Reserved
$ -
Other - existing GF Bonds
$ -
- - -
Other - existing Sewer Bonds
$ -
- - -
Other - existing Water Bonds
$ -
- - -
Total:
$ 5,882,673 $ 2,582,673 $ 3,300,000 $ - $ - $ - $ -
Evaluation Committee Use Only:
Reviewed and Approved By:
Version
Requesting Department
Date
Draft
Auditing
Date
Revised
Purchasing
Date
Accepted
Final Approval
Funding for $2,582,673 has already been obtained and approved for the OPM and Designer through FY21. This request is for $3,300,000 which will provide
funding for OPM and Design services through the Design Phase of the PSPS Project ($2.1M); and fund the estimated costs for Pre-Construction Services which will
be provided by the selected CM@Risk firm ($1,200,000).