Healey Cost Breakdown — File 213081
ARTHUR D.HEALEY SCHOOLYARD, U-12 RECREATION FIELD, ADA RAMP AND STAIRS TO MYSTIC HOUSING - Additional Contaminated Soil Costs
2/1/22 ESTIMATE
Funding:
Bond FY22
Board Order No. 209483
6,000,000.00
$
COSTS TO DATE: LANDSCAPE DESIGN, CONSTRUCTION, LSP SERVICES, STOCKPILED SOIL REMOVAL*
(5,746,328.00)
$
AVAILABLE BALANCE
253,672.00
$
Estimate of Costs for removal of in-situ contaminated soils and related items
Based on Pre-Chacterization Data obtained to date
To be removed to out of state facility (based on elevated levels of Antimony)
CONTAMINATED SOIL REMOVAL COST PROJECTIONS
Levels of contamination of in-situ soils assumed to be similar to those previously excavated - but remain unknown
Lower unit cost
vs
Contract Unit Cost
4800 cy/7200 Tons
4800 cy/7200 Tons
Quantity Estimate:
4,800 cy or 7200 tons
at $78.35/ton
at $150/ton
Cost per ton: $78.35
$78.35
564,120.00
$
564,120.00
$
1,080,000.00
$
Additional Costs:
1) Additional LSP costs
$29,500
(proposed for upcoming WL amendment)
2) Additional LSP Services Soil Testing, consulting, and reporting for In-Situ soils
ESTIMATE
$60,000
Soil Testing, consulting, reporting for In-Situ soils
4) Additional Classic Site Solutions - Related costs
(Soil testing, Lab reports, Site Control Measures, LSP and Project Coordination, Equipment costs)
ESTIMATE
150,000
803,620.00
$
(B4 20% contingency)
5) Contingency
20%
160,724.00
$
964,344.00
$
* Classic Site Solutions Change Order No 2 for removal of stockpiled soils in process - to be signed off prior to Feb. School Vacation