Matters ▸ Attachment
CC SHS Add Appropriation 2022Jun09 v2 — File 213954
SHS Supplemental
Appropriations
Presentation to City Council
Mayor Katjana Ballantyne
Richard E. Raiche, Director of Infrastructure & Asset
Management
Edward Bean, Director of Finance
9 June 2022
Presentation outline
• Construction management update since December 2021
• Finance plan
• If interested:
• Background information from November 2021 presentation to City
Council
2
Construction management
Work and budget update
3
December 2021 Budget Adjustment
• Extraordinary unforeseen costs & schedule impacts
• ACM soils
• Covid-19
• Auditorium walls
• Executed settlement agreement with Suffolk
4
Revised project budget Dec 2021
Category
March 2017 Value
Dec 2021 Value
Construction
$199,747,908
$237,066,092
Soft costs
$36,702,127
$34,423,765
Furnishings & equipment
$5,096,000
$5,784,414
Contingency
$14,436,669
$6,584,962
Total
$255,982,704
$283,859,233
Building occupancy
Phase 1: Jan 2020
Ph 1&2: Mar 2021
Building occupancy
Phase 2: Aug 2020
Ph 2A: Dec 2021
Field completion
Summer 2021
Summer 2023
5
Dec
2021
6
Jun
2022
7
December 2021
8
June 2022
9
Continuing challenges
• ACM-containing debris
from old library
• Limited landfill
availability
• 4+ amendments to
DEP workplan
• Exports in 2022
• ACM: 1,010 truckloads,
34,340 tons
• Clean: 10 truckloads,
340 tons
10
Revised project budget June 2022
Category
Dec 2021 Value
Dec 2021 Value
Construction
$237,066,092
$240,672,114
Soft costs
$34,423,765
$34,423,765
Furnishings & equipment
$5,784,414
$5,784,414
Contingency
$6,584,962
$2,978,910
Additional debris disposal
$800,000
Total
$283,859,233
$284,659,233
11
Finance plan
12
Somerville
High School
Funding
2017
2022
City Share
134,147,557
168,659,233
MSBA Share
121,835,148
116,000,000
Total Funding
255,982,705
284,659,233
Planned City
Resources
2017
Debt
130,300,000
Facility Stabilization Fund
(Reserve)
7,174,379
Total Planned City
Resources
137,474,379
Debt
Allowable
under Debt
Exclusion
Debt Exclusion 11/8/2016
130,300,000
Additional debt exclusion
allowable under borrowing
9,682,704
Total allowable debt under debt
exclusion
139,982,704
Borrowed debt exclusion as of
6/3/2022
135,367,851
Remaining amount available for
debt exclusion
4,614,853
City Share
Funding
Sources
2022
Borrowed Debt Exclusion
135,367,851
Additional Borrowing Debt Exclusion
4,614,853
Energy Rebate
258,029
Premium Revolving
3,673,158
D2 (Land Proceeds USQ)
7,108,112
Facility Stabilization Fund
8,964,735
Free Cash
7,080,519
Unallocated Covid 19 Stabilization Fund
1,545,805
Unused SHS bond proceeds (Completed
Projects)
46,171
Total City Share
168,659,233
Additional slides to aid in
answering questions
Background presented to City Council November 2021
17
Change management
1,700 PCOs, CCDs & risk items over project lifetime
18
Corrections & clarifications to contract
• guideline
19
Owner-directed discretionary
20
Unforeseen site conditions
21
Unforeseen building conditions
22
New restrictions and conditions
23
Extraordinary unanticipated
costs
High-level overview of significant costs
24
Standard change & approved costs
Category
Amount
Declined value management
$2,640,153
Design changes & clarifications
≈ $2,400,000
Discretionary design changes
$377,934
25
Unforeseen direct costs
Category
Amount
Phase 1 Asbestos containing material (ACM) disposal
$1,859,528
Phase 2A Auditorium structural revisions
$754,630
Covid-19 mitigation expenses (including Mods rental)
$1,482,332
Additional police & fire details
$712,820
Phase 3 ACM disposal to date
$3,942,526
Projected phase 3 ACM disposal (NTWP 8)
$2,099,343
26
Schedule impact costs
Category
Amount
Phase 1 ACM delays
$2,640,153
Covid-19 & additional Phase 1A, 1B, 2, 2A delays
$6,962,440
Phase 3 ACM delays through August 2023 (NTWP 8)
$7,620,617
27
Settlement Agreement:
Adjust GMP & schedule for all completed
& known required work
• 198 open PCO’s & potential claims for completed work
• Phase 3 work & delays known as of October 22nd
• Shift final cost negotiation & litigation risk to Suffolk
• Exceptions for items outside of Suffolk’s control
28