Matters ▸ Attachment
Copy of Building Improvements_Capital Program Request Sheet_FY22 CIP — File 214030
Project Title:
Project Address:
Department:
Project Mgr.:
Email:
New Project or Modification:
Department Priority:
Rank your project(s) in order of priority from your point of view. If you propose four projects, rank them 1, 2, 3, 4, with 1 being the highest, and so forth.
Project Description/Scope of Work:
Justification:
Relationship to Other Projects:
Category: Please check all appropriate boxes
Architectural/Engineering Feasibility Study
Architectural/Engineering Construction Document Services & Construction Admin
Building Alteration/Repair/Renovation/Addition/New Construction
Building Improvements (non-construction)
Purchase of Equipment (incl. vehicles, office equipment, hardware, etc.)
Information Technology Systems/Platforms (e.g. cloud based, internet based, etc.)
Street/Sidewalk/Monument Improvements
Water Improvements
Sewer Improvements
Land Development
Land Acquisition
Land Disposition
Parks and Open Space
Other
Operational Impact:
What impact will this project have on operational costs?
Reduce Cost (greater than 5%)
Reduce Cost (less than 5%)
Cost Unchanged
Increase Cost (less than 5%)
Increase Cost (greater than 5%)
Deb Mitrano
dmitrano@somervillema.gov
Complete repairs and improvements to existing municipally-owned buildings, including but not limited to: consulting, design, and
construction administration; remedial structural work; roof and building envelope repairs; mechanical system replacement; and interior
retrofits.
Work is required to comply with current building code, eliminate weather intrusion, increase facility lifecycle and usability, improve
energy efficiency, satisfy program needs, and otherwise maintain occupancy of the municipal buildings.
These ongoing building upkeep projects are required to support and enable all other City functions, including those that further strategic
vision and goals.
Upgrades will result in negligable increased maintenance costs and may result in long-term costs savings due to greater buildling
efficiency and usefulness.
IAM - Capital Projects
CAPITAL IMROVEMENT PROJECT (CIP) REQUEST - FY22
FORM A - DESIGN & CONSTRUCTION
Building Improvements
Various
Necessary
Modification to Existing Project
Second
Design and Construction Project Funding
Total Estimated Cost
FY 21
FY 22
FY 23
FY 24
FY 25
FY 26
Capital Costs:
Feasibility Study
$ -
Land Acquisition/Appraisal
$ - $ - $ - $ - $ - $ - $ -
Environmental Remediation/LSP
$ -
Demolition & Site Clearance
$ - $ - $ - $ - $ - $ - $ -
Owner's Proj. Mgr./Clerk of the Works
$ -
Designer Services (SD)
$ 200,000
$ 200,000
Designer Services (CA)
$ 400,000
$ 300,000 $ 100,000
Construction
$ 2,080,000 $ -
$ 1,600,000 $ 480,000
Insurance (builder's risk, addtl. Polices)
$ - $ -
$ - $ - $ -
Furniture & Equipment (FFE)
$ -
Police Details
$ - $ - $ - $ -
$ - $ -
Contingency
$ -
Other (Specify)
$ - $ - $ - $ - $ - $ - $ -
Other (Specify)
$ - $ - $ - $ - $ - $ - $ -
Total:
$ 2,680,000 $ - $ - $ 2,100,000 $ 580,000 $ - $ -
Please provide suggested sources. This section will be finalized jointly by Finance and the Department.
Funding Sources:
Prior Years
Funding
FY 22
FY 23
FY 24
FY 25
FY 26
Stabilization Fund
$ - $ -
GO Bonds
$ 2,680,000
$ - $ 2,100,000 $ 580,000 $ - $ -
Retained Earnings
$ -
General Fund
$ -
Special Assmnt.
$ - - - - - - -
Ch. 90
$ -
Grants
$ - - - - - - -
Receipts Reserved
$ -
Other (Specify)
$ - - - - - - -
Other (Specify)
$ - - - - - - -
Total:
$ 2,680,000 $ - $ - $ 2,100,000 $ 580,000 $ - $ -
Evaluation Committee Use Only:
Reviewed and Approved By:
Version
Requesting Department
Date
Draft
Auditing
Date
Revised
Purchasing
Date
Accepted
Final Approval
$2,680,000 FY22 authorization planned; will be spent in FY23