Matters ▸ Attachment
Committee Report - SBFM - 6-30-22 — File 214095
School Building Facilities and Maintenance Special Committee
Page 1 of 4
Printed 7/14/2022
June 30, 2022
REPORT OF THE SCHOOL BUILDING FACILITIES AND MAINTENANCE SPECIAL
COMMITTEE
Attendee Name
Title
Status
Arrived
Beatriz GomezMouakad
Chair
Present
Lance L. Davis
Vice Chair
Present
Jesse Clingan
Ward Four City Councilor
Present
Others present: Rich Raiche - Capital Projects, Jill Lathan - DPW, Marc Hamel - DPW, Andre Green -
School Committee, Laura Pitone - School Committee, Hannah Carrillo - Legislative Liaison, Peter
Forcellese - Legislative Clerk.
The meeting took place virtually via GoToWebinar and was called to order at 6:04 PM by Chair Gomez
Mouakad and adjourned at 7:43 PM on a roll call vote of 2 in favor (Councilors Davis and Gomez
Mouakad), none against and 1 absent (Councilor Clingan).
Chair Gomez Mouakad explained that future meetings of this committee will be held jointly with the
School Committee or one of its committees. Noting that the City Council oversees all city buildings,
Chair Gomez Mouakad said that the purpose of the committee is to get everyone on the same page with
respect to school buildings. School Committee member Laura Pitone spoke about sharing the work and
increasing transparency and accountability to ensure that the proper resources are available. The School
Department has assigned John Callahan as the Director of Facilities Management for school buildings.
DPW Commissioner Jill Lathan pointed out that Mike Bowler, from the DPW, is the Facilties Manager
for all city buildings, including school buildings. Chair Gomez Mouakad mentioned several of the
problems being experienced in the schools and said that she would like to perform crisis management
without disrupting any classroom instruction.
School Buildings - Parks
213071: That the Executive Director of the Office of Strategic Planning and Community
Development provide an update on the status of work and finances of the Community
Preservation Act grants of 2018 for the Brown School and West Somerville Neighborhood
School playground designs and the continuing plans for the projects.
Councilor Davis inquired about the status of the schoolyard at the Brown school. Director Raiche replied
that an update from project manager Arn Franzen, who was unable to attend this meeting, was forwarded
to the School committee. Chair Gomez Mouakad Chair reported that an RFP has gone out for the project
and construction is expected to commence in August/fall of this year. Councilor Davis noted that the
workings of local government are moving at a slow pace and he commented on the need for a plan to
minimize disruptions and provide for an outdoor space for students during construction.
School Building Facilities and Maintenance Special Committee
Page 2 of 4
Printed 7/14/2022
RESULT:
KEPT IN COMMITTEE
School Building - Maintenance Systems and Staff
213114: That the Commissioner of Public Works identify, and provide the information
requested within, staff who are designated to school building maintenance and
management.
Discussed with 213115.
Superintendent Hamel stated that a member of his staff is cataloging HVAC systems in the schools and
identifying potential problems. Not counting major repairs, the repairs and maintenance that need to be
performed will cost approximately $700,000. Andy Rider, the city’s Preventive Maintenance Manager,
has created a database to catalog all HVAC devices in the city, including their parts, e.g., valves.
Superintendent Hamel reported that there will be 39 custodians for the schools and that he has enough
staff to handle small carpentry, electrical and plumbing repairs. He told the committee that a balance
needs to be reached when contracting out repairs.
The elevators at the Winter Hill and East Somerville Schools need repairs and a new elevator vendor
was brought on board as of a month ago under a 1-year contract. Because there are up to 5 different
elevator manufacturers used in the system and the elevators are of different ages, Superintendent
Hamel has requested that the same technician be assigned to all elevator calls in the city to provide
consistency.. Director Raiche said that the contract between the DPW and Cannistraro, the
mechanical contractor, is different and far more robust than the one it had with Honeywell.
Councilor Davis commented that he did not see a vendor for composting at the schools and he asked
Liaison Carrillo to follow up on this.
RESULT:
WORK COMPLETED
213115: That the Commissioner of Public Works identify vendors contracted for school
building maintenance and the scope of their contracts.
Discussed with item# 213114.
RESULT:
WORK COMPLETED
212962: That the Commissioner of Public Works report on all school building deferred
maintenance projects completed following the ventilation system assessment, proposed
completion dates, and strategies to assess needs for future deferred maintenance projects.
Commissioner Lathan said that the DPW has been working with IAM and needs more time to address the
issues.
RESULT:
KEPT IN COMMITTEE
213889: That the City Solicitor review the design issues related to ineffective shades and
placement of projector equipment in the high school auditorium and seek recovery for
costs to the city or other legal recourse available.
School Building Facilities and Maintenance Special Committee
Page 3 of 4
Printed 7/14/2022
Councilor Davis explained that the cost to correct these problems, which seem to be the result of a poor
design, is about $30,000 and he would like someone other than the city to incur the cost.. Director Raiche
stated that Solicitor David Shapiro will be submitting a formal response on this matter. Director Raiche
said it's important to understand recourse in matters such as this and went on to explain that designers are
not expected to be perfect - they're expected to perform their job with a general standard of care. It's
understood that there will be errors that will require some design changes as well as errors of omission.
The high school project is at about 2% in errors and the percentage for filing a lawsuit is around 5,
therefore, he doesn't think there is a legal recourse to recoup any money for these problems.
RESULT:
KEPT IN COMMITTEE
213892: That the Administration respond to educator and parent concerns regarding
building maintenance and capital improvements for the Winter Hill School.
Superintendent Hamel told the committee that his team is working with Director Raiche’s team and that
they’re in the process of making a list of mechanical repairs needed at the Winter Hill School. The
smaller repairs will be handled by the DPW while larger ticket items will be processed through Capital
Projects. Director Raiche reported that funding is available to perform a district wide assessment of
school buildings. He also said that the Winter Hill School will be evaluated for potential renovation. The
previously installed Honeywell equipment needs to be replaced and that will take some time to
accomplish. Long term resolution could involve replacing some systems since parts are no longer made.
Superintendent Hamel explained the failure of the school’s air conditioning system saying that as the
chiller was being charged, multiple leaks were discovered and repaired. There was then a seal failure and
although an overnight shipment of the seal was promised, it took 2 weeks to receive it.
Chair Gomez Mouakad requested that a more detailed list of problems be provided at the next
committee meeting.
RESULT:
KEPT IN COMMITTEE
213898: That the Commissioner of Public Works and the Director of Infrastructure and
Asset Management report on all major repairs and work orders for the Winter Hill
Community School and the Brown School over the past five years.
Councilor Davis stated his surprise that some of the bigger problems weren't included on the list. He
spoke about past problems at the Brown School, e.g., the roof collapse during a snowstorm as well as
roof leaks over the course of many years. He noted that there was no central method of monitoring
problems and repairs over time, saying that maintenance programs need to be implemented to avoid
future problems. Chair Gomez Mouakad commented that the intent is to understand what happened
in the past so that future problems can be prevented.
Director Raiche said the list is not complete due to a division of labor between IAM and DPW.
Despite the multiple roof repairs at the Brown School, the leaks have persisted. Data is now being
centralized and efforts are underway to implement a robust system to capture all maintenance and
repairs across all assets, with buildings being the most complex. A report is provided to the mayor
on a bi-weekly basis to keep the visibility of the importance of this matter.
RESULT:
KEPT IN COMMITTEE
School Building Facilities and Maintenance Special Committee
Page 4 of 4
Printed 7/14/2022
213897: That the Director of Infrastructure and Asset Management report on the status of
the 1895 building.
Director Raiche said that a presentation was made to City Council in Nov of 2021 and is available here:
<https://www.somervillema.gov/buildingmasterplan>. The 1895 building is not suitable for
educational purposes but is suitable for office space. School Committeewoman Pitone pointed out
that the building has not been released by the School Department to the city and is being considered
for use by SCALE. She noted that there is no space to house students in the event that current class
space is not able to be used.
Chair Gomez Mouakad asked if the administration has any plans for the building and Director Raiche
said that the city has infinite needs and finite resources. He stated that a decision needs to be made
on the future of the building soon. Chair Gomez Mouakad noted she would bring this item back to
committee in a few months to provide proper follow-up as this is a Somerville Public Schools
Building and as per School Committee Member Pitone it is still unclear what school services could
remain in the building to support school functions.
RESULT:
KEPT IN COMMITTEE
Reference Material:
•
PSUF response to City Council Request (with 213071)
•
CC Response 2.24.22 Submitted 3.16.22 (with 213114, 213115)
•
CC Response 5.16.22 PUPW Final 5.12.22 (with 212962)
•
WH Brown (with 213898)