2024.07.11 memorandum for extension — File 24-1374
July 11, 2024
Roberta Cameron
Community Preservation Act
City of Somerville
[phone removed] ext. 2528
Re:
Extension for FY21 CPA contract
SHA4CD, Grace Baptist Church – 59 Cross Street
Greetings Roberta,
We are writing to request an extension for the CPA FY21 contract, awarded to the Somerville Hispanic Association
for Community Development for masonry restoration to the building’s exterior. Due to unforeseen delays, more
time is needed to fully complete the project, which is expected by Spring 2025 or sooner.
For some background, the current, consolidated construction contract for the three CPA grants and ARPA grant
was originally going to be split into multiple general contracts, each with its own general contractor. For example,
the elevator pit was going to be installed by a different contractor than the elevator hoist way. It was originally
planned that the elevator pit contractor would also accomplish the FY21 masonry work as part of their collected
scope. However, the staggering of different grants with different timelines made it very difficult to coordinate with
several general contractors, leading to these delays. However, now that all work for all four grants has been
consolidated under one contract, the work will be able to proceed immediately as part of the overall accessibility
improvement project. In terms of timeline, as mentioned above and subject to permitting and construction
schedule, the FY21 masonry work is expected to be complete by Spring 2025 or sooner.
Thank you for the consideration in extending this grant contract.
Sincerely,
Shawn Willett
Principal, Architect for Somerville Project
[email removed]