Eversource_Somerville_Council_Electrification_Slides_Nov 2024 — File 24-1552
Somerville City
Council Update
1
o Introductions
o Massachusetts’ Clean Energy Goals
o Electric Sector Modernization Plan (ESMP)
o Demand Growth
o Projects Underway and Planned
o Outreach and Stakeholder Engagement
o Q&A
Agenda
Massachusetts’ Clean Energy Goals
33%
Reduction by
2025
50%
Reduction by
2030
75%
Reduction by
2040
NET ZERO EMISSIONS
by
2050
MA LAW REQUIRES REDUCING
GREENHOUSE GAS EMISSIONS
2022 Climate Bill requires each Electric Distribution Company develop an Electric-
Sector Modernization Plan (ESMP) to proactively upgrade the distribution and,
where applicable, transmission systems to meet the Commonwealth’s climate goals
MA LAW REQUIRES DEVELOPMENT
OF ELECTIC SECTOR MODERNIZATION
PLAN
Home of the Clean Energy Future
Solving for Increased Electric Demand
•
Infrastructure Needed
Requires an electric network
buildout and upgrades at an
unprecedented pace and
scale, in collaboration with
customers, communities,
policymakers, and other
stakeholders.
•
Meaningful Engagement
Those potentially impacted by
this transition deserve to play
a role in energy discussions
that affect their lives
UPGRADES
AHEAD
Yesterday’s Grid
Tomorrow’s Grid
WHERE WE ARE
WHERE WE
ARE HEADING
Key Drivers of the Net-Zero Goals
Zero-carbon heating projected to add
3.5 GW of winter demand by 2035
Electric vehicle adoption projected to
add 1.3 GW of winter demand by 2035
0
2
4
6
8
10
12
14
16
18
Current Base Load
2028
2033
2035
2040
2045
2050
Gigawatts (GW)
Enabled by 10-year Plan
Residential
Commercial/
Industrial
Transportation
Heating
What is a
Gigawatt?
It’s the
equivalent of
100 million
LED bulbs!
Source: energy.gov
Eversource Peak Electric Demand
System shifts
from summer
peaking to
winter peaking
7
Location of Major Capital Projects in the 10-Year Plan
Metro West
4 new stations
4 station upgrades
Southern
4 new stations
7 station upgrades
Western
2 new stations
11 station upgrades
Investments in 17 new clean energy hubs and upgrades to 26 over the next ten years will enable
the clean energy future in Massachusetts
Metro Boston
7 new stations
4 station upgrades
•
The Company is closely monitoring development in Somerville
•
New Office blocks and life science building development at
Assembly, Boynton Yards, and Union Square make up 81% of
60MW of new load in Somerville city proper
What’s driving the near-term demand
growth in Somerville?
8
81%, 49
16%, 10
2%, 1
2%, 1
0
10
20
30
40
50
60
Office/Life Science Lab
Residential/Retail
Other
Transportation
Load (MW)
Large Customer Categories for Step Loads to 2030
10 Year Capacity Deficiencies in The City of Somerville translate to negative
reliability outcomes if not immediately addressed
9
Substation
Name
Boston Communities Served
2030
Substation
Loading %
Ten-Year Project Solution
And Need Date
Mystic
Charlestown, City of Somerville
99
2022. Somerville Substation Expansion (Delayed as of September 2024)
2032. New Charlestown/Somerville Substation
Mystic
City of Somerville
•
New Charlestown/Somerville Substation provides
long-term capacity relief for neighborhood of
Charlestown and City of Somerville
Legend:
Area near capacity
Area at Capacity
Potential New Substation Area
Area directly benefiting from
New Substations
New
Charlestown/Somerville
Substation (2032)
9
Somerville Substation
Expansion (2024)
Union Square Planning | City of Somerville (somervillema.gov)
Prospect Street Substation #402 (Somerville) and Distribution
Work (Somerville & Cambridge)
Underway – Construction ongoing for addition of a third
transformer at the existing Prospect Street Substation in
Somerville. This project also includes about 2.5 miles of
new distribution duct bank, including portions in Somerville
and Cambridge.
Greater Cambridge Energy Program, Substation #8025
Underway - Executive Facilities Siting Board approval of new
underground substation, five underground transmission routes
through city streets to existing substations in Boston, Cambridge,
and Somerville.
New Projects in Planning Phase
Planning – Underground Cable Modernization Program (UCMP)
aims to replace high pressure fluid filled (HPFF) cable with new
duct bank and cross-linked polyethylene (XLPE) cable between
Mystic and Prospect Street substation and Mystic to North
Cambridge substation.
Planning - Fence and Control House Upgrades
Electric System Projects Currently Underway and Planned for Somerville
10