Matters ▸ Attachment
Capital Request- Trum Field — File 26-0197
Priority #
of
Title:
Project Description:
Justification:
Please rank this project on a scale of 1 to 5 for the following criteria
3 Public Health and Safety
1 Return on Investment
1 Operational Efficiency Improvements
1 Overall Quality of Life
Catefory: Please check all appropriate boxes
Architectural/Engineering Feasibility Study
Architectural/Engineering Construction Document Services & Construction Admin
X
Building Renovation/Addition/New Construction
X
Building Improvements
Purchase of Equipment
Technology Equipment
Street/Sidewalk/Monument Improvements
Water Improvements
Sewer Improvements
Land Development
Land Acquisition
Parks
Other
Mayor's Goal:
Project Address:
Trum Field LED Lighting
9. Environment
This project savings energy and enhances city climate goals of reducing utility emissions.
Installation of LED lights and controls at Trum Field
541 Broadway
Total
Estimated
Cost
Prior Years
Funding
FY 2026
FY 2027
FY 2028
FY 2029
FY 2030
Capital Costs:
Preliminary
$ - $ - $ - $ - $ - $ - $ -
Design
- - - - - - -
Land/ROW
- - - - - - -
Construction
210,525 - 50,000 160,525 - - -
Equipment
- - -
- - -
Administration
- - - - - - -
Other (Specify)
- - - - - - -
Other (Specify)
- - - - - - -
Total:
$ 210,525 $ - $ 50,000 $ 160,525 $ - $ - $ -
Funding Sources:
Capital Stab. Fund
$ - $ - $ - $ - $ - $ - $ -
GO Bonds
- - - - - - -
Special Assmnt.
- - - - - - -
Grants
- - - - - - -
Energy Stabilization F 191,415 - 191,415 - - - -
Incentives
19,110 - 19,110 - - - -
Total:
$ 210,525 $ - $ 210,525 $ - $ - $ - $ -
Operational Impact:
FY 2026
FY 2027
FY 2028
FY 2029
FY 2030
Other (Specify) $ - $ - $ - $ - $ -
Other (Specify) - - - - -
Other (Specify) - - - - -
Other (Specify) - - - - -
Total:
$ - $ - $ - $ - $ -
This project has a large electrical cost savings element and also enhances the operation of the field lighting
system
Projected construction period in Summer/Fall of 2026 contingent on stadium scheduling and cost estimate
based on vendor proposal