October 2025 CSO Draft Plan — File 26-0650
Draft Combined Sewer Overflow
Updated Long Term Control Plan
File ID 25-1451 Officer’s Communication
to City Council
Infrastructure & Asset Management
23 October 2025
Presenter's Preamble
• This extended presentation deck, including supplemental slides (26
through 89), is provided to the Council as a reference document and
to facilitate follow up discussions
• Many slides provide links to other presentations, videos, and
resources for further information
• Much like the May 2025 Officer’s Communication to the Council, even
the presented slides (3 through 23) could be topics of prolonged
discussion
• It is the presenter’s intention to move very quickly through the slides
and only provide the highest-level overview on each topic
• The presenter is happy to follow up on any of these topics in person
or at subsequent meetings
2
Formal regulatory process
3
Continuation of CSO control efforts
System Wide CSO Reduction Since the 1980s
*Annual discharge volume based on the prior Typical Year
Variance Water Study Area
*Volumes consider climate change
Formal regulatory process parties
4
Drafting &
executing plan
City of Cambridge
(Stantec, W&S)
Massachusetts
Water Resources
Authority (MWRA)
(AECOM)
City of Somerville
(Dewberry, CBI)
Reviewing &
approving plan
Massachusetts
Department of
Environmental
Protection
US
Environmental
Protection
Agency
Input &
comments
•
Charles River
Watershed Association
•
Mystic River
Watershed Association
•
Save the Alewife
Brook
•
MWRA Advisory Board
•
Neighboring cities &
towns
•
Various State agencies
•
General public
Formal Variance Water Schedule
5
What it means for Somerville
• Legal (and moral) obligation to
mitigate CSOs
• Federal/State Administrative
Order will bind Sewer CIP for a
generation
6
• Will constrain future Capital
Investments & operating
budgets
Photos by David Stoff & Ann McDonald / Save the Alewife Brook
Council action on this item
• Council approval not required for submission of plan to
DEP/EPA
• However, plan will drive sewer CIP and rates for decades
• Therefore, plan will influence future Council actions on
rates
• Infrastructure & Asset Management would like a
sense of the Council’s position on the plan
7
High level summary of process & conclusions
Supplemental Slides (24 through 87) provide support for Q/A
• Planning process
• Community outreach & engagement
• Tools for predicting CSO mitigation
• Vocabulary: “Typical Year” and “Level of Control”
• Alternatives, analysis & evaluation
• Eliminated alternative: Sewer separation
• Upstream contributions & downstream constraints
• Difficulties with & costs of sewer separation
• Eliminated alternative: 25-Year level of control
• Large storms causes multiple system failures resulting in sanitary pollution
• Other sources of pollution and Charles/Alewife/Mystic water quality
• Scale & cost of CSO control
• Limitations of the Variance Water plan compared to success stories nationally
• Local efforts outside of the Variance Water plan to improve water quality
• Eliminated alternative: Lower level of control
8
Draft recommended plan
Cambridge, Somerville & MWRA technical team’s
Goldilocks alternative
9
Proposed construction
10
Alewife Brook
Pump Station
Dilbo
y
Field
MWR003
Fresh Pond
Not to Scale
Little
Pond
Spy
Pond
CAM401
B
MWR003 1.5
MG Storage
Tank
CAM401A 1.5
MG Storage Tank
CAM401A
Increased
Conveyance
CAM00
2
CAM401A
Legend:
Combined Sewer System Facility
CSO Outfall
CSO Storage Tank
Sewer Separation
CSO Storage Conduit
Near-surface Conveyance
N
SOM001
A
CAM00
1
CAM401B and
SOM001A 2.3 MG
Microtunnel Storage
Conduit
9 ft diameter
CAM001 8 Acres of
Sewer Separation
3.AB Hybrid 2
Level of Control: 0 CSOs in 2050TY
Storage:
- Tanks: 2
- Tunnel: 0
- Microtunnel: 1.0 miles long
Key Features
Conveyance: 0.75 miles long
Sewer Separation: 8 acres
GSI: with separation/ other street
excavation
Land Acquisition: Yes
Time to Complete: 13-18 years
Preliminary Cost: $340 Million
95 Acres of
Sewer
Separation
Mystic
River
Legend:
Combined Sewer System Facility
CSO Outfall
CSO Storage
Sewer Separation
Storm Drain
Mystic
River
Somerville
Marginal
CSO Facility
DeLauri
Pump
Station
MWR20
5
SOM007A
/
MWR205A
SOM007A/MWR205
A 2.7 MG Storage
Tank
Stormwater Trunk
Line to Mystic
River
Remaining Activation Frequency and
Treated Discharge Volume in the 2050
TY
Total
Volume
(MG)
Activation
Frequency
6.77
2
SOM007A/
MWR205A
6a.MR Hybrid 1
Level of Control: Limited CSOs in
2050TY
Storage:
- Tanks: 1
- Tunnel: 0
- Microtunnel: 0
Key Features
Conveyance: 0
Sewer Separation: 95 acres
GSI: with separation/ other street
excavation
Land Acquisition: Yes
Time to Complete: 5-10 years
Preliminary Cost: $170 Million
Not to Scale
N
CAM00
5
CAM00
7
MWR01
0
MWR20
1
CAM017
MWR20
3
RE046-
19
RE046-
30
RE046-
381
RE046-
100
RE046-
105
RE046-54
RE046-55-1
Not to Scale
N
Legend:
Combined Sewer System Facility
CSO Outfall Tributary to Charles River
CSO Outfall Tributary to Boston Harbor
RE046 CSO Regulator
Stormwater Storage
CSO Storage
Sewer Separation
RE046-
62A
Bosto
n
Harbor
Ward Street
Headworks
Facility
Prison Point
CSO Facility
CAM017 80 Acres of
Partial Sewer Separation
CAM005 2.5 MG
Storage Tank
RE046-100 0.06 MG
Storage Conduit
MWR02
3
188 Acres of Partial
Sewer Separation
MWR01
8
MWR01
9
MWR02
0
Not to Scale
N
Columbus
Park
Headworks
Facility
8.CR Hybrid 1
Level of Control: Limited CSOs in
2050TY
Storage:
- Tanks: 1
- Tunnel: 0
- Microtunnel: 0
- Storage Conduits: 1
Key Features
Sewer Separation: 268 acres
GSI: with separation/ other street
excavation
Land Acquisition: Yes
Time to Complete: 23-28 years
Preliminary Cost: $360 Million
Remaining Activation Frequency and
Volume in the 2050 TY
Total
Volume
(MG)
Activation
Frequenc
y
0.0
0
CAM005
0.0
0
CAM007
0.0
0
CAM017
0.88 –
0.94
2
MWR018-020
0.11
2
MWR023
0.0
0
MWR010
26.8*
4
MWR201
*treated discharge
Projected CSO elimination
14
Plan performance – 2050 Typical Year
15
Hydraulic Model Predictions 2050 TY
Level of Control
Receiving Water
CSO Discharge Volume (MG)
Activation Frequency
Recommended
Plan
Current
Conditions
Recommended
Plan
Current
Conditions
6.7 Treated
29.3
2
8
1 – Limited CSOs in
2050 Typical Year
Upper Mystic
0
20.9
0
13
2 – Zero CSOs in 2050
Typical Year
Alewife Brook
1.2 Untreated
26.8 Treated
38.4
4
6
1 – Limited CSOs in
2050 Typical Year
Charles River
Plan performance – Historical record
Alewife Brook
Recorded/reported events at all 7 Alewife outfalls 1 Jan 2015 thru 31 Dec 2024 versus model results for recommended alternative for that rainfall record
16
92% reduction in activation frequency
(109 to 9 for 10-year period)
79% reduction in total volume
(170 to 35 MG for 10-year period)
0
5
10
15
20
25
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
Number of Activations
Existing Conditions
Preferred Alternative
0
10
20
30
40
50
60
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
Volume of CSO (MG)
Existing Conditions
Preferred Alternative
Plan performance – Historical record
Mystic River upstream of dam
Recorded/reported events at SOM007A outfall 1 Jan 2015 thru 31 Dec 2024 versus model results for recommended alternative for that rainfall record
17
94% reduction in activation frequency
(102 to 6 for 10-year period)
96% reduction in total volume
(239 to 9 MG for 10-year period)
0
5
10
15
20
25
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
Number of Activations
Existing Conditions
Preferred Alternative
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
80.00
2015
2016
2017
2018
2019
2020
2021
2022
2023
2024
Volume of CSO (MG)
Existing Conditions
Preferred Alternative
Projected financial impact &
Financial Capability Assessment (FCA)
18
Provisional FCA results
• Alt 1 Residential Indicator
• Cost per Household = 1.34% MHI – Mid-Range Burden
• Alt 2 Residential Indicator
• Mid-Range Burden FY2033 through FY2040
• Low Burden before and after
• Alt 2 Lowest Quintile Residential Indicator
• Low Burden FY2027 through FY2029
• Mid-Range Burden FY2030 through end of projection
• EPA methodology indicates Somerville has the financial
capacity to undertake this plan on this schedule
19
Note: At the time of this presentation, costs and allocations are being QA/QC’ed. FCA will be revised in November.
Provisional bill impacts: 208% increase from FY26 to FY55
FY 2036
FY 2035
FY 2034
FY 2033
FY 2032
FY 2031
FY 2030
FY 2029
FY 2028
FY 2027
FY 2026
Dashboard
2.0%
2.0%
2.0%
5.0%
5.0%
10.0%
15.0%
15.0%
15.0%
20.0%
12.0%
Usage Rate Increase
$ 6,039,416
$ 4,796,173
$ 656,941
$ 5,212,712
$ 9,680,613
$ 14,456,825
$ 24,211,545
$ 36,706,503
$ 31,759,034
$ 24,433,561
$ 16,293,191
Balance Excess/Deficiency
1.65
1.67
1.56
1.60
1.62
1.66
1.59
1.55
1.70
2.12
2.11
Debt Service Coverage
$1,838.62
$1,804.92
$1,771.88
$1,739.49
$1,662.37
$1,588.93
$1,455.39
$1,281.21
$1,129.75
$998.04
$851.70
Annual Bill SFR
38.60%
38.46%
39.09%
37.56%
36.48%
35.55%
35.54%
33.45%
27.12%
19.86%
15.42%
Debt Service/Revenue
$ 10,000,000
$ 10,000,000
$ 15,000,000
$ 15,000,000
$ 15,000,000
$ 20,000,000
$ 20,000,000
$ -
$ -
$ -
Cash Funded CIP
$ 1,447,815
$ 1,114,383
$ 4,927,781
$ 4,347,360
$ 3,783,845
$ 4,785,746
$ 4,063,831
$ 16,039,966
$ 15,572,782
$ 15,119,206
Debt Funded Project Costs
20
Note: At the time of this presentation, costs and allocations are being QA/QC’ed. MWRA rates will then be calculated, leading to refined Somerville rates.
Rate projections will be revised in November.
Next steps
21
Variance Waters CSO LTCP Update
22
2025
Activities
• Presentations to
MWRA Boards
• Finalize FCA
• Produce report
• Submit draft
recommended plan to
EPA and DEP by
December 31, 2025
2026
Activities
• Public mtg #6
on draft
recommended plan
• Public hearing and
public comment
period
• Additional outreach in
affected communities
• Team reviews
comments and
modifies plan
2027 and
Beyond
• Final plan submitted
January 2027
• EPA and DEP review
and set the plan for
further CSO control
• Design of projects
• Construction!
FY2027 Water & Sewer Rates
• Long-term Capital Investment Plan requirements
• DEP/EPA approval of January 2027 Final Plan will establish legally-
enforceable CIP for next 20+ years
• Somerville ust also consider critical pipeline rehabilitation and flood
mitigation components of CIP
• Future revenue requirements and enterprise fund health
• Critical to maintain financial metrics (debt service coverage, debt
service to revenue ratio, total debt, revenue vs. expenses) to maintain
bond rating
• Raise rates early to cash-fund future projects
• Prepare for annual rate increases of 15% to 20% for
next 4 to 5 years
23
Questions / Supplemental Slide Index
24
• Planning process Slide 27
• Community outreach & engagement Slide 28
• Tools for predicting CSO mitigation Slide 33
• Vocabulary: “Typical Year” and “Level of Control” Slide 38
• Alternatives, analysis & evaluation Slide 44, 48
• Eliminated alternative: Sewer separation Slide 53
• Upstream contributions & downstream constraints Slide 54
• Difficulties with & costs of sewer separation Slide 58
• Eliminated alternative: 25-Year level of control Slide 64
• Large storms causes multiple system failures resulting in sanitary pollution Slide 65
• Other sources of pollution and Charles/Alewife/Mystic water quality Slide 69
• Scale & cost of CSO control Slide 72
• Limitations of the Variance Water plan compared to success stories nationally Slide 77
• Local efforts outside of the Variance Water plan to improve water quality Slide 84
• Eliminated alternative: Lower level of control Slide 88
Council action on File ID 25-1451
• Straw poll
• “Does the Council support the recommended plan as presented,
including the proposed level of control and projected rate impacts?”
• Discussion
• Statements in support or opposed
• Item
• Place on file, or
• Keep open for further discussion
25
Supplemental Slides
Planning process
Mechanics of drafting a recommended plan
27
Community outreach and
engagement
Included in scope approved by DEP/EPA
28
CSO Plan Public Meetings
29
1.
CSO Control Plan Update - Public Mtg #1
June 29, 2022
2.
CSO Public Mtg #2 - 12-15-22
3.
Updated CSO Control Plan Public Meeting
#3 Cambridge, Somerville, MWRA 11-15-23
4.
Combined Sewer Overflow (CSO) Control
Planning Update – January 2025
5.
Updated Combined Sewer Overflow Control
Plan Public Meeting 5 - September 25, 2025
– YouTube
6.
Listening Session
(https://www.youtube.com/watch?v=k3jLXiO
Dafg)
CSO Plan Additional Engagement
• Monthly updates with DEP/EPA
• Workshops with CRWA, MyRWA & StAB
• October 2023 in person – Tools, typical year, process
• June 2024 in person – Alternatives development, mapping exercise
• December 2024 virtual – Alternatives development, cost assumptions
• September 2025 in person – Alternatives overview, evaluation criteria
• Asynchronous input through website and Menti polls
• Tabling at Civic Days and other events
30
City Council Presentations
City Council 22 May 2025 ID# 25-0966 –
CSOs, Updated LTCP, Examples &
Stormwater Billing Plan
City Council 13 March 2025 ID# 25-0510 –
Impacts of CSOs on Alewife Brook
31
Additional Resources
• Combined and Sanitary Sewer Overflow Control | City of
Somerville
• Combined Sewer Overflow Control Planning Program - Joint
efforts by Cambridge, MWRA, and Somerville | SomerVoice
• Save the Alewife Brook – environmental health is community
health
• It's Time to Cut the Crap — Charles River Watershed
Association
• Mystic River Watershed Association | MyRWA | Boston
32
Tools for predicting CSO
mitigation
Predicting CSO frequency and volumes for different size
storms for current and future conditions
33
Hydraulic model of sewer system
34
CAM007
CAM005
Cottage Farm
MWR201
MWR010
MWR020
MWR019
MWR018
CAM017
MWR023
Water quality model of receiving waters
Typical Year, design storms, and climate change
36
The presentation from public meeting # 2 includes more details on climate change and precipitation simulations. The
presentation from public meetings #3 and #4 includes details on resulting CSO frequency and volumes.
The presentation and recording is on the project webpage: https://voice.somervillema.gov/joint-cso-planning
Future Baseline Condition Model Results
Receiving
Water
CSO Discharge Volume (MG)
Activation Frequency
2050 25-year
Storm
(7.8 inches)
2050 5-year
Storm
(5.3 inches)
2050 Largest Storm
in the Typical Year
(3.3 inches)
2050 Typical
Year
Prior Typical
Year
2050
Typical
Year
Prior
Typical
Year
120.6
65.5
16.6
38.4
7.9
6
3
Charles
River
40.1
20.9
4.84
20.9
9.9
13
8
Alewife
Brook
27.2
17.4
10.5
29.3
1.3
8
2
Mystic
River
Looking into the future to select a ‘Preferred Alternative’ – the
2050 Typical Year and 2050 Design Storms
37
24-hr Precipitation Depths (in)
Cornell
20502,3
NOAA
Atlas 14
Baseline1
Return
Period
4.0
3.3
2-yr
5.3
4.3
5-yr
6.4
5.2
10-yr
7.8
6.3
25-yr
Total Depth: 10.3
in over 59 hours
6.2 (24-hr depth
around the peak)
March 2010
Total Depth: 5.2
in over 17 hours
5.2
Ida (Sept, 2021)
REFERENCES
1. Perica, S., Pavlovic, S., StLaurent, M., Trypaluk, C., Unruh, D., Martin, D. 2015. NOAA Atlas 14: Precipitation-Frequency Atlas of the United States; Volume 10 Version 3.0: Northeastern States. https://hdsc.nws.noaa.gov/hdsc/pfds/pfds_map_cont.html
2. Steinschneider, S., & Najibi, N. (2022). Observed and Projected Scaling of Daily Extreme Precipitation with Dew Point Temperature at Annual and Seasonal Scales across the Northeastern United States, Journal of Hydrometeorology, 23(3), 403-419.
https://journals.ametsoc.org/view/journals/hydr/23/3/JHM-D-21-0183.1.xml
3. Climate Resilience Design Standards & Guidelines. Climate Resilience Design Standards Tool. https://resilientma.org/rmat_home/designstandards/
•
Selected the 2050 planning horizon
for the CSO Control Plan (first in
the nation!)
•
Developed the 2050 Typical
Year (TY) as a rainfall series of
90 storms that range in intensity
and duration
•
Identified 2050 design storms
“Level of Control”
Term used to describe how big a storm the system will
handle
38
39
Four Levels of Control Being Evaluated
Hydraulic Model Predictions
Receiving Water
CSO Discharge Volume (MG)
Activation
Frequency
2050 25-year
Storm
2050 5- year
Storm
2050 Largest
Storm in TY
2050 TY
2050 TY
27.2
17.4
10.5
29.3
8
Upper Mystic
40.1
20.9
4.84
20.9
13
Alewife Brook
120.6
65.5
16.6
38.4
6
Charles River
40
Four Levels of Control Being Evaluated
Hydraulic Model Predictions
Receiving Water
CSO Discharge Volume (MG)
Activation
Frequency
2050 25-year
Storm
2050 5- year
Storm
2050 Largest
Storm in TY
2050 TY
2050 TY
27.2
17.4
10.5
29.3
8
Upper Mystic
40.1
20.9
4.84
20.9
13
Alewife Brook
120.6
65.5
16.6
38.4
6
Charles River
Level 1: Significantly reducing
CSO discharges from those
predicted to occur in a 2050 Typical
Year (“Limited CSO in 2050
Typical Year”)
41
Four Levels of Control Being Evaluated
Hydraulic Model Predictions
Receiving Water
CSO Discharge Volume (MG)
Activation
Frequency
2050 25-year
Storm
2050 5- year
Storm
2050 Largest
Storm in TY
2050 TY
2050 TY
27.2
17.4
10.5
29.3
8
Upper Mystic
40.1
20.9
4.84
20.9
13
Alewife Brook
120.6
65.5
16.6
38.4
6
Charles River
Level 2: No CSO in a
2050 Typical Year (“0
CSOs in 2050 Typical
Year”)
Level 1: Significantly reducing
CSO discharges from those
predicted to occur in a 2050 Typical
Year (“Limited CSO in 2050
Typical Year”)
42
Four Levels of Control Being Evaluated
Hydraulic Model Predictions
Receiving Water
CSO Discharge Volume (MG)
Activation
Frequency
2050 25-year
Storm
2050 5- year
Storm
2050 Largest
Storm in TY
2050 TY
2050 TY
27.2
17.4
10.5
29.3
8
Upper Mystic
40.1
20.9
4.84
20.9
13
Alewife Brook
120.6
65.5
16.6
38.4
6
Charles River
Level 2: No CSO in a
2050 Typical Year (“0
CSOs in 2050 Typical
Year”)
Level 1: Significantly reducing
CSO discharges from those
predicted to occur in a 2050 Typical
Year (“Limited CSO in 2050
Typical Year”)
Level 3: No CSO
in a 2050 5-year,
24-hour design
storm (“0 CSOs in
2050 5-year
storm”)
43
Four Levels of Control Being Evaluated
Hydraulic Model Predictions
Receiving Water
CSO Discharge Volume (MG)
Activation
Frequency
2050 25-year
Storm
2050 5- year
Storm
2050 Largest
Storm in TY
2050 TY
2050 TY
27.2
17.4
10.5
29.3
8
Upper Mystic
40.1
20.9
4.84
20.9
13
Alewife Brook
120.6
65.5
16.6
38.4
6
Charles River
Level 2: No CSO in a
2050 Typical Year (“0
CSOs in 2050 Typical
Year”)
Level 1: Significantly reducing
CSO discharges from those
predicted to occur in a 2050 Typical
Year (“Limited CSO in 2050
Typical Year”)
Level 3: No
CSO in a 2050
5-year, 24-hour
design storm (“0
CSOs in 2050
5-year storm”)
Level 4: No
CSO in a 2050
25-year, 24-
hour design
storm (“0 CSOs
in 2050 25-
year storm”)
Alternatives
Envisioning ways to reconstruct the sewer systems
44
CSO Reduction and Elimination Tools
45
The presentation from public meeting # 3 includes more details on each tool.
The presentation and recording is on the project webpage: https://voice.somervillema.gov/joint-cso-planning
Sewer Separation
Green Stormwater Infrastructure
Storage
Conveyance
Regional Tunnel
Developing CSO Control Alternatives
46
The presentation from public meeting # 4 includes more details on building alternatives.
The presentation and recording is on the project webpage: https://voice.somervillema.gov/joint-cso-planning
39 Alternatives Under Consideration
47
Number of Alternatives Under Consideration
Level of CSO Control
Charles River
(Lower):
9 CSO Outfalls
Mystic River
(Upper):
1 CSO Outfall
Alewife Brook:
6 CSO Outfalls
2
3
2
Limited CSOs in the 2050 TY
7
4
6
0 CSOs in the 2050 TY
2
3
2
0 CSOs in the 2050 5-Year Storm
2
3
2
0 CSOs in the 2050 25-Year
The presentation from public meeting # 5 describes 37 alternatives.
The presentation and recording is on the project webpage: https://voice.somervillema.gov/joint-cso-planning
Analysis & Evaluation
Examining the relative pro’s and con’s of alternatives
48
• Level of CSO control
• Permitting uncertainty
• Site acquisition risks
• Capital Cost and Life Cycle Cost
• Timeline to implementation/CSO benefits
• Impact on priority, vulnerable, and environmental justice
populations
• Benefits criteria
Preferred Alternative Selection Considerations
49
The presentation from public meeting # 5 provides details on the selection considerations.
The presentation and recording is on the project webpage: https://voice.somervillema.gov/joint-cso-planning
50
Benefits Criteria
Evaluation Criterion
Criteria Category
Water quality impact; improve/reduce phosphorus loads
CSO Performance
Schedule: minimize duration to CSO reduction benefit
Minimize construction impacts
Construction
•
Impacts to public uses during construction
•
Neighborhood impacts during construction
Minimize construction complexity/risk
•
Depth to excavation
•
Construction complexity
Operation and maintenance/safety considerations
Operations,
Maintenance &
Resiliency
Resiliency and adaptability
Opportunity to upgrade existing infrastructure
Flooding: reduce sewer/stormwater flood risk
Community & Ancillary
Benefits
Community co-benefits and long-term site impacts
•
Community co-benefits
•
Permanent impacts to public uses
Impacts to non-variance CSOs
Stakeholder Input
51
• Reduce / eliminate CSOs and sanitary sewer overflows
• Improve ecosystem health
• Include near-term improvement to the Alewife
• Maximize nature-based solutions when possible
• Provide meaningful benefits to EJ communities and abutters
• Have a short construction timeline
• Reduce flooding and flood risk
• Are site-able
• Allow for increased recreation
• Rehabilitate sewer infrastructure
• Are coordinated with other municipal plans and goals
• Minimize / Do not minimize neighborhood disruption during construction
• Prioritize / Do not prioritize cost and affordability to rate payers
The presentation from public meeting # 5 provides details on the selection considerations.
The presentation and recording is on the project webpage: https://voice.somervillema.gov/joint-cso-planning
Scoring example
52
Eliminated alternative:
Sewer separation
Full sewer separation seems like an obvious fix, why is
that not the recommendation?
53
Sewer separation does not
fully eliminate CSOs
Upstream contributions & downstream constraints
create CSOs in any storm larger than the Typical Year
54
Infiltration and Inflow (I/I)
55
*Source: 2025 MWRA I/I Report page 107.
0
5
10
15
20
25
Lexington
Belmont
Arlington
Medford
Cambridge
Somerville
Annual Average (mgd)
Estimated Area Flow Components
Sanitary
Infiltration
Inflow
Infiltration and Inflow (I/I)
56
*Source: 2025 MWRA I/I Report page 107.
0
5
10
15
20
25
Lexington
Belmont
Arlington
Medford
Cambridge
Somerville
Annual Average (mgd)
Estimated Area Flow Components
Sanitary
Infiltration
Inflow
Sewer separation only removes
combined inflow (and some infiltration)
Sewer separation ignores separate I/I
Regional system constraints
57
Sewer separation is very
difficult to achieve
The region grew around pipes from the 19th Century, the
replacement systems need to accommodate climate
change, and outfalls must mitigate stormwater pollution.
58
Multiple new outfall pipes, stormwater
storage tanks, pumping & treatment
59
Information on preliminary design Mystic River Outfall and Sewer Separation project: https://voice.somervillema.gov/mystic-river-outfall
Virtual community meeting 29 October 2025: https://us06web.zoom.us/webinar/register/WN_N2eQE99FRECRyJa6srkrqg#/registration
60
*Preliminary cost estimates are under review and subject to change.
6.AB Sewer Separation
5.MR Sewer Separation
7.CR Sewer Separation
Level of Control: 0 CSOs in 2050TY
Storage:
- Tanks: 0
- Tunnel: 0
- Microtunnel: 0
Key Features
Conveyance: 0
AB Sewer Separation: 900 acres
MR Sewer Separation: 690 acres
CRSewer Separation: 4,400 acres
GSI: with separation
Land Acquisition: Yes
Time to Complete: 50+ years
Preliminary Cost: $6,840 Million
• Any storm greater than the largest storm in the 2050 TY
storm produces CSOs!
S O M E R V I L L E F C A A N A L Y S I S
2024 FCA Guidance – Measure of Financial Burden
Alternative 1:
The financial impact of current and proposed
CSO controls on residential users
“Snapshot in time” of current & projected
system costs
Alternative 2:
Long-term financial plan and rate model
that evaluates the annual impacts of
current and proposed CSO controls.
Annual utility rate increases necessary to
fund the plan
Resulting annual residential customer bills
61
EPA has published guidance on how to complete an FCA and offers two
alternative approaches
Provisional FCA results
• Alt 1 Residential Indicator
• Cost per Household = 4.52% MHI – High Burden
• Alt 2 Residential Indicator
• Mid-Range Burden FY2029 through FY2033
• High Burden starting in FY2034
• Alt 2 Lowest Quintile Residential Indicator
• High Burden starting in FY2031
• EPA methodology indicates Somerville does not have the
financial capacity to undertake this plan on this schedule
and would need more than 50 years to complete it
62
Note: At the time of this presentation, costs and allocations are being QA/QC’ed. FCA will be revised in November.
Bill impacts: 673% increase from FY26 to FY55
63
Note: At the time of this presentation, costs and allocations are being QA/QC’ed. Rate projections will be revised in November.
FY 2036
FY 2035
FY 2034
FY 2033
FY 2032
FY 2031
FY 2030
FY 2029
FY 2028
FY 2027
FY 2026
Dashboard
3.0%
5.0%
10.0%
10.0%
15.0%
19.0%
29.0%
29.0%
30.0%
30.0%
12.0%
Usage Rate Increase
$ 6,733,895
$ 5,262,677
$ 3,726,979
$ 11,452,378
$ 31,270,018
$ 60,397,348
$ 72,556,918
$ 47,697,330
$
34,243,369
$ 26,656,046
$ 16,293,191
Balance Excess/Deficiency
2.64
2.66
2.53
2.37
2.25
2.02
1.79
1.63
1.59
1.75
2.11
Debt Service Coverage
$3,805.16
$3,697.82
$3,527.45
$3,217.68
$2,936.07
$2,568.76
$2,177.78
$1,715.18
$1,356.57
$1,071.21
$851.70
Annual Bill SFR
31.20%
30.97%
31.76%
33.13%
34.31%
37.26%
39.92%
39.71%
35.08%
26.52%
15.42%
Debt Service/Revenue
$ 80,000,000
$ 80,000,000
$ 80,000,000
$ 80,000,000
$ 80,000,000
$ 50,000,000
$ -
$ -
$ -
$ -
Cash Funded CIP
$ 26,746,055
$ 23,636,947
$ 20,618,395
$ 17,687,762
$ 14,842,488
$ 42,080,085
$ 89,398,141
$ 86,794,312
$
84,266,322
$ 81,811,963
Debt Funded Project Costs
Eliminated alternative:
25-Year level of control
We’re planning for the future, why not aim higher?
64
7.8 inches of rain in 24 hours
breaks the system
Even with CSO mitigation to the 25-year level of control,
sanitary flows contaminate neighborhoods and
waterways
65
66
67
68
Other sources of polution
69
These pollutants have negative impacts on water quality, environmental health,
and public health .
Eliminating CSOs alone does not result in swimmable and fishable waterbodies.
CSOs
Stormwater
Dry weather
•
Pathogens (bacteria,
viruses)
•
Oil and grease
•
Wipes
•
Nutrients (Phosphorus,
Nitrogen)
•
Pharmaceuticals
•
Industrial waste
•
Others
•
Pathogens (bacteria,
viruses)
•
Oil and grease
•
Nutrients (Phosphorus,
Nitrogen)
•
Trash
•
Others
•
Illicit connections
•
Leaky sewer pipes
•
Wildlife and dog
excrement
•
Decomposing leaves
Example sources of pollution in our waterbodies
Water Quality model results
71
Percentage Time Entire Modeled River is in Compliance with Previous Single Sample Maximum Criterion
Enterococcus (61#/100mL)
E. coli (235#/100mL)
Model Run
Stormwater
Only
CSO Only
Non-CSO
Sources
All Sources
Stormwater
Only
CSO
Only
Non-CSO
Sources
All
Sources
Alewife Brook
38%
99%
35%
35%
38%
99%
36%
36%
2050 Typical
Year
Mystic River
46%
95%
30%
30%
46%
96%
45%
45%
2050 Typical
Year
CSO Projects for 25-Year
level of control
72
Alewife Brook
Pump Station
MWR003
Fresh Pond
Little
Pond
Spy
Pond
CAM401
B
Alewife 41.6 MG CSO
Storage Tunnel
32-ft. diameter
CAM401A CSO Conveyance to
Storage Tunnel
CAM401A
SOM001
A
CAM00
1
Dilbo
y
Field
TBM Mining Shaft
and Dewatering
Pump Station
TBM Retrieval
Shaft and Odor
Control Facility
CAM00
2
Not to Scale
N
Legend:
Combined Sewer System Facility
CSO Outfall
CSO Storage Tunnel Drop Shaft
Storage Tunnel
Near-surface Conveyance
11.AB Tunnel
Level of Control: 0 CSOs in 2050,
25-Year Storm
Storage:
- Tanks: 0
- Tunnel: 1.5 miles long, 32 ft
dia.
- Microtunnel: 0
Key Features
Conveyance: 0.75 miles long
Sewer Separation: 0
GSI: with street excavation
Land Acquisition: Yes
Time to Complete: 12-15 years
Preliminary Cost: $1,700 Million
95 Acres of Sewer
Separation
Mystic
River
Legend:
Combined Sewer System Facility
CSO Outfall
CSO Storage
Sewer Separation
Mystic
River
Somerville
Marginal
CSO Facility
DeLauri
Pump
Station
MWR20
5
SOM007A
/
MWR205A
SOM007A/MWR205A
14.2 MG Storage Tank
Stormwater Trunk
Line to Mystic River
12.MR Hybrid 1
Level of Control: 0 CSOs in 2050,
25-Year Storm
Storage:
- Tanks: 1
- Tunnel: 0
- Microtunnel: 0
Key Features
Conveyance: 0
Sewer Separation: 95 acres
GSI: with separation/ other
street excavation
Land Acquisition: Yes
Time to Complete: 5-10 years
Preliminary Cost: $340 Million
Not to Scale
N
CAM00
5
CAM00
7
MWR01
0
MWR20
1
CAM017
MWR20
3
RE046-
19
RE046-
30
RE046-
381
RE046-
100
RE046-
105
RE046-54
RE046-55-1
MWR02
3
Not to Scale
N
Legend:
Combined Sewer System Facility
CSO Outfall Tributary to Charles River
CSO Outfall Tributary to Boston Harbor
RE046 CSO Regulator
CSO Storage Tunnel Drop Shaft
CSO Storage
CSO Storage Tunnel
CSO Storage Conduit
RE046-
62A
Bosto
n
Harbor
Ward Street
Headworks
Facility
Prison Point
CSO Facility
MWR01
8
MWR02
0
TBM Mining Shaft
and Dewatering
Pump Station
MWR01
9
132 MG CSO
Storage Tunnel
32 ft. diameter
0.05 MG Storage
Conduit
2.22 MG
Microtunnel Storage
Not to Scale
N
12.CR Tunnel
Level of Control: 0 CSOs in 2050,
25-Year Storm
Storage:
- Tanks: 0
- Tunnel: 4.5 miles long
- Microtunnel: 1 mile long, 9 ft dia.
- Conduit: 1
Key Features
Sewer Separation: 0
GSI: with street excavation
Land Acquisition: Yes
Time to Complete: 15-20 years
Preliminary Cost: $2,600 Million
Bill impacts: 347% increase from FY26 to FY55
76
Note: At the time of this presentation, costs and allocations are being QA/QC’ed. Rate projections will be revised in November.
FY 2036
FY 2035
FY 2034
FY 2033
FY 2032
FY 2031
FY 2030
FY 2029
FY 2028
FY 2027
FY 2026
FY 2025
Dashboard
2.0%
2.5%
3.0%
8.0%
13.5%
16.0%
22.0%
22.5%
23.0%
23.0%
12.0%
N/A
Usage Rate Increase
$ 869,548
$ 3,386,967
$ 2,755,596
$ 6,070,403
$ 10,409,732
$ 4,071,708
$ 2,001,801
$ 392,989
$ 253,001
$ 1,124,577
$ 16,293,191
$ 10,686,098
Balance Excess/Deficiency
2.04
2.11
2.05
2.10
2.06
1.94
1.80
1.70
1.76
2.08
2.11
1.90
Debt Service Coverage
$2,653.25
$2,603.58
$2,543.00
$2,472.43
$2,298.18
$2,039.10
$1,774.39
$1,476.06
$1,226.99
$1,019.99
$851.70
$817.59
Annual Bill SFR
36.70%
35.80%
35.62%
34.36%
34.27%
35.01%
35.68%
34.11%
28.57%
20.72%
15.42%
14.97%
Debt Service/Revenue
$ 40,000,000
$ 40,000,000
$ 40,000,000
$ 40,000,000
$ 25,000,000
$ 22,000,000
$ 15,000,000
$ 10,000,000
$ 10,000,000
$ 24,000,000
Cash Funded CIP
$ 24,414,285
$ 22,538,141
$ 20,716,642
$ 18,948,196
$ 32,231,258
$ 33,564,328
$ 38,945,950
$ 42,374,708
$ 40,849,231
$ 25,368,186
Debt Funded Project Costs
Still Mid-Range Burden for Somerville. Other MWRA communities TBD
Comparison to plans in other
regions
If other cities can do it, why can’t we?
77
Variance water
combined sewer
area
• 9 square miles
78
Philadelphia
GSI Solutions
• 143 square miles
• 143 square miles
79
New York City DEP
GSI Solutions
• 299 square miles
80
Washington DC
Stormwater
Solutions
• 982 square miles
81
Milwaukee Metro
Sewer District
Stormwater Solutions
& Flood Control
• 350 square miles
82
Responsibilities & opportunities
CSOs, stormwater & overall water quality
83
Efforts outside the Variance
Waters CSO LTCP Update
84
Somerville Stormwater Fee & Credits
• Program is designed in incentivize on-site stormwater management
85
See City Council 22 May 2025 meeting ID# 25-0966 for details.
IAM-Engineering is working on public outreach materials. Please stay tuned.
Cambridge City Council
Policy Order 2025 #136
• Consider costs & benefits of meeting 2050 25-year level
of control
• Update stormwater regulations for private development
• Public outreach on sewer/stormwater investments
• Create Combined Sewer Overflow Commission
86
Pending legislation
• In Joint Committee on Environment and Natural Resources
• S.608/H.1031 - An Act Relative to Combined Sewer Overflows
• H.1046 – An Act to Eliminate Combined Sewer Overflows in
Massachusetts Waterways
• S.658/H.3938 – An Act Pertaining to Regional Resilience and Flood
Protection Entities
• In Joint Committee on Housing
• S.1014 – An Act to Provide Sewer & Water Rate Relief
87
Eliminated alternative:
Lower level of control
Why not submit a modest mitigation plan that minimizes
rate impacts?
88
Marginal cost savings do not justify discharge
89
$800
$1,800
$2,800
$3,800
$4,800
$5,800
$6,800
FY 2026
FY 2028
FY 2030
FY 2032
FY 2034
FY 2036
FY 2038
FY 2040
FY 2042
FY 2044
FY 2046
FY 2048
FY 2050
FY 2052
FY 2054
Annual SFR Sewer Bill
Recommended plan = 3.1x FY26 rates
25-Year control = 4.5x FY26 rates
Sewer Separation, TY control = 7.7x FY26 rates
Lower control = 2.8x FY26 rates
Draft Combined Sewer Overflow
Updated Long Term Control Plan
File ID 25-1451 Officer’s Communication
to City Council
Infrastructure & Asset Management
23 October 2025