Matters ▸ Attachment
Somerville Museum CPC Off-Cycle request - $98,053 — File 23-1203
7/19/23, 10:12 PM
Mail - Roberta Cameron - Outlook
https://outlook.office365.com/mail/inbox/id/AAMkADRhYjZjZjg2LThmNjktNDc4OC04NzM5LWNlYjhkN2M2ZjBiOQBGAAAAAACfcPhbZDNKSLNOhgm…
1/2
Memorandum requesting additional funds for the Somerville Museum Care of Historic
Collections Project (FY22 Renovation of Collection Storage)
Barbara Mangum <[email removed]>
Wed 7/19/2023 6:28 PM
To:Roberta Cameron <rcameron@somervillema.gov>
Cc:Alison Drasner <[email removed]>
2 attachments (276 KB)
Stack Scehdule Extension - Cost with adjusted Change Order (1).pdf; CPA FY22 Budget amendment 2 request 7_16_2023.xls;
This email is from an external source. Use caution responding to it, opening attachments or clicking links.
Hi Roberta,
Attached please find my budget for the Museum's collection storage renovation project and how it has
changed since our inception just two years ago. The project is now substantially complete and will be a
tremendous improvement in the use of the collections for the education and delight of the people of
Somerville. However, as you can see from the attached bill from our contractor Stack Design/Build, we
have had change orders amounting to $81,905 and another $38,000 (estimate) of work to be done on 7
windows at the basement level: removing brick and masonry to allow the reinsertion and waterproofing
of 3 painted wooden windows nearly identical to those that were earlier removed as a result of the
renovation project and another 4 that on inspection were found to be in dire need of repair.
The work on the windows requires some explanation. The basement at the Museum required extreme
waterproofing due to the amount of water traveling under the building. This had brought about mold
conditions in the collection storage area that were unsafe for both volunteers and staff, but also for the
preservation of the collections. As part of the collection storage renovation project, four original
hopper/basement windows were removed: one from the Central Street side and three from the north side
that faces a small alley between the Museum building and the neighbors. The Museum received a
certificate of appropriateness from the Somerville Historic Preservation Commission in 2022 to remove
the windows and brick them in, removing a potential source of water leakage from the storage area.
The Museum is grateful to have been awarded a grant of $140,000 from the Massachusetts Cultural
Facility Fund/Mass Development toward the costs of the collection storage space renovation. One of the
facets of the MCFF grant projects is that it is a reimbursement program. Therefore, the Museum had to
expend all $140,000 of the award prior to requesting the grant and did not do so until about March. In
April, the Museum filed a project notification form with the Massachusetts Historical Commission
(MHC). This was required to receive the funds. To our surprise, the MHC differed with the SHPC about
the removal of the windows and required that three of the four basement level windows be restored back
into the Museum's foundation. The Museum is now working with our contractor to undertake this work
prior to winter. In addition, in examining this issue, deficiencies were found in the remaining 4 original
hopper windows. For reasons of closing out the collection renovation project under the current building
permit, as well as not wanting to change contractors mid-stream, the Museum proposes to restore the
three original windows and conserve/repair the other four original windows at the same time. We have
been keeping Sarah White of the SHPC informed of the project's development and are now applying to
the SHPC for a permit for appropriateness for this new phase of the project.
As a result of these increased costs, we are hoping that the CPC will consider out of cycle funding for the
Museum in the amount of $98,053. This will enable the Museum to pay the final bills to the contractor
7/19/23, 10:12 PM
Mail - Roberta Cameron - Outlook
https://outlook.office365.com/mail/inbox/id/AAMkADRhYjZjZjg2LThmNjktNDc4OC04NzM5LWNlYjhkN2M2ZjBiOQBGAAAAAACfcPhbZDNKSLNOhgm…
2/2
and finish the work required on the windows this Fall.
As a private mostly volunteer run nonprofit, we are bringing as many varied sources of income as we can
to support the project including the funds from the MCFF noted above, $65,000 in two grants from the
Cabot Family Charitable Trust as well as about $55,000 in volunteer time and efforts. Our Capital
Campaign has raised over $2m to support the transformation of the Museum to date. However, as we are
in the last phase of the campaign, it is getting harder to come up with new sources of income. In addition
to the usual expenses incurred in a project like this, the Museum has also spent over $57,000 on storage
over the past 2.5 years with Gentle Giant and currently, is paying for the return of the collections.
Please let me know if I should send a more formal request to the CPC board about this matter. I am
trying to make the deadline of getting this out to you today, hence the email.
Many thanks for your help in this and other matters,
Barbara Mangum
President of the Board of Trustees
Somerville Museum
1 Westwood Road
Somerville, MA 02143
Change order Number
Change Order Title
Current change
order cost
GC Reduction amount
(includes 1.5% insurance
& 5% Fee)
Revised CO Subtotal
12.5% Markup
on CO
New Total cost
of Change Order
1
Rework Plumbing Connection to Radiators
$6,373.19
$393.19
$5,980.00
$747.50
$6,727.50
2
Demo & Dispose of Metal Door @ Vault
$1,678.39
$103.55
$1,574.84
$196.86
$1,771.70
3
Renovation of Vault Room
$13,775.99
$905.77
$12,870.22
$1,608.78
$14,479.00
4
Additional Repair of heating units
$3,915.57
$849.89
$3,065.68
$383.21
$3,448.89
7
Temp Light Fixtures
$2,443.77
$150.76
$2,293.01
$286.63
$2,579.64
8
HVAC Scope Gap
$5,504.60
$339.60
$5,165.00
$645.63
$5,810.63
10
Moving Existing Condensate pipe
$2,749.64
$169.64
$2,580.00
$322.50
$2,902.50
11
Added walls & Ceiling Work
$24,412.06
$1,506.00
$22,906.06
$2,863.26
$25,769.32
12
Door Hardware & Lock
$358.09
$22.09
$336.00
$42.00
$378.00
5 & 13
Added 6 Weeks of schedule
$35,809.20
$35,809.20
$16,033.65
$2,004.21
$18,037.86
$97,020.50
$40,249.69
$72,804.46
$81,905.02
Total of CO excluding Scheudle Extension
$61,211.30
Total owed by SVM
to Stack
$20,693.72
Somerville Museum FY2022:
Improved Care of Historic
Collections
comments
Non-CPA
contribution
CPA Contribution
Total
Non-CPA
contribution
CPA Contribution
Total
Non-CPA
contribution
CPA Contribution
Total
SOURCES:
Museum capital campaign
Museum Inkind contributions
(volunteers and 10% overhead)
$81,499
$81,499
$81,499
$81,499
$111,101
$111,101
MCFF/MassDevelopment
$140,000
$140,000
$140,000
$140,000
$140,000
$140,000
Cabot Family Charitable Trust
$40,000
$40,000
$40,000
$40,000
$65,000
$65,000
Total
$261,499
$157,352
$418,851
$261,499
$257,352
$518,851
$316,101
$355,405
$671,506
if $98,053 is
approved in out of
cycle funding
EXPENSES:
Hard Costs
Stack+Co. Construction Contract
Project Requirements
$13,865
$13,865
Demo and make safe -removal of
existing electrical
$7,500
Demolition and removal of existing
walls, heating elements
$6,200
$13,050
$13,050
Demolish and dispose of vault
$8,200
$0
$0
Drill holes in existing (concrete floor)
slab and pour new 4" slab throughout
balance of basement
$12,790
$15,000
$15,000
Masonry
$10,050
$10,050
Rough Carpentry
$6,100
$6,100
Drainage mat on floors and walls
$6,870
$7,680
$7,680
Doors, Frames, Hardware
$6,600
$6,600
Metal studs and drywall walls around
perimeter
$18,645
$36,500
$36,500
Epoxy paint on concrete floor
$3,500
$791
$1,209
$791
$1,209
Scrape and paint of ceiling and walls.
$5,605
$6,000
$6,000
Allowance for installation of new
sump pump
$4,000
$8,480
$8,480
HVAC assistance allowance
$3,500
$67,500
$67,500
Vapor Barrier underneath concrete
$3,250
$0
$0
Electrical/FA allowance
$16,500
$33,820
$33,820
CPA FY 2022 application budget
9/30/2021
CPA FY 2022 budget 7/14/2022
CPA FY 2022 budget 7/16/2023
Allowance for
trenching/excavation/backfill for new
interior perimeter (french) drain
$8,500
$0
$0
8 weeks of Super time
$32,000
Senior management time
$12,800
General Conditions
$44,800
$44,800
Subtotal
$149,859
$239,504
$239,504
insurance
$4,072
$4,072
5% profit
$7,493
$13,776
$13,776
Subtotal Demo and Renovation of
Collection Storage
$157,352
$31,941
$257,352
$289,293
$31,941
$257,352
$289,293
Change Orders from 1/1/2023-
5/31/2023
$81,905
$81,905
Change Order for Repair/Restoration
of the Museum's 1930s Basement
Windows including 3 located in the
collection storage area.
$21,852
$16,148
$38,000
HVAC fof collection storage,
including HVAC engineer costs
$63,250
$63,250
$63,250
$63,250
$63,250
$63,250
Supplies for stabilizing collections
$5,000
$5,000
$5,000
$5,000
$10,000
$10,000
Storage Furniture
$46,800
$46,800
$46,800
$46,800
$65,000
$65,000
Subtotal Hard Costs
$115,050
$115,050
$146,991
$404,343
$160,102
$98,053
$258,155
Soft Costs
R Graf, Owner's Representative and
architectural consultant
$12,000
$12,000
$12,000
$12,000
$4,300
$4,300
P. Quinn, Architect and firm
$35,000
$35,000
$35,000
$35,000
$41,545
$41,545
B.Mangum, Art Conservator and
Project Manager
$11,700
$11,700
$11,700
$11,700
$11,700
$11,700
Building permit for east end basement
work
$3,943
$3,943
$0
$0
$0
$0
Builder's Risk Insurance
$3,362
$3,362
$3,362
$3,362
$3,362
$3,362
Subtotal Soft Costs
$66,005
$66,005
$62,062
$62,062
$60,907
$0
$60,907
Total Soft and Hard Renovation
Project Cost
$181,055
$157,352
$338,407
$209,053
$257,352
$466,405
$252,950
$355,405
$608,355
10% Contingency
$40,300
$40,300
$7,600
this is 20% of the
window project as the
other projects are
mostly completed
Total Project Cost before Inkind
$221,355
$157,352
$378,707
$209,053
$257,352
$466,405
$260,550
$355,405
$615,955
Additional in-kind museum
contribution and indirect costs*
$81,499
$81,499
$81,499
$81,499
$111,101
$111,101
Total Renovation Project Cost with
in-kind contributions
$302,853
$157,352
$460,205
$290,552
$257,352
$547,904
$371,651
$355,405
$727,056
% contributions
66%
34%
100%
53%
47%
100%
51%
49%
100%
*In-kind contributions
Barbara Mangum Administration
(volunteer)
$15,600
$15,600
$15,600
$15,600
$17,753
$17,753
Museum in kind contributions:
Evelyn Battinelli (Executive
Director/Exec Dir. Emeritus)
$5,720
$5,720
$5,720
$5,720
$5,720
$5,720
Museum in kind contribution:
Treasurer
$2,600
$2,600
$2,600
$2,600
$2,845
$2,845
Alison (Asst. Director/Executive
Director)
$2,860
$2,860
$2,860
$2,860
$6,240
$6,240
Volunteers: Collection Care
Committee ( 1 volunteer @
$28.45/hr * 3 hrs/day* 5 days*26
weeks)
$11,096
$11,096
$11,096
$11,096
$11,096
$11,096
Cost of collection storage offsite
during construction and transport
of the collections back to the
Museum by Gentle Giant.
$33,623
$33,623
$57,448
$57,448
cash contribution
Total inkind contributions
$71,499
$71,499
$71,499
$71,499
$101,101
$101,101
Total indirect costs (capped at $10k)
$10,000
$10,000
$10,000
$10,000
$10,000
$10,000
Subtotal inkind contributions and
indirect costs
$81,499
$81,499
$81,499
$81,499
$111,101
$111,101