PROJECT DESCRIPTION
In FY23 the Somerville Hispanic Association for Community Development received a $425,000 CPA
grant intended to restore second floor windows and gutters and to continue masonry work to preserve
the envelope of the former Grace Baptist Church located at 59 Cross Street. Subsequently SHA4CD was
awarded ARPA funds to install an elevator and handicapped accessible bathrooms, as the building is
required to come into compliance with ADA. As the full cost for the accessibility improvements exceeds
the ARPA award, SHA4CD requests to use the CPA funds that were awarded in FY23 to prioritize
completion of the elevator installation before continuing with restoration of the exterior envelope.
ALIGNMENT WITH FY24 COMMUNITY PRESERVATION PLAN
The Community Preservation Plan prioritizes historic resources projects that make historic public and
institutional buildings safe and accessible, so that they are functional for their intended use. The
Community Preservation Plan further emphasizes strategically‐advantageous projects that improve
accessibility and support Somerville’s vulnerable populations. The Grace Baptist Church building
requires accessibility improvements to comply with the Americans with Disabilities Act, and to better
serve the volunteers and patrons of the food pantry and other community services provided in the
building. While the exterior envelope renovation remains a critical outstanding need, coordination with
the project funded by ARPA presents a time‐sensitive opportunity to address accessibility
requirements.
RECOMMENDATION
On October 25, 2023 by a vote of 7‐0, the Community Preservation Committee recommended
reallocating $425,000 from the FY23 grant to the Somerville Hispanic Association for Community
Development that was planned for exterior envelope restoration to instead make accessibility
improvements to 59 Cross Street.
FUNDING CONDITIONS FROM FY23 GRANT
The CPA‐funded portion of the project must be initiated within three years unless an extension
is granted by the CPC.
CPA funds will be used only for CPA eligible expenses.