Matters ▸ Attachment
217 Somerville Avenue (Open Space lot) FY24 — File 23-1849
Project Title:
Project Address:
Department:
Project Mgr.:
Email:
New Project or Modification:
Department Priority:
Rank your project(s) in order of priority from your point of view. If you propose four projects, rank them 1, 2, 3, 4, with 1 being the highest, and so forth.
Project Description/Scope of Work:
Justification:
Relationship to Other Projects:
Category: Please check all appropriate boxes
Architectural/Engineering Feasibility Study
Architectural/Engineering Construction Document Services & Construction Admin
Building Alteration/Repair/Renovation/Addition/New Construction
Building Improvements (non-construction)
Purchase of Equipment (incl. vehicles, office equipment, hardware, etc.)
Information Technology Systems/Platforms (e.g. cloud based, internet based, etc.)
Street/Sidewalk/Monument Improvements
Water Improvements
Sewer Improvements
Land Development
Land Acquisition
Land Disposition
Parks and Open Space
Other
Operational Impact:
What impact will this project have on operational costs?
Reduce Cost (greater than 5%)
Reduce Cost (less than 5%)
Cost Unchanged
Increase Cost (less than 5%)
Increase Cost (greater than 5%)
217 Somerville Ave
FORM A ‐ DESIGN & CONSTRUCTION
CAPITAL IMROVEMENT PROJECT (CIP) REQUEST ‐ FY24
Jon Bronenkant
jbronenkant@somervillema.gov
The estimated increase to existing operation costs will vary depending on the final design and concept of the space. However, as this will
be a new publicly accessible open space it will require routine maintenance and upkeep in line with the similar level of routine
maintenance provided to existing city owned parks and open spaces.
217 Somerville Ave (Open Space lot)
The project received a CPA award of $100K to begin the public engagement and design process for the final open space concept for the
lot. As the large scale developments in the adjacent Union Square and Boynton Yards transformation districts continue to come online
the need for dedicated open space in this district becomes increasingly critical to mitigate the impacts of urban heat island effects and
provide recreational and open space accessibility for the neighboring constituents.
The project will create a new community pocket park on the 217 Somerville Ave site along the eastern portion of Union Square. The funds
will be used for landscape construction and installation of features such as benches, tables, playground equipment, and other passive
recreational amenities. The funding will also go towards the installation of stormwater management and other green infrastucture as
well as construction administration services.
OSPCD - PSUF
The project will compliment the long planned transformation development that is underway in the adjacent Union Square and Boynton
Yards districts. These developments will significantly increase the density of the neighborhood amplifying the need and urgency to have a
quality accessible open space amenity for the local constituency.
Desirable
New Project
Third
Design and Construction Project Funding
Total Estimated Cost
Prior Years
Funding
FY 24
FY 25
FY 26
FY 27
FY 28
Capital Costs:
Feasibility Study
$ -
Land Acquisition/Appraisal
$ -
-
- - - - -
Environmental Remediation/LSP
$ -
Demolition & Site Clearance
$ -
-
- - - - -
Owner's Proj. Mgr./Clerk of the Works
$ -
Designer Services (SD through CA)
$ 100,000 - 100,000
Construction
$ 1,200,000 - 600,000
600,000
- -
Insurance (builder's risk, addtl. Polices)
$ -
- -
Furniture & Equipment (FFE)
$ -
Police Details
$ -
- -
Contingency
$ 300,000
300,000
Other (Specify)
$ -
-
- - - - -
Other (Specify)
$ -
-
- - - - -
Total:
$ 1,600,000 $ ‐ $ 700,000 $ 900,000 $ ‐ $ ‐ $ ‐
Please provide suggested sources. This section will be finalized jointly by Finance and the Department.
Funding Sources:
Prior Years
Funding
FY 24
FY 25
FY 26
FY 27
FY 28
Stabilization Fund
$ -
$ - $ -
$ -
$ - $ -
$ -
GO Bonds
$ 1,000,000 - 600,000
400,000
- -
Retained Earnings
$ -
General Fund
$ -
Special Assmnt.
$ -
-
- - - - -
Ch. 90
$ -
Grants
$ 500,000 -
-
500,000 - - -
Receipts Reserved
$ -
Other (CPA)
$ 100,000
100,000 - - - -
Other (Specify)
$ -
-
- - - - -
Total:
$ 1,600,000 $ ‐ $ 700,000 $ 900,000 $ ‐ $ ‐ $ ‐
Evaluation Committee Use Only:
Reviewed and Approved By:
Version
Requesting Department
Date
Draft
Auditing
Date
Revised
Purchasing
Date
Accepted
Final Approval
Project currently has CPA funding to complete design however no additional funding beyond that.