Matters ▸ Attachment
Committee Report - Finance 7-7-10 — File 189884
July 7, 2010
Finance Committee
Page 1 of 3
Printed 7/8/2010
REPORT OF THE FINANCE COMMITTEE
Attendee Name
Title
Status
Arrived
Maryann M. Heuston
Chair
Present
William A. White Jr.
Vice Chair
Present
John M Connolly
Alderman At Large
Present
Rebekah L. Gewirtz
Ward Six Alderman
Absent
Bruce M Desmond
Alderman
Present
Dennis M. Sullivan
Alderman At Large
Present
Gerald Boyle
Project Manager
Present
Paul Trant
Captain
Present
Doug Willardson
Analyst
Present
189166 - Requesting Approval to Expend a $150,000 Grant from the MA Exec. Office of
Public Safety and Security and the State 911 Regional Public Safety Communications
Center to Conduct a Feasibility for a Regional Emergency Communications Center.:
This item had been sent back to committee for further review.
RESULT:
APPROVED
189620 - Requesting an Appropriation of $57,600 from the Capital Stabilization Fund for
the Purchase of Recycling Carts.:
RESULT:
KEPT IN COMMITTEE
Next: 12/31/2010 12:00 AM
189865 - Request to Declare (16) Police Vehicles as Surplus.:
Captain Trant stated that these vehicles were obtained via drug forfeitures and that they are all
considered either junk or un-repairable.
RESULT:
APPROVED
189863 - Requesting Approval to Extend the Contract of Johnson Roberts Associates to
12/31/10:
Committee Meeting
July 7, 2010
Finance Committee
Page 2 of 3
Printed 7/8/2010
Mr. Boyle told the members that the city would not incur any additional cost by extending the
contract.
RESULT:
APPROVED
189864 - Requesting Approval to Extend the Contract of TBA Architects, Inc. to 12/31/10:
Mr. Boyle told the members that the city would not incur any additional cost by extending the
contract.
RESULT:
APPROVED
189857 - Requesting Approval to Proceed with CM-At-Risk Delivery Method for ESCS
Renovation Project:
This program would help to stop construction delays and allow projects to be completed 3 to 6
months sooner than with the traditional design/bid/build process. The CM-At-Risk process
allows the city to negotiate a no bid contract. At the end of the schematic design stage, CM-At-
Risk would determine the construction cost and provide an estimate for the project. If the figures
don't agree, the city is free reject the process, but would then have to begin the traditional
process. CM-At-Risk is a transparent process that uses the city's bottom line in calculating the
cost of a project and provides the city with the ability to see the costs. All CM-At-Risk projects
are overseen by the Attorney General's Office.
RESULT:
APPROVED
189859 - Requesting Appropriation of $50,000 from Receipts Reserved for Appropriation-
Insurance Losses to East Somerville Community School Reconstruction for an
Independent Cost Estimator for the ESCS Project:
RESULT:
APPROVED
189861 - Requesting Approval to Extend the Contract of Symmes Maini & McKee at the
Argenziano School Project to Assist with the Administration of a Grant to Install Solar
Panels:
The city needs time to put this out for bid and would incur no additional cost by extending the
project.
RESULT:
APPROVED
Committee Meeting
July 7, 2010
Finance Committee
Page 3 of 3
Printed 7/8/2010