Matters ▸ Attachment
Committee Report - Finance - 8-23-11 — File 191832
August 23, 2011
Finance Committee
Page 1 of 2
Printed 8/24/2011
REPORT OF THE FINANCE COMMITTEE
Attendee Name
Title
Status
Arrived
Maryann M. Heuston
Chair
Present
William A. White Jr.
Vice Chair
Present
John M Connolly
Alderman At Large
Present
Rebekah Gewirtz
Ward Six Alderman
Present
Thomas F. Taylor
Ward Three Alderman
Absent
Robert C. Trane
Ward Seven Alderman
Present
Omar Boukili
Administrative Assistant
Present
Doug Willardson
Auditing
Present
David Lutes
OSEP
Present
Kevin Kelleher
Chief Fire Engineer
Present
Robert May
OSPCD
Present
Stan Koty
DPW Commissioner
Present
191746 - Requesting an appropriation of $80,000 for the purchase of new radio equipment
and authorization to borrow $80,000 in a bond to meet said appropriation.:
This expense is being bonded, for a short term, to take advantage of the current low interest rates.
Chief Kelleher spoke about the FCC mandates regarding narrow band frequencies and told the
members that there may be some grant money that could be used to help pay for the needed new
equipment. Additional upgrades to the infrastructure will be needed next year at a cost of about
$70,000.
RESULT:
APPROVED
191753 - Requesting acceptance of a $140,494 grant from FEMA’s Assistance to
Firefighters program, for the Fire Dept. to meet new FCC radio requirements.:
RESULT:
APPROVED
191785 - Requesting the approval of a ten year “Zero Sort” contract with Casella Recycling
LLC.:
Committee Meeting
August 23, 2011
Finance Committee
Page 2 of 2
Printed 8/24/2011
Mr. Lutes explained that Casella Recycling needs to have a ten year contract in order to justify
their cost in this program. Under the terms of the contract, the revenue would be split, with 60%
going to Casella and 40% going to the city. The carts used in the program would belong to
Casella until the end of the ten year contract, at which time they would be gifted to the city.
Alderman White requested to see the figures used in calculating the city's projected revenue and
requested that language be included in the contract giving the city the right to audit the records
that impact the city's share of revenue.
The committee requested that the following be added to the contract:
1. a definition of ACR,
2. audit rights of city on trucks and
3. a second option for a 50/50 revenue share
RESULT:
KEPT IN COMMITTEE
191786 - Requesting extension of a Contract with Howard/Stein-Hudson Inc., to August 30,
2012, to complete the Union Sq. roadway/streetscape improvement design plan.:
Mr. May explained that there have been delays with the project and he spoke about the peer
review undertaken by MIT. Chairman Heuston stated that neither she, nor Alderman Taylor, like
the proposed design and feel that it would hurt the businesses in Union Square. Mr. May stated
that the cost of the contract extension would be $370,000 and that without it, the city would not
be able to redesign the plan. Chairman Heuston expressed her desire to meet with the area's
business community first, and then with the neighbors, to obtain their input.
RESULT:
KEPT IN COMMITTEE
191795 - Requesting an appropriation of $25,000 from the Capital Projects Stabilization
Fund to fund architectural and engineering services for an ice rink at Lincoln Park.:
RESULT:
KEPT IN COMMITTEE