FY12-16 CIP — File 192074
Capital Investment Plan
Fiscal Years 2012‐2016
City of Somerville
Massachusetts
Mayor Joseph A. Curtatone
City Government
Joseph A. Curtatone, Mayor
Edward Bean, Finance Director
Doug Willardson, Budget Analyst
Board of Aldermen
Rebekah L. Gewirtz, President, Ward 6
Thomas F. Taylor, Vice President, Ward 3
Dennis M. Sullivan, At‐large
John M. Connolly, At‐large
William A. White Jr., At‐large
Bruce M. Desmond, At‐large
William M. Roche, Ward 1
Maryann M. Heuston, Ward 2
Walter F. Pero, Ward 4
Sean T. O' Donovan, Ward 5
Robert C. Trane, Ward 7
City of Somerville, Massachusetts
3
Table of Contents
Capital Plan Overview..............................................................................................................................6
Capital Planning Process.........................................................................................................................7
Sources of Funding....................................................................................................................................9
Capital Investment Plan Financing Policies................................................................................. 11
FY2012 Capital Financing Strategy................................................................................................. 12
General Fund Debt Service .......................................................................................................... 13
Assembly Square Stabilization Fund‐Supported Debt Service.................................... 15
Veteran’s Memorial Ice Rink Enterprise Fund Supported Debt Service.................. 16
Water/Sewer Enterprise Fund Supported Debt Service................................................ 17
Capital Stabilization Fund............................................................................................................ 17
State and Federal Funds or Grants........................................................................................... 19
District Increment‐Supported Debt Service......................................................................... 20
FY2013‐2016 Suggested Capital Projects and Funding Sources........................................ 21
Individual Project Descriptions ........................................................................................................ 25
Private Way Reconstruction ....................................................................................................... 26
Benches & Barrels Reconstruction........................................................................................... 27
Conway 2nd Ice Rink...................................................................................................................... 28
Conway Ice Rink Locker Rooms................................................................................................ 29
Christmas Decorations .................................................................................................................. 30
Lincoln Park Sports Complex...................................................................................................... 31
Kenny Park Design.......................................................................................................................... 32
Winter Hill Play Area Design ...................................................................................................... 33
Bike Share Program........................................................................................................................ 34
111 South Street Park Design..................................................................................................... 35
Ed Leathers Park Design............................................................................................................... 36
Quincy Street Park Renovation.................................................................................................. 37
North Street Playground............................................................................................................... 38
Pearl and Florence Street Park.................................................................................................. 39
Harris Park Swap............................................................................................................................. 40
Broadway Streetscape................................................................................................................... 41
Community Path............................................................................................................................... 42
Beacon Street Reconstruction.................................................................................................... 43
Road Resurfacing............................................................................................................................. 44
Morse Kelley Playground and Park.......................................................................................... 45
Dickerman Park................................................................................................................................ 46
Boathouse Design ............................................................................................................................ 47
Union Square Central Library..................................................................................................... 48
West Branch Library Renovation ............................................................................................. 49
Ladder Truck ..................................................................................................................................... 50
Fire HQ Apron Replacement....................................................................................................... 51
Breathing Air Compressor........................................................................................................... 52
Toyota Prius Fire Prevention ..................................................................................................... 53
(8) Ford Taurus ................................................................................................................................ 54
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
4
(2) Ford Escapes .............................................................................................................................. 55
(2) Ford Explorers........................................................................................................................... 56
(1) Ford Van ‐ 14 Passenger........................................................................................................ 57
(1) License Plate Reader............................................................................................................... 58
(1) Mobile A/V Surveillance Equipment................................................................................ 59
Police Radios...................................................................................................................................... 60
(5) Laptops with Language Software...................................................................................... 61
Furniture/Computer Equip. Replacement............................................................................ 62
Bullet‐proof Vests............................................................................................................................ 63
ADA Improvements......................................................................................................................... 64
Fire Apparatus .................................................................................................................................. 65
Police Vehicles................................................................................................................................... 66
Engine 7 Roof Replacement ........................................................................................................ 67
Fire Administrative Command Vehicle .................................................................................. 68
Powder House Rotary Signal Equipment.............................................................................. 69
Engine 7 Renovation ...................................................................................................................... 70
High School Roof Replacement.................................................................................................. 71
High School Careers Room........................................................................................................... 72
High School Weight Room............................................................................................................ 73
High School Repairs........................................................................................................................ 74
East Somerville Community School......................................................................................... 75
Union Square Transportation Study........................................................................................ 76
DIF Infrastructure Projects.......................................................................................................... 77
Acquire 161 Broadway.................................................................................................................. 78
Acquire Union Square Post Office............................................................................................. 79
DPW Roof ............................................................................................................................................ 80
SCAT Repairs ..................................................................................................................................... 81
Public Safety Building Sally Port............................................................................................... 82
DPW Vehicles..................................................................................................................................... 83
ISD Renovation ................................................................................................................................. 84
Other Building Improvements ................................................................................................... 85
Ice Rink Zamboni ............................................................................................................................. 86
(2) 15 Passenger Vans................................................................................................................... 87
Ice rink security system................................................................................................................ 88
Aldermanic Chamber Furniture................................................................................................ 89
City Hall Pointing and Painting.................................................................................................. 90
Radio Conversion............................................................................................................................. 91
Human Resources Information System.................................................................................. 92
Appendices
Appendix A: FY2012‐2016 Capital Projects by Funding Source ........................................ 94
Appendix B: Somerville Long‐Term Debt Outstanding as of June 30, 2011.................. 96
CAPITAL INVESTMENT
PROGRAM
“Capital planning and budgeting is
central to economic development,
transportation, communication,
delivery of other essential
services, and environmental
management and quality of life.
Much of what is accomplished by
local government depends on
asound longterm investment in
infrastructure and equipment.”
– from ICMA’s Capital Budgeting: A Guide for
Local Governments
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
6
CAPITAL PLAN OVERVIEW
The City of Somerville’s $142.7 million five‐year Capital Investment Plan is an
investment program for the City’s future. This plan was created with the underlying
themes of upgrading and modernizing the City’s aging infrastructure and facilities,
expanding the City’s economic base, and helping improve the City’s diverse and
important neighborhoods. The Capital Plan is the City’s investment roadmap for the
next five years and should be strategically implemented to provide Somerville’s
residents with an improved quality of life along with a more efficient and effective
government.
The Capital Investment Plan is comprised of two parts: the Capital Budget, which is
presented to the Mayor and the Board of Aldermen and approved annually, and a
Capital Plan that outlines potential projects over a five year time span.
The Capital Investment Plan document details projected spending for equipment
and construction projects over the next five years, providing policymakers the
opportunity to finance projects, coordinate City needs, and plan for future risks and
needs.
A Capital project is defined as a major, non‐recurring expenditure that generally
meets all of the following criteria:
• Massachusetts General Laws permit the City to issue bonds to finance the
expenditure
• The expenditure is a facility, object, or asset costing more than $25,000
• The expenditure will have a useful life of 10 years or more for buildings or
building components and five years for vehicles and equipment; and
• Planning, engineering, or design services may be considered capital when
such services are integral to a construction, renewal, or replacement project
that meets the criteria for a capital expenditure
Projects and assets that do not meet these requirements are considered operating
expenses and are included in the operating budget.
Examples of typical capital projects include:
• New public buildings (including equipment & furnishings)
• Significant alterations, additions, or improvements to existing buildings
• Land improvements, acquisition, and development
• Equipment replacement and/or refurbishing
• Street construction and major resurfacing
• Water main construction and rehabilitation
• Long‐range planning studies
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
7
A Capital Investment Plan provides many benefits, including:
Focuses attention on community goals and needs. Capital projects can be brought
into line with the City's objectives, allowing projects to be prioritized based on need.
Furthermore, the CIP can be used as an effective tool for achieving the goals set
forth in the City's Comprehensive Plan.
Encourages more efficient program administration. By enhancing the level of
communication among the various departments implementing capital improvement
projects, the City is able to better coordinate efforts, avoiding duplication of efforts
and potential conflicts. Work can be more effectively scheduled and available
personnel and equipment can be better utilized when it is known in advance what,
when, and where projects will be undertaken.
Identifies the most economically sound means of funding projects. Through proper
planning, the need for bond issues or other revenue production measures can be
foreseen and action can be taken before the need becomes so critical that
emergency financing measures are required. By identifying funding needs the City is
able to target needs by priority and work to put in place sources of funding for those
projects where capacity may fall short.
Enhances the City's credit rating. Dramatic changes in the tax structure and bonded
indebtedness can be avoided with proper planning that allows the City to minimize
the impact of capital improvement projects. By keeping planned projects within the
financial capabilities of the City, we are able to preserve our credit rating and make
the City more attractive to business and industry.
CAPITAL PLANNING PROCESS
The Capital Investment Plan is prepared from a city‐wide perspective. There is no
assumption of a budget quota for individual departments.
Capital budget requests are submitted by Department Heads to the Finance
Department accompanied by detailed cost estimates of capital costs and potential
impact on the Operating Budget. The Finance Department evaluates the City’s
overall financial situation and, within this larger context, each department’s request
is compared to the prior year’s recommendations and to any long‐term plan for that
department. Important questions raised in the process include: Does the request
reflect an interdepartmental planning effort? Has the department considered all
sources of funding? Has the Department undertaken a cost/benefit analysis? The
Finance Department looks for evidence of longer term planning for departmental
needs, of planning for maintenance expenses, and of interdepartmental cooperation.
While most departmental requests have merit, the City’s projected financing
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
8
resources fall short of accommodating all requests. Very difficult decisions must be
made as to what projects receive funding in any given fiscal year. In reviewing the
requests of the operating departments, the Administration determines whether or
not the request will fulfill one of the following goals of the Mayor:
Mayoral Goals
1. [Quality of Life] Celebrate Somerville as and exceptional place to live, work
and play.
2. [Safe Neighborhoods] Protect and Support families and individuals.
3. [Fiscally Sound Management] Maximize return on taxpayer dollars
4. [Education] Provide high‐quality education opportunities to meet the needs
of our students and community.
5. [Economic Development & Community Vision] Promote Economic
Development consistent with SomerVision and the City’s Comprehensive
Master Plan.
6. [Accountability & Performance] Improve City performance by increasing
accountability and transparency.
7. [Customer Service] Offer professional and courteous treatment, prompt and
thorough responses to constituent requests, and reliable access to
government services.
8. [Innovation & Technology] Utilize new technologies to better coordinate,
support and deliver city services.
9. [Environment] Promote a healthy environment by adopting eco‐friendly
policies and implementing energy efficiency.
10. [Innovative and Responsive Workforce] Promote and innovative and
responsive workplace that solves problems, achieves goals and delivers
quality services to citizens.
If the project meets one of the Mayor’s goals, the city uses a number of other criteria
for evaluation. Major focal points of evaluation are:
• Imminent threat to the health and safety of citizens/property
• Preservation of operations. This does not include ordinary maintenance but
rather maintaining a current service level through improvement of a capital
asset. These may be major expenditures that will avoid costly replacement in
the future.
• Requirement of State or Federal Law/regulation
• Improvement of Infrastructure
• Improvement in the efficiency and effectiveness of service delivery
• Alleviation of an overtaxed/overburdened situation
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
9
After considerable review and discussion, the Mayor finalizes each project. The
individual projects are codified into the Capital Investment Plan. Each project in the
CIP has an individual data sheet describing the project in detail. Each project data
sheet includes:
o Project title: Provides a brief description of the project.
o Site Information: Location map and address (if available) indicating the
project’s approximate location within the city.
o Description/Justification: Information about the purpose and scope of the
project and explanation of why the project is needed.
o Impact on Operating Budget: An integral part of planning for a capital project
is to ensure that funding is available for any additional, ongoing operating
and maintenance costs that will be incurred once a project is complete. These
include: additional staffing, utilities, debt service payments, etc. The Capital
Investment Plan addresses this issue by including anticipated impacts on the
operating budget in each project data sheet.
o Project Costs/Source of Funds: Details of project expenditures and sources of
funding, including prior years funding and sources for the project.
SOURCES OF FUNDING
The Capital Budget represents the funding for the first year of the Plan. Projects in
the first year of the Plan generally represent the city’s most immediate investment
priorities. Projects that are included in the Plan are not guaranteed for funding as
the Plan is a reflection of the need within the City. The Capital Investment Plan is
intended to be a fluid document that will be subject to change each year as priorities
change and as additional information on funding streams becomes more defined.
Loss of state aid, emergencies, unforeseen and extraordinary expenditures in the
operating budget, higher than anticipated borrowing costs, and federal grant
cutbacks are all factors that can force a change in the assumptions of the Capital
Investment Plan.
Funding for the first year of the Plan is submitted to the Board of Aldermen for
appropriation. Each item is considered separately in accordance with the
Massachusetts General Laws.
The potential funding sources for the City’s capital investments are:
• Available Funds (Free Cash) – The City regularly appropriates General Fund
“Free Cash” to finance short‐term, small capital investment projects in their
entirety. Funds may be appropriated directly from the General Fund Tax
Levy to the Operating Budget.
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
10
• Enterprise Fund Proceeds – The City Operates the following Enterprise
Funds: Water, Sewer, Ice Rink, and Dilboy Field. The policy of the City of
Somerville is to recover the full budgetary cost of water and sewer
operations and capital replacement from water and sewer use charges. Debt
Service and issuance costs associated with water and sewer projects are
financed from water and sewer use charges. Program receipts from the
operation of the Veterans Memorial Skating Rink and the Dilboy Field may be
used to finance capital projects for these respective entities.
• Enterprise Fund Retained Earnings – The accumulated earnings of an
Enterprise fund may be used to fund capital improvements. The earnings
flow to an Equity Account known as “Retained Earnings” and are certified
annually by the State Department of Revenue.
• Debt Service – Projects funded by debt service refer to those expenditures
that are acquired through borrowing, the payments for which may or may
not affect the next fiscal year, but in any event are paid for over an extended
period of time, usually three to twenty years. Those extended payments
include both principal and interest, usually referred to as “debt service”. The
City has traditionally financed large capital projects with debt service. Debt
Service can be appropriated under the General Fund Tax Levy, from
Enterprise Funds, or from Stabilization Funds.
• Stabilization Funds – Massachusetts General Law, Chapter 40, Section 5B
provides for the establishment and maintenance of Capital Project
Stabilization Funds. The Mayor and the Board of Aldermen may vote to
appropriate sums of money into a Stabilization Fund for purposes of
accumulating sums for future capital project financing. Appropriations may
be made from a Stabilization Fund by a two‐thirds vote of the Board of
Aldermen for any purpose for which the City is authorized to borrow under
Chapter 44, Sections 7 and 8. The City’s largest Stabilization Funds are the
Capital Projects Stabilization Fund (Pay‐As‐You‐Go Projects) and the
Assembly Square Stabilization Fund (Parks and Park Improvements).
• Unexpended/Unobligated Bond Proceeds – Unexpended and unobligated
balances from bond proceeds, may be appropriated on the motion of the
Mayor by the Board of Aldermen, and used as a financing source for a new
capital improvement projects with an asset life similar to the original issue.
• District Increment Financing – M.G.L. Chapter 40Q authorizes cities and
towns to create development districts to segregate the taxes levied against
new property developed in such districts since they were created (“Tax
Increments”) and to use and pledge such tax increments to finance project
costs within the district. A development district may be as small as one parcel
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
11
or may comprise up to 25% of a town or city's land. A district can be in effect
for a maximum of 30 years. Each district must have a unique development
program. The development program spells out the goals of the district and
the means to achieve them. Once a district and program have been certified,
the city or town has the ability to use various tools to implement the
program. These include acquiring land, constructing or reconstructing
improvements (such as buildings, roads, schools and parks), incurring
indebtedness and pledging tax increments and other project revenues for
repayment of these debts. The City is using DIF as a financing tool for
infrastructure development at Assembly Row.
• State and Federal Grants – The City uses dedicated state aid and grant
funding to finance capital investment when these funds are available. The
most notable sources of this financing are Chapter 90 State Highway Funds
and the Community Development Block Grant.
• Sale of Surplus Property – Proceeds from the sale of surplus municipal real
estate may be appropriated on the motion of the Mayor by the Board of
Aldermen for financing capital projects. Generally, these proceeds are
appropriated to a Stabilization Fund.
• Public/Private Partnerships – A Public/Private Partnership is a contractual
agreement between a public agency and a private sector entity whereby the
skills and assets of each sector (public and private) are shared in delivering a
service or facility for the use of the general public. In addition to the sharing
of resources, each party shares in the risks and rewards potential in the
delivery of the service and/or facility.
• Other Available Funds – Other sources include Parking Meter Receipts,
Insurance Recoveries, and closeouts to Undesignated Fund Balance.
CAPITAL INVESTMENT PLAN FINANCING POLICIES
The City of Somerville has adopted several Capital Investment Financing Policies as
a guide for decision‐making.
A) General Fund Debt Service Benchmark
Except for projects or improvements authorized by a Proposition 2 ½ Debt
Exclusion vote of the electorate, long‐term debt for general financing for
general municipal purposes shall be not exceed five percent (5%) of total
General Fund expenditures. This benchmark measures the City's ability to
finance debt within its current budget, similar to the measurement of
household income dedicated to mortgage payments. This is the most
immediate measure of ability to pay.
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
12
B) Water & Sewer Enterprise Funds Benchmark
Water and Sewer Debt Service should not exceed twenty percent (20%) of
water and sewer operating revenues. This benchmark recognizes the
capital intensive nature of the Water & Sewer Enterprise Funds while
ensuring that investment in the City’s water and sewer systems does not
place dramatic increases on the ratepayer.
C) Use of “Free Cash”
Free Cash in excess of that needed to fund the Operating Budget should be
used for non‐recurring or emergency expenditures or appropriated to a
Stabilization Fund for future capital projects and equipment purchases.
The City will endeavor to apportion a minimum of 30% of its yearly free
cash certification to the Capital Investment Plan.
D) Use of Debt
All current operating expenditures will be paid for with current operating
revenues. The City will not use long‐term debt for current operations.
E) Sale of Assets
Proceeds from the sale of surplus municipal property shall be dedicated to
capital improvement financing.
F) Stabilization Fund Balances
A minimum balance of $4.8 million shall be maintained as reserves as of
June 30th of each fiscal year. Of the $4.8 million in reserves, a minimum
balance of $2 million shall be maintained in the Capital Stabilization Fund.
This benchmark is established to assure the bond rating agencies of adequate
reserves.
FY 2012 CAPITAL FINANCING STRATEGY
The “Capital Budget” represents the funding for the first year of the capital
improvement plan each year. Projects in the annual budget represent the City’s
most immediate investment priorities and are the projects with the highest return
on investment for the taxpayers of Somerville.
As noted earlier, the City strives to keep General Fund Debt Service costs at a ratio of
5% or less of General Fund Operating Expenditures. In measuring the benchmark
and planning over the five year period of the Plan, the City will assume a Long‐Term
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
13
interest rate of 4.5% for long‐term issues and a Short Term Borrowing Rate of 2%.
In the early stages of projects, the City generally borrows on a short‐term basis. The
City evaluates market conditions as the project progresses to determine the
feasibility of borrowing on a long‐term basis. The Five Year Capital Project Plan
Payment Schedule, included in the appendix, assumes borrowing on a short‐term
basis for a period of two years, at which point the City issues a long‐term general
obligation bond. The City assumes an average growth of 4.5% a year in General
Fund Expenditures.
Below is the financing strategy for the FY2012 Capital Budget.
General Fund Debt Service
The City's relatively low ratio of debt service to general fund expenditures provides
more budgetary flexibility to address financial problems that may arise. Debt
payments are not discretionary. Courts have ruled that these payments must be
made even before salary payments for employees. Communities with high levels of
debt service relative to operating expenditures have a larger portion of their budget
dedicated to payments that must be made regardless of the community's financial
situation. Having a lower ratio means less money is dedicated to debt service, which
means more flexibility exists within the operating budget.
Expenditures for General Fund Debt Service totaled $8,843,192 at June 30,
2011. This constituted a ratio of 4.95% General Fund Debt Service
Expenditures to General Fund Expenditures.
The Projected General Fund Debt Service at June 30, 2011 before adding on projects
from the FY2012‐FY2016 Capital Investment Plan is as follows:
Fiscal Year
Projected Debt
Service
Projected Debt Service to
General Fund Expenditure Ratio
2012
$ 9,605,690
5.25%
2013
$ 9,280,277
4.86%
2014
$ 9,080,624
4.55%
2015
$ 9,074,646
4.06%
2016
$ 7,611,761
3.49%
The most immediate capital need for the City is the reconstruction of the fire
damaged East Somerville Community School. Gutted by fire in December 2007, East
Somerville Community School students have been re‐routed to four different
schools throughout the City. The plan is to reunite students under one roof in a
newly renovated school to open by September 2013. The renovated East Somerville
Community School will be considered state‐of‐the‐art with 36 classrooms; four
technology/computer labs; a full size gym; and a new media center/library.
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
14
The original cost estimate for the reconstruction was $33,185,258. The funding plan
included: $15,237,996 in MSBA School Construction Reimbursement (State);
$10,023,433 in Insurance Proceeds (City); $8,000,000 in General Obligation Bonds
(City).
The difficulty of renovating a school as opposed to new construction altered original
cost estimates and construction bids came in at $8.1 million above budget. An
intensive value‐engineering analysis was conducted to reduce cost without reducing
scope. Those efforts resulted in reducing the cost of the project by $3 million. The
revised cost estimate for the project is $38,309,249.
The revised funding plan will require the City to borrow an additional $5 million for
a total of $13 million to ensure timely completion of the project by September 2013.
The new funding plan is as follows: $15,237,996 in MSBA School Construction
Reimbursement (state); $10,023,433 in Insurance Proceeds (City); $13,000,000 in
General Obligation Bonds (City).
Original debt service projections assumed the issuance of an $8 million, 30 year,
General Obligation Bond, with level principal payments. The city has calculated the
additional debt service required to issue a $13 million, 30 year, General Obligation
Bond at level principal payments to be $270,445 annually. Steps will be taken to
mitigate the additional debt service and its impact on the General Fund in the
following ways:
• Continue efforts to consolidate school and city programs to reduce rental
payments
• Bid out an ESCO contract to produce energy savings at the new school
• Work with MSBA to examine and tap into creative financing options
• Work with NSTAR to secure energy rebates
• Apply for PARC Grants
All of the debt service assumptions assume mitigation of $270,445 in debt service
payments on an annual basis.
The following chart lists the FY2012 Projects selected to be funded in the Capital
Budget by General Fund Debt Service. Detailed descriptions can be found in the
Project Description Section of the Plan.
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
15
PROJECT
BOND
AMOUNT
TERM FY2012
FY2013
FY2014
FY2015
FY2016
EAST SOMERVILLE
COMMUNITY SCHOOL
$13,000,000
30
‐
730,442
783,333
768,333
753,333
SALLY PORT
$200,000
20
4,000
4,000
19,000 18,550
18,100
HIGH SCHOOL ROOF
$150,000
20
3,000
3,000
14,250 13,912
13,575
ISD RENOVATION
$100,000
20
3,000
3,000
14,250
13,912
13,575
DPW ‐OTHER
BUILDING REPAIRS
$100,000
20
2,000
2,000
9,500 9,275
9,050
LADDER TRUCK
$1,125,000
15
22,500
22,500
125,625 122,250
118,875
OLD U. S. FIRE
STATION REPAIRS
$30,000
20
600
600
2,850 2,782
2,715
FIRE HQ APRON
REPLACEMENT
$55,000
20
1,100
1,100
5,225
5,101
4,978
DPW ROOF
$50,000
20
1,000
1,000
4,750 4,637
4,525
RADIO CONVERSION
$80,000
5
1,600
1,600
16,000 16,000
16,000
DPW VEHICLES
$750,000
15
15,000
15,000
83,750 81,500
79,250
GRAND TOTAL
$15,640,000
53,800 784,242 1,078,533 1,056,252 1,033,976
The chart below shows Projected Debt Service after the inclusion of the FY2012
Projects.
Fiscal Year
Projected Debt
Service
Projected Debt Service to
General Fund Expenditure Ratio
2012
$ 9,605,690
5.25%
2013
$ 9,787,369
5.12%
2014
$ 9,640,607
4.83%
2015
$ 9,498,416
4.55%
2016
$ 8,357,313
3.83%
Assembly Square Stabilization Fund Supported Debt Service
The Assembly Square Stabilization Fund is a specific stabilization fund to provide
funding for the construction and renovation of parks throughout the City. The
Stabilization Fund is a source of debt service for the parks projects. In prior fiscal
years, the Assembly Square Stabilization Fund has funded debt service for the
following projects: Hodgkins Park, Albion Park, Grimmons Park, and Community
Path Design and Improvement.
The source of the funds is a development agreement with Federal Realty Investment
Trust (FRIT), the developer of Assembly Square. The balance of the Assembly
Square Stabilization Fund as of June 30, 2011 was $3,449,660.
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
16
Many of the City’s Parks Projects are funded from multiple sources including
Community Development Block Grants, PARC Grants, and the Assembly Square
Stabilization Fund. The City intends to add several new parks projects to be funded
partially by the Assembly Square Stabilization in FY2012. The projects are as
follows:
PROJECT
BOND
AMOUNT
TERM
FY2012 FY2013
FY2014
FY2015
FY2016
DICKERMAN PARK
RENOVATION
$ 169,720
15
3,395 3,395
18,952
18,443
17,934
MORSE‐KELLY
PLAYGROUND
$ 298,220
15
5,964
5,964
33,300
32,406
31,511
HARRIS PARK SWAP
AND DESIGN
$ 200,000
15
4,000
4,000
22,333
21,733
NORTH STREET
PLAYGROUND
$ 390,000
15
‐ 7,800 7,800
43,550
42,380
QUINCY STREET
PARK
$ 100,000
15
‐ 2,000 2,000
11,167
10,866
$1,157,940
9,359
23,159
66,052
127,899 124,424
Below are the debt service obligations for the Assembly Square Stabilization fund
before and after the FY2012 projects are included.
Fiscal
Year
Projected Assembly Square
Debt Service
(Excluding FY12 Projects)
Revised Projected Assembly
Square Debt Service
(Including FY12 Projects)
2012
$ 308,675
$ 318,034
2013
$ 319,903
$ 343,062
2014
$ 319,333
$ 385,385
2015
$ 328,613
$ 456,512
2016
$ 320,493
$ 444,917
Veterans Memorial Ice Rink Enterprise Fund Supported Debt Service
The City assumed operational control of the DCR Veterans Memorial Ice Rink on
Somerville Avenue in 2010. It became evident early on that the Veterans Memorial
Ice Rink did not currently meet the community demand for: ice time for existing
hockey leagues; women’s adult leagues; training space for the City’s first ever girls
hockey program; special needs; and public skating hours. In the interest of
expanding year‐round recreational space for Somerville youths and residents, the
City has embarked on the construction of a new, outdoor skating rink situated
adjacent to the Veterans Memorial Ice Rink. Cost of construction for the new ice rink
will be $3,303,664. The funding plan for the new Ice Skating Rink is $2,435,355 in
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
17
General Obligation Bonds and $868,309 in Capital Stabilization Funds. Debt Service
for the new construction will be paid from program revenues from the Enterprise
Fund and mitigation revenues from an agreement with Clear Channel flowing to the
Enterprise Fund.
FY2012 FY2013
FY2014
FY2015
FY2016
Ice Rink Enterprise Fund‐
Supported Debt Service
64,423 95,112 267,627 261,542 255,576
Water‐Sewer Enterprise Fund Supported Debt Service
Debt Service is annually budgeted in each of the Enterprise Funds for Sewer
Construction & Reconstruction, Water Main Renovation and Repair, and capital
equipment purchases such as Water Meters. The Water and Sewer Enterprise Funds
can also utilize retained earnings for future capital projects, subject to appropriation
by the Mayor and the Board of Aldermen.
FY2011 Debt Service totaled $1,856,302 in the Water Department and $542,565 in
the Sewer Department. Debt Service is well below the 20% ratio to Operating
Revenues. Total Operating Revenues in FY2011 were $28,838,065. The
Water/Sewer Enterprise Fund debt service schedule is shown below.
FY2012
FY2013
FY2014
FY2015
FY2016
Total Water/Sewer Principal
2,051,026
1,771,750 1,676,533 1,567,204 1,473,416
Total Water/Sewer Interest
320,532
287,437
254,340
220,048
186,514
Total Water/Sewer Debt Service 2,371,557
2,059,187 1,930,873 1,787,251 1,659,930
Capital Stabilization Fund
“Pay‐as‐you‐go” capital financing occurs when cash rather than some form of debt is
used to fund all or a portion of a capital project. Pay‐as‐you‐go financing allows the
local government to avoid the debt markets, avoid interest and other debt issuance
expenses, and expedite the purchase of less expensive or recurring capital assets.
Pay‐as‐you‐go financing helps preserve flexibility in future operating budgets and
helps preserve the City’s financial condition. The pay‐as‐you‐go fund in Somerville
is the Capital Stabilization Fund.
“Free Cash” is annually appropriated to the Capital Stabilization Fund; the Fund may
also receive money from external sources. The Administration appropriated an
additional $1,000,000 in Free cash to the Capital Stabilization Fund for FY2012.
This appropriation is higher than the $850,000 appropriated to the Capital
Stabilization Fund in FY2011. The $1,000,000 appropriation along with the current
fund balance in the Capital Stabilization fund leaves $1,878,026 available for
funding pay‐as‐you‐go projects. Additionally, the City expects to receive another
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
18
$700,000 from Federal Realty Investment Trust (FRIT) which will be deposited into
the Capital Stabilization Fund. The following projects will be funded out of monies
available in the Capital Stabilization fund. More information can be found on these
projects in the following “Individual Project Descriptions” section.
CAPITAL STABILIZATION FUND PROJECTS
Item
Dept.
Project Cost
Benches & Barrels
DPW
$ 25,000
Private Way Reconstruction
DPW
$ 50,000
Christmas Decorations
DPW
$ 150,000
Conway 2nd Rink
DPW
$ 868,309
Ice Rink Locker Rooms
DPW
$ 174,000
High School Careers Room
DPW/School
$ 40,000
High School Weight Room
DPW/School
$ 50,000
High School Repairs
DPW/School
$ 100,000
DPW SubTotal
$ 1,457,309
Breathing Air Compressor
Fire
$ 48,500
Toyota Prius Fire Prevention
Fire
$ 24,700
Fire SubTotal
$ 73,200
(8) Ford Taurus
Police
$ 232,000
(2) Ford Escapes
Police
$ 48,000
(2) Ford Explorers
Police
$ 62,000
(1) Ford Van ‐ 14 Passenger
Police
$ 45,000
(1) License Plate Reader
Police
$ 25,000
(1) Laptop for LPR
Police
$ 5,000
(1) Mobile A/V Surveillance Equip.
Police
$ 20,000
(10) Handheld Portable Radios
Police
$ 30,000
(6) Mobile Radios for Cruisers
Police
$ 24,000
(5) Laptops with Language Software
Police
$ 7,500
Furniture/Computer Equip.
Replacement
Police
$ 10,000
Bullet‐proof Vests
Police
$ 35,000
Police SubTotal
$ 543,500
Zamboni
Recreation
$ 120,000
(2) 15 Passenger Vans
Recreation
$ 52,000
Ice rink security system
Recreation
$ 17,460
Lincoln Park Turf & Rink Design
Recreation
$ 100,000
Kenny Park Design
Recreation
$ 25,000
Winter Hill Play Area Design
Recreation
$ 25,000
Recreation SubTotal
$ 339,460
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
19
Bike Share
Health
$ 144,905
Health SubTotal
$ 144,905
Aldermanic Chamber Chairs
Aldermen
$ 8,000
Committee Room Table and Chairs
Aldermen
$ 11,600
Aldermen SubTotal
$ 19,600
GRAND TOTAL
$ 2,577,974
State and Federal Funds or Grants
Chapter 90 Highway Funds
Chapter 90 Highway Funds are state funds derived from periodic transportation
bond authorizations and apportioned to communities for highway and street
projects based on a formula taking into consideration local road mileage, local
employment levels, and population estimates. Local highway projects are approved
in advance by the State, then after the submission of certified expenditure reports to
the Mass Highway Department, communities receive cost reimbursements to the
limit of the grant. The amount of the grant changes each year. In FY2012, the City
will receive $1,119,718 in Ch. 90 Funds. Below is a list of streets to be resurfaced
using Ch. 90 Funds in FY2012.
CHAPTER 90 FUNDED PROJECTS
Street
Length
Width (Curb to Curb)
Arlington Street
470
26
Auburn Avenue
494
19
Autumn Street
428
14.25
Curtis Street
800
26.5
Cutter Street
751
26
Dell Street
466
26.75
George Street
291
20
Hathorn Street
356
26.75
Ivaloo Street
720
27.25
Kent Street
376
16.75
268
35
Lincoln Parkway
548
26.5
Sunnyside Avenue
322
23.5
Walnut Street
1,935
28.5
Total Linear Feet
8,225
Raised Table
4,500 SF
Community Development Block Grants
The Community Development Block Grants (CDBG) Entitlement Program is one of
the more significant federal grant programs that make money available for local
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
20
government infrastructure and capital projects. Several projects have a portion of
their funding provided by CDBG funds. Please see the project descriptions for
further details. A full description of CDBG funded projects can be found in the CDBG
“One Year Action Plan” and the OSPCD Consolidated Plan 2008‐2013. The City also
intends to utilize the Section 108 Loan Guarantee Program of the CDBG Program to
assist in the acquisition of 161 Broadway, which will lead to the construction of a
mixed use building that includes a senior center, police substation, retail space and
housing. Section 108 is a loan guarantee provision of the Community Development
Block Grant (CDBG) program that provides communities with a source of financing
for economic development, housing rehabilitation, public facilities, and large scale
physical development projects.
District Increment Financing Supported Debt Service
There are three large infrastructure projects under development in the Assembly
Square Financing District. These infrastructure projects, the extension of Assembly
Square Drive, installation of a storm water conduit, and construction of internal
roadways in Assembly Square, will allow for the further development of Assembly
Square. These infrastructure improvements will be paid for by a bond that is
supported by the incremental increase in property taxes due to the newly developed
property. The city expects to issue $15 million in tax increment‐supported bonds in
February or March 2012, and other $10 million in 2014, if the developer reaches
certain thresholds.
FY2013‐2016 CAPITAL PROJECTS PLAN
The first year of the Capital Investment Program (FY2012) is the Capital Budget
scheduled for the City and provides information on the projects, which need the
approval of the Mayor and the Board of Aldermen. The remaining four years of the
program (FY2013‐FY2016) should be viewed as a Capital Plan for the City’s
leadership and is subject to change based upon the availability of funds.
In some cases, the Capital Investment Plan will identify an unfunded project that the
organization has identified as desirable but lacking a funding source. By identifying
these projects early on as priorities, financial planners are given the opportunity to
design funding scenarios around different levels of priority spending.
The City’s foreseeable future projects include a Vehicle/Equipment Replacement
Program for the Police Department, Fire Department, and Public Works
Department. Each year, the Police, Fire, and Public Works Departments purchase
replacement equipment and vehicles to maintain the fleet as it deteriorates. For
FY2012‐FY2016, the City anticipates spending $750,000 per year on DPW vehicles
and equipment (i.e. pickup trucks, snow plows, street sweepers); approximately
$400,000 per year to replace the Police fleet (i.e. cruisers, detective vehicles); and a
varying amount on Fire Apparatus. Given the relatively short life‐cycle for Police
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
21
Vehicles, the Capital Stabilization Fund will be utilized for Police Vehicle purchases.
General Fund debt service will be used to purchase Fire and DPW Equipment.
Since the scope of the capital plan is limited to affordability, the City continues to
have a significant capital need. The core of any Capital Investment Program should
be the maintenance/repair of and improvements to a community’s infrastructure
and that is the case with this CIP which continues to address on‐going infrastructure
improvements including streets, sidewalks, parks/playgrounds, and water sewer
systems. Over the years, many building improvement projects were deferred due to
budgetary issues. As many of the City’s buildings are very old, the City is undergoing
a comprehensive planning process to determine (1) which buildings the city needs
and will continue to maintain; and (2) what improvements and renovations each of
those buildings needs to continue to be of service. The study will determine which
projects are of the highest priority, the financial investment needed, and a potential
schedule for improvements. The FY2012‐FY2016 Capital Investment Plan provides
space for additional general fund debt service that may be added to the later years
of the Plan to accommodate needed building renovations.
The extension of the Green Line from Lechmere Station through Somerville and the
placement of an Orange Line Station at Assembly Square have the potential to
transform Somerville in the next few years, providing improved transportation
connections, open space, community services, and facilitating commercial
development that expands the City’s tax base. The FY2012‐2016 Capital Investment
Plan commits $25 million in public investment to infrastructure at Assembly Square
through the mechanism of the DIF. To unleash the development potential in Union
Square, additional public investment in infrastructure will be required as it is
acknowledged that transportation improvements at Union Square will be the
linchpin to capitalize on the new transit station and promote significant private
investment. As part of the plan to revitalize Union Square, the City is seeking a grant
from the Massachusetts Public Library Construction Program to fund 60% of the
cost of a new Public Library in Union Square. Total cost of new construction is
estimated to be $32,681,095. The City is currently investigating a number of funding
options for the Library and to promote the development of Union Square including
grants, public‐private partnerships, additional debt service, I‐Cubed, and District
Incremental Financing.
Projected General Fund Debt Service after the inclusion of the
FY2012FY2016 Projects
The chart below projects General Fund Debt Service for all FY2012‐FY2016 Projects
financed by General Fund Debt Service.
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
22
Fiscal
Year
Projected Debt
Service
Projected Debt Service to General
Fund Expenditure Ratio
2012
$ 9,605,690
5.25%
2013
$ 10,487,541
5.25%
2014
$ 10,403,230
4.99%
2015
$ 9,648,853
4.42%
2016
$ 9,769,959
4.29%
The City’s goal of maintaining a ratio of Debt Service to General Fund Expenditures of
5% is exceeded in FY2012 and FY2013 but drops below the threshold in FY2014 and
beyond due to the retirement of debt.
FY 2012‐FY2016 CAPITAL INVESTMENT PROJECTS
Item
Dept.
Project Cost
Funding Source
Year
1. Quality of Life
Private Way Reconstruction
DPW
$ 50,000
Capital Stabilization
FY12
Benches & Barrels
DPW
$ 25,000
Capital Stabilization
FY12
Conway 2nd Ice Rink
DPW
$ 3,303,664
Capital Stabilization
FY12
Conway Ice Rink Locker Rooms
DPW
$ 174,000
Capital Stabilization
FY12
Chistmas Decorations
DPW
$ 150,000
Capital Stabilization
FY12
Lincoln Park Sports Complex
Recreation
$ 2,040,000
Capital Stabilization
FY12‐14
Kenny Park Design
Recreation
$ 25,000
Capital Stabilization
FY12
Winter Hill Play Area Design
Recreation
$ 25,000
Capital Stabilization
FY12
Bike Share Program
Health
$ 244,905
Capital Stabilization
FY12, 13
111 South Street Park Design
OSPCD
$ 50,660
CDBG
FY12
Ed Leathers Park Design
OSPCD
$ 53,311
CDBG
FY12
Quincy Street Park Renovation
OSPCD
$ 325,000
Multiple
FY12‐13
North Street Playground
OSPCD
$ 1,190,000
Multiple
FY12‐13
Pearl and Florence Street Park
OSPCD
$ 435,000
Multiple
FY12‐13
Harris Park Swap
OSPCD
$ 1,000,000
Multiple
FY12‐13
Broadway Streetscape
OSPCD
$ 8,767,989
Multiple
FY12‐13
Community Path
OSPCD
$ 2,045,358
Multiple
FY12‐15
Beacon Street Reconstruction
OSPCD
$ 4,495,000
Multiple
FY12‐14
Road Resurfacing
DPW
$ 1,119,718
Ch. 90 Gas Tax
FY12
Morse Kelley Playground and Park
OSPCD
$ 682,220
Assembly SQ Stab.
FY12
Dickerman Park
OSPCD
$ 425,720
Assembly SQ Stab.
FY12
Boathouse Design
OSPCD
$ 175,000
Capital Stabilization
FY14
Union Square Central Library
OSPCD
$ 32,681,095
To‐be‐determined
FY16
West Branch Library Renovation
DPW
$ 400,000
Debt Service
FY16
Total
$ 59,883,640
2. Safe Neighborhoods
Ladder Truck
Fire
$ 1,125,000
Debt Service
FY12
Fire HQ Apron Replacement
Fire
$ 55,000
Debt Service
FY12
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
23
Item
Dept.
Project Cost
Funding Source
Year
Breathing Air Compressor
Fire
$ 48,500
Capital Stabilization
FY12
Toyota Prius Fire Prevention
Fire
$ 24,700
Capital Stabilization
FY12
(8) Ford Taurus
Police
$ 232,000
Capital Stabilization
FY12
(2) Ford Escapes
Police
$ 48,000
Capital Stabilization
FY12
(2) Ford Explorers
Police
$ 62,000
Capital Stabilization
FY12
(1) Ford Van ‐ 14 Passenger
Police
$ 45,000
Capital Stabilization
FY12
(1) License Plate Reader
Police
$ 30,000
Capital Stabilization
FY12
(1) Mobile A/V Surveillance Equipment
Police
$ 20,000
Capital Stabilization
FY12
Police Radios
Police
$ 54,000
Capital Stabilization
FY12
(5) Laptops with Language Software
Police
$ 7,500
Capital Stabilization
FY12
Furniture/Computer Equip.
Replacement
Police
$ 10,000
Capital Stabilization
FY12
Bullet‐proof Vests
Police
$ 35,000
Capital Stabilization
FY12
ADA Improvements
OSPCD
$ 50,000
CDBG
FY12
Fire Apparatus
Fire
$ 3,099,500
Debt Service
FY13‐16
Police Vehicles
Police
$ 1,600,000
Debt Service
FY13‐16
Engine 7 Roof Replacement
DPW
$ 65,000
Capital Stabilization
FY13
Fire Administrative Command Vehicle
Fire
$ 35,000
Capital Stabilization
FY13
Powder House Rotary Signal Equip.
DPW
$ 300,000
Debt Service
FY14
Engine 7 Renovation
DPW
$ 1,650,000
Debt Service
FY15
Total
$ 8,596,200
4. Education
High School Roof Replacement
DPW/School
$ 150,000
Debt Service
FY12
High School Careers Room
DPW/School
$ 40,000
Capital Stabilization
FY12
High School Weight Room
DPW/School
$ 50,000
Capital Stabilization
FY12
High School Repairs
DPW/School
$ 100,000
Capital Stabilization
FY12
East Somerville Community School
School
$ 38,309,249
Multiple
FY12
Total
$ 38,649,249
5. Economic Development
Union Square Transportation Study
OSPCD
$ 800,000
Multiple
FY12‐13
DIF Infrastructure Projects
OSPCD
$ 25,000,000
Tax Increment
FY12‐13
Acquire Union Square Post Office
OSPCD
$ 2,575,000
To‐be‐determined
FY16
Acquire 161 Broadway
OSPCD
$ 1,500,000
Sec 108 Loans
FY12‐13
Total
$ 29,875,000
6. Accountability & Performance
DPW Roof
DPW
$ 50,000
Debt Service
FY12
Old Union Square Firehouse Repairs
DPW
$ 30,000
Debt Service
FY12
Public Safety Building Sally Port
DPW
$ 200,000
Debt Service
FY12
DPW Vehicles
DPW
$ 3,500,000
Debt Service
FY12‐16
ISD Renovation
ISD
$ 150,000
Debt Service
FY12
Other Building Improvements
DPW
$ 100,000
Debt Service
FY12
Zamboni
Recreation
$ 120,000
Capital Stabilization
FY12
(2) 15 Passenger Vans
Recreation
$ 52,000
Capital Stabilization
FY12
Ice rink security system
Recreation
$ 17,460
Capital Stabilization
FY12
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
24
Item
Dept.
Project Cost
Funding Source
Year
Aldermanic Chamber Furniture
Aldermen
$ 19,600
Capital Stabilization
FY12
City Hall Pointing and Painting
DPW
$ 500,000
Debt Service
FY14
Total
$ 4,739,060
8. Innovation & Technology
Radio Conversion
DPW
$ 455,000
Debt Service
FY12
Human Resources Information System
Personnel
$ 500,000
Debt Service
FY13
Total
$ 955,000
GRAND TOTAL
$142,698,149
Capital Spending by Mayoral Goal
1. Quality of Life,
$59,883,640
2. Safe
Neighborhoods,
$8,596,200
4. Education,
$38,649,249
5. Economic
Development,
$29,875,000
6. Accountability &
Performance,
$4,739,060
8. Innovation &
Technology,
$955,000
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
25
Capital Project Descriptions
Sorted by Mayoral Goal
Capital Improvement Plan FY2012‐2016
Title:Private Way Reconstruction
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
50,000 ‐ 50,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 50,000 $ ‐ $ 50,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 50,000 $ ‐ $ 50,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 50,000 $ ‐ $ 50,000 $ ‐ $ ‐ $ ‐ $ ‐
This work will be contracted out; consequentially
there will be no operating impact.
Funds to pay for repairs to private ways
throughout the city.
The City typically pays for repairs to private ways
that are open and available for public use.
City of Somerville, Massachusetts
26
Capital Improvement Plan FY2012‐2016
Title:Decorative Benches and Barrels
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
‐
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
25,000 ‐ 25,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 25,000 $ ‐ $ 25,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 25,000 $ ‐ $ 25,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 25,000 $ ‐ $ 25,000 $ ‐ $ ‐ $ ‐ $ ‐
Purchase of decorative benches and trash barrels
to be installed throughout the city. The street
furniture is made to withstand the elements, be
easily cleanable (i.e. graffiti, gum), and require
very little maintenance.
These elegant but durable benches and barrels will
improve the aesthetics of the city's streetscape and
encourage pedestrian traffic. They will also
decrease the amount of litter found on city streets.
There will be additional barrels to dispose of, but
they can be absorbed with existing personnel
City of Somerville, Massachusetts
27
Capital Improvement Plan FY2012‐2016
Title:Conway Park 2nd Ice Rink
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
570 Somerville Ave.
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
‐
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
3,303,664 ‐ 3,303,664 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 3,303,664 $ ‐ $ 3,303,664 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 868,309 $ ‐ $ 868,309 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
2,435,355 ‐ 2,435,355 ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 3,303,664 $ ‐ $ 3,303,664 $ ‐ $ ‐ $ ‐ $ ‐
Construct a covered ice rink next to the existing
Veteran's Memorial Ice Rink to accommodate
additional ice‐related programs.
By providing additional recreational opportunities,
the ice rink will encourage exercise, reduce
childhood obesity and develop a sense of
teamwork within Somerville youth. Ongoing
operational costs will be off set by user fees.
Service fees for the rinks will cover all operating
costs.
City of Somerville, Massachusetts
28
Capital Improvement Plan FY2012‐2016
Title:Veteran's Ice Rink Locker Rooms
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
570 Somerville Ave.
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
‐
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
174,000 ‐ 174,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 174,000 $ ‐ $ 174,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 174,000 $ ‐ $ 174,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 174,000 $ ‐ $ 174,000 $ ‐ $ ‐ $ ‐ $ ‐
Remodel and construct new locker rooms at the
ice rink. The facility's current locker rooms are
badly configured and inadequate. This project will
develop new locker rooms consistent with the
needs of the rink.
Currently the High School Hockey team's locker
room does not have shower facilities. Players are
forced to shower at one end of the building and
dress in another.
The new locker rooms will require the same
maintenance as the existing locker rooms.
City of Somerville, Massachusetts
29
Capital Improvement Plan FY2012‐2016
Title:Replace Decorations
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
‐
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
150,000 ‐ 150,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 150,000 $ ‐ $ 150,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 150,000 $ ‐ $ 150,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 150,000 $ ‐ $ 150,000 $ ‐ $ ‐ $ ‐ $ ‐
Purchase replacement decorations for all holidays,
especially Christmas. The newest decorations
were purchased in 2004.
The current decorations look dated and tattered.
New decorations can be expected to last 3 to 5
years.
Since these are only replacement decorations,
there will be no operational impact.
City of Somerville, Massachusetts
30
Capital Improvement Plan FY2012‐2016
Title:Lincoln Park Turf & Ice Rink
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
290 Washington Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
100,000 ‐ 100,000 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ 1,100,000 840,000 ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 100,000 $ ‐ $ 100,000 $ 1,100,000 $ 840,000 $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 100,000 $ ‐ $ 100,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
1,940,000 ‐ ‐ 22,000 38,800 139,633 213,333
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 2,040,000 $ ‐ $ 100,000 $ 22,000 $ 38,800 $ 139,633 $ 213,333
An estimate on the additional operating costs of an
ice rink can be better determined after the rink has
been designed.
This project will fund the design and construction
to replace the natural field at Lincoln Park with a
synthetic turf and develop an outdoor skating rink.
The two projects will be combined into one sports
complex.
The existing field has poor drainage and cannot
maintain adequate grass coverage for the current
level of use. The new ice rink will provide
additional recreational opportunities to Somerville
youth and adults.
City of Somerville, Massachusetts
31
Capital Improvement Plan FY2012‐2016
Title:Kenny Park Design
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
Highland Ave & Grove Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
25,000 ‐ 25,000 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 25,000 $ ‐ $ 25,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 25,000 $ ‐ $ 25,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 25,000 $ ‐ $ 25,000 $ ‐ $ ‐ $ ‐ $ ‐
It has been over 20 years since the Kenny Park in
Davis Square has been remodeled. This will
provide funds for a design to modernize the park.
The park is showing some age and the play
structures do not have the latest safety upgrades.
Any improvements will meet the City's new
standards for safety and durability.
The redesigned park will require no more
maintenance than the existing park.
City of Somerville, Massachusetts
32
Capital Improvement Plan FY2012‐2016
Title:Winter Hill School Play Area Design
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
Sycamore St. & Evergreen Ave.
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
25,000 ‐ 25,000 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 25,000 $ ‐ $ 25,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 25,000 $ ‐ $ 25,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 25,000 $ ‐ $ 25,000 $ ‐ $ ‐ $ ‐ $ ‐
Similar to Kenny Park, it has been over 20 years
since the Winter Hill School Play Area has been
remodeled. This will provide funds for a design to
modernize the park.
The park is showing some age and the play
structures do not have the latest safety upgrades.
Any improvements will meet the City's new
standards for safety and durability.
The redesigned park will require no more
maintenance than the existing park.
City of Somerville, Massachusetts
33
Capital Improvement Plan FY2012‐2016
Title:Hubway Bike Share System
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
Multiple
Project Address:
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
100,000 ‐ 100,000 100,000 ‐ ‐ ‐
Equipment
44,905 ‐ 44,905 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 144,905 $ ‐ $ 144,905 $ 100,000 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 244,905 $ ‐ $ 144,905 $ 100,000 $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
$ 244,905 $ ‐ $ 144,905 $ 100,000 $ ‐ $ ‐ $ ‐
A Hubway Bike Share System is a new form of public transportation. Bicycles are available to
members to extend the reach of public transit in the city, and can be picked up and dropped off
at any station in the network. People can buy annual subscriptions or shorter‐term passes. By
commiting at this time, the City will be able to access funds available through MAPC/MBTA to
help pay for the stations.
This project represents a major new investment in non‐motorized transportation options within
the city. The capital funding allows the system to be operational for 3 years. At the end of the 3
years, the City will own the equipment (bicycles and station kiosks), and will be covering or
exceeding on‐going operation fees through revenue‐sharing with the operator.
There is an estimated yearly operational cost of $12,839 per station or $77,034. It is likely that
CDBG funds can support the operations.
City of Somerville, Massachusetts
34
Capital Investment Plan FY2012‐2016
Title:111 South Street Park Design
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
111 South Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
55,000 4,340 50,660 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 55,000 $ 4,340 $ 50,660 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
55,000 4,340 50,660 ‐ ‐ ‐ ‐
Total:
$ 55,000 $ 4,340 $ 50,660 $ ‐ $ ‐ $ ‐ $ ‐
The additional park acerage will require additional
work, but it can be maintained with those currently
on staff.
This project will design a new off‐leash recreational
dog area. Park amenities will include secure areas
in which to bring a dog as well as dog supplies to
clean up after a dog and other pet‐friendly features.
Additional areas are needed for residents to
unleash and let their dogs run. There is a high
demand for additional dog parks in Somerville.
City of Somerville, Massachusetts
35
Capital Investment Plan FY2012‐2016
Title:Leathers Park Expansion Design
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
5. Economic Development & Community Vision
Project Address:
106 Walnut Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
53,311 ‐ 53,311 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 53,311 $ ‐ $ 53,311 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
53,311 ‐ 53,311 ‐ ‐ ‐ ‐
Total:
$ 53,311 $ ‐ $ 53,311 $ ‐ $ ‐ $ ‐ $ ‐
The City has acquired two small parcels adjacent to
the recently completed Ed Leathers Park. The City
is proposing to expand the park to incorporate the
additional space. Funding will be used for
demolition, testing, clean‐up and design.
The Ed Leathers Park is relatively small and
increasing its footprint will help this community
park be more utilized by the neighborhood.
The additional park acerage will require additional
work, but it can be maintained with those currently
on staff.
City of Somerville, Massachusetts
36
Capital Investment Plan FY2012‐2016
Title:Quincy Street Park
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
Quincy Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
80,000 ‐ 80,000 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
245,000 ‐ 145,000 100,000 ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 325,000 $ ‐ $ 225,000 $ 100,000 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Assembly SQ Stab
100,000 ‐ ‐ 100,000 ‐ ‐ ‐
Grants
225,000 ‐ 225,000 ‐ ‐ ‐ ‐
Total:
$ 325,000 $ ‐ $ 225,000 $ 100,000 $ ‐ $ ‐ $ ‐
The Quincy Street Park is being redesigned as a
community green space with three slightly terraced
levels with a lawn, tree canopy, native shrubs and
groundcover plantings emphasizing the native New
England landscape and encouraging bird habitats.
There will also be an ADA accessible boardwalk
path and a raised deck optimizing views from the
sight.
The existing park is in very poor condition and as
such is not well utilized.
The new park will require no more maintenance
than the existing park.
City of Somerville, Massachusetts
37
Capital Investment Plan FY2012‐2016
Title:North Street Playground
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
North Street and Broadway
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
135,000 ‐ 135,000 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
1,055,000 ‐ 665,000 390,000 ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 1,190,000 $ ‐ $ 800,000 $ 390,000 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Assembly SQ Stab
390,000 ‐ ‐ 390,000 ‐ ‐ ‐
Grants
800,000 ‐ 800,000 ‐ ‐ ‐ ‐
Total:
$ 1,190,000 $ ‐ $ 800,000 $ 390,000 $ ‐ $ ‐ $ ‐
The project will increase green space as well as
update the recreational equipment. The funding
will be used for design, testing, clean‐up and
construction.
The project will increase the amount of green space
as well as update the park to current city standards.
The new park will require no more maintenance
than the existing park.
City of Somerville, Massachusetts
38
Capital Investment Plan FY2012‐2016
Title:Pearl and Florence Street Park
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
Pearl and Florence Streets
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
75,000 ‐ 75,000 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
360,000 ‐ ‐ 360,000 ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 435,000 $ ‐ $ 75,000 $ 360,000 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
75,000 ‐ 75,000 ‐ ‐ ‐ ‐
To‐be‐determined
360,000 ‐ ‐ 360,000 ‐ ‐ ‐
Total:
$ 435,000 $ ‐ $ 75,000 $ 360,000 $ ‐ $ ‐ $ ‐
This past year the City acquired a vacant parcel at
the corner of Pear and Florence Streets in order to
design and construct a "passive" park that will
increase the green space in the neighborhood and
take advantage of one of East Somerville's largest
trees.
The park plans will increase green space as well as
retain a historic Somerville tree.
The additional park acerage will require additional
work, but it can be maintained with those currently
on staff.
City of Somerville, Massachusetts
39
Capital Investment Plan FY2012‐2016
Title:Harris Park Swap and Design Work
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
Cross St. East Mystic
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
135,000 ‐ 135,000 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
865,000 ‐ 665,000 200,000 ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 1,000,000 $ ‐ $ 800,000 $ 200,000 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Assembly SQ Stab
200,000 ‐ ‐ 200,000 ‐ ‐ ‐
Grants
800,000 ‐ 800,000 ‐ ‐ ‐ ‐
Total:
$ 1,000,000 $ ‐ $ 800,000 $ 200,000 $ ‐ $ ‐ $ ‐
The existing Harris Park, near I‐93, is in a poor
location for a park and is under‐utilized. This
project would provide design work for a new park
on vacant parcels near the current park site. This
would allow the city to market the current park to a
developer and, in exchange for the park property,
the developer would construct the new park on the
vacant parcels.
The end result will be improved park space and
additional tax revenue for the City.
The new park will require no more maintenance
than the existing park.
City of Somerville, Massachusetts
40
Capital Investment Plan FY2012‐2016
Title:Broadway Streetscape Improvements
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
8,767,989 ‐ 8,767,989 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 8,767,989 $ ‐ $ 8,767,989 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
MWRA
1,500,000 ‐ 1,500,000 ‐ ‐ ‐ ‐
W/S Enterprise
1,000,000 ‐ 1,000,000 ‐ ‐ ‐ ‐
Grants
6,267,989 ‐ 6,267,989 ‐ ‐ ‐ ‐
Total:
$ 8,767,989 $ ‐ $ 8,767,989 $ ‐ $ ‐ $ ‐ $ ‐
The project will eliminate an unneeded travel lane
and increase sidewalk and bike lane space along
1/2 a mile of Broadway in East Somerville. It will
also create "nodes" made of larger plaza areas in
front of key businesses.
This project will transform the appearance and
business climate in East Somerville revitalizing an
under‐utilized neighborhood in the City. ADA
amenities and pedestrian improvements will be
included as well.
Lower Broadway will continue to be maintained by
the Highway and Parks Depts. The landscaping will
require little maintenance.
City of Somerville, Massachusetts
41
Capital Investment Plan FY2012‐2016
Title:Community Path Extension
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
288,200 ‐ 288,200 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
1,757,158 ‐ ‐ 1,757,158 ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 2,045,358 $ ‐ $ 288,200 $ 1,757,158 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Federal Earmark
1,012,389 ‐ ‐ 1,012,389 ‐ ‐ ‐
CDBG
288,200 ‐ 288,200 ‐ ‐ ‐ ‐
Other Grants
744,769 ‐ ‐ 744,769 ‐ ‐ ‐
Total:
$ 2,045,358 $ ‐ $ 288,200 $ 1,757,158 $ ‐ $ ‐ $ ‐
This project will provide the design, environmental
work and construction of the Community Path
extension from Cedar Street on the west to Lowell
Street on the east.
This extention will actively promote healthy living
and alternative transportation methods. When the
MBTA's Green Line extension is complete, the
community path will link the Minuteman Bikeway
to Downtown Boston.
The additional path mileage will require additional
work, but it can be maintained with those currently
on staff.
City of Somerville, Massachusetts
42
Capital Investment Plan FY2012‐2016
Title:Beacon Street Reconstruction
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
400,000 ‐ ‐ 200,000 200,000 ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
4,095,000 ‐ ‐ ‐ 4,095,000 ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 4,495,000 $ ‐ $ ‐ $ 200,000 $ 4,295,000 $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Federal Earmark
2,484,748 ‐ ‐ ‐ 2,484,748 ‐ ‐
Federal Target
1,610,252 ‐ ‐ ‐ 1,610,252 ‐ ‐
Ch. 90 Funds
400,000 ‐ ‐ 200,000 200,000 ‐ ‐
Total:
$ 4,495,000 $ ‐ $ ‐ $ 200,000 $ 4,295,000 $ ‐ $ ‐
Reconstruction of Beacon Street from the
Cambridge City line to Oxford Street. New
sidewalks, curbing, drainage and signal
improvements are included.
The reconstruction of Beacon Street will not only
improve traffic flow and comfort, but the new
amenities will improve the business district as well.
Beacon Street will continue to be maintained by the
Highway and Parks Depts. The landscaping will
require little maintenance.
City of Somerville, Massachusetts
43
Capital Investment Plan FY2012‐2016
Title:CH. 90 Road Resurfacing
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Length
Width (Curb to Curb)
470
26
494
19
428
14.25
800
26.5
751
26
466
26.75
291
20
356
26.75
720
27.25
376
16.75
268
35
548
26.5
322
23.5
1,935
28.5
8,225
4,500 SF
Ivaloo Street
Kent Street
Lincoln Parkway
Sunnyside Avenue
Walnut Street
Total Linear Feet
Raised Table
Arlington Street
Auburn Avenue
Autumn Street
Curtis Street
Cutter Street
Dell Street
George Street
Hathorn Street
Street
Every year the State provides Ch. 90 Funds for maintaining
the City's streets. The City will receive $1,119,718 in Ch. 90
funds in FY2012. The roads to be resurfaced are listed
below. Additionally, $40,000 is set aside for engineering
and design to be used as needed with these resurfacing
projects.
The streets to be resurfaced were ranked and prioritized
by the Superintendent of Highways and the DPW
Commissioner
The newly resurfaced streets will decrease the operational
costs of the City by decreasing the number of potholes that
will need to be repaired as well as reduce the amount of
broken street sweeping and snow plow equipment.
City of Somerville, Massachusetts
44
Capital Investment Plan FY2012‐2016
Title:Morse Kelley Playground
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
Craigie and Summer Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
682,220 ‐ 682,220 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 682,220 $ ‐ $ 682,220 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
384,000 ‐ 384,000 ‐ ‐ ‐ ‐
Assembly SQ Stab
298,220 ‐ 298,220 ‐ ‐ ‐ ‐
Total:
$ 682,220 $ ‐ $ 682,220 $ ‐ $ ‐ $ ‐ $ ‐
The project will reconstruct the Morse Kelly
Playground and Park to include more green area,
active recreational areas, a community garden and
new playground equipment.
The current park lacks adequate green space and is
not very inviting.
The new and improved park structures will be
easier to maintain than the existing structures.
City of Somerville, Massachusetts
45
Capital Investment Plan FY2012‐2016
Title:Dickerman Park Renovation
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
Craigie and Kimball Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
425,720 ‐ 425,720 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 425,720 $ ‐ $ 425,720 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
256,000 ‐ 256,000 ‐ ‐ ‐ ‐
Assembly SQ Stab
169,720 ‐ 169,720 ‐ ‐ ‐ ‐
Total:
$ 425,720 $ ‐ $ 425,720 $ ‐ $ ‐ $ ‐ $ ‐
Dickerman Park will be renovated to better use the
elevated park area and to include more green
space. New playground facilities will also be
included.
The current park lacks adequate green space and is
not very inviting.
The new and improved park structures will be
easier to maintain than the existing structures.
City of Somerville, Massachusetts
46
Capital Improvement Plan FY2012‐2016
Title:Blessing of the Bay Boathouse Design
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
32 Shore Drive
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
175,000 ‐ ‐ ‐ 175,000 ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 175,000 $ ‐ $ ‐ $ ‐ $ 175,000 $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 175,000 $ ‐ $ ‐ $ ‐ $ 175,000 $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 175,000 $ ‐ $ ‐ $ ‐ $ 175,000 $ ‐ $ ‐
The new design will not require any additional
operating expenditures.
This project will provide for the design work to
make the boathouse more inviting, accessible and
utilized.
The Blessing of the Bay Boathouse is a Somerville
treasure and helps connect the city with the Mystic
River. Additionally, the improved boathouse will
provide greater recreational opportunities.
City of Somerville, Massachusetts
47
Capital Investment Plan FY2012‐2016
Title:Union Square Central Library
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
220 Washington Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
32,681,095 ‐ ‐ ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 32,681,095 $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
13,031,095 ‐ ‐ ‐ ‐ ‐ ‐
City TBD
19,650,000 ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 32,681,095 $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
As designed, the new Central Library will serve as
the civic and cultural heart of Somerville. The new
facility will offer a robust collection, high‐tech
services, and provide a landmark building designed
with inviting rooms for children, youth, and adults.
The operational impact of this project can not be
determined at this point in time.
Acquisition and redevelopment of a key site in
Union Square in advance of the Green Line
extension.
City of Somerville, Massachusetts
48
Capital Investment Plan FY2012‐2016
Title:West Somerville Branch Library
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
40 College Avenue
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
400,000 ‐ ‐ ‐ ‐ ‐ 400,000
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 400,000 $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ 400,000
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
400,000 ‐ ‐ ‐ ‐ ‐ 8,000
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 400,000 $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ 8,000
This project would renovate the West Somerville
branch library. Damaged caused by moisture
intrusion would be repaired and the building
would be sealed from further intrusion.
The renovated building will decrease the need for
continued pathwork repairs to the interior of the
building.
The West Branch Library is a beautiful historic
building, but major portions of the building have
water damage.
City of Somerville, Massachusetts
49
Capital Improvement Plan FY2012‐2016
Title:Fire Ladder Truck
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
1,125,000 ‐ 1,125,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 1,125,000 $ ‐ $ 1,125,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab Fund $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
1,125,000 ‐ 22,500 22,500 125,625 122,250 118,875
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 1,125,000 $ ‐ $ 22,500 $ 22,500 $ 125,625 $ 122,250 $ 118,875
This purchase will replace the current 17‐year old
tower ladder which will be 18‐years old before a
replacement is obtained.
This is a part of the Fire Department evaluation
recommended apparatus replacement plan. In
accordance with NFPA 1901, the spare ladder
which will be replaced will be 24 years old.
The new ladder truck will likely require less
maintenance and repairs than the existing truck.
City of Somerville, Massachusetts
50
Capital Improvement Plan FY2012‐2016
Title:Fire Headquarters Apron Replacement
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Project Address:
266 Broadway
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
55,000 ‐ 55,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 55,000 $ ‐ $ 55,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
55,000 ‐ 1,100 1,100 5,225 5,101 4,987
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 55,000 $ ‐ $ 1,100 $ 1,100 $ 5,225 $ 5,101 $ 4,987
Full depth replacement of the apparatus apron in
front of Fire Headquarters including the entire
apron from the doorway to the streetline, the
walkway into the station and the sidewalk from
Kenneson Road to Walnut Street.
The current uneven walking surface presents a
serious hazard to firefighters and citizens.
The new apron will require less ongoing
maintenance than the current crumbling apron.
City of Somerville, Massachusetts
51
Capital Improvement Plan FY2012‐2016
Title:Breathing Air Compressor
Project Description:
Justification:
Photo Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
48,500 ‐ 48,500 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 48,500 $ ‐ $ 48,500 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 48,500 $ ‐ $ 48,500 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 48,500 $ ‐ $ 48,500 $ ‐ $ ‐ $ ‐ $ ‐
The breathing air compressor is used to refill self‐
contained breathing air apparatuses used by the
firefighters. The cost and availability of parts are
limiting factors in the continued use of this
equipment.
The current system is 23‐years old and has
experienced several breakdowns per year over the
past few years. The compressor must function
properly to quickly return fire companies to full
service after an incident.
As the current compressor needs frequent repairs,
the new compressor will save on costs for parts
and labor.
City of Somerville, Massachusetts
52
Capital Improvement Plan FY2012‐2016
Title: Fire Prevention Replacement Vehicles
Project Description:
Justification:
Photo Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
FY 2012
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
24,700 ‐ 24,700 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 24,700 $ ‐ $ 24,700 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 24,700 $ ‐ $ 24,700 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 24,700 $ ‐ $ 24,700 $ ‐ $ ‐ $ ‐
Replace the vehicle used by Fire Prevention with a
more economical, fuel‐efficient vehicle.
This will complete the replacement of all Fire
Prevention and day personnel vehicles with the fuel‐
efficient hybrid Prius. The Fire Prevention vehicles
are heavily used throughout the City providing
inspections daily.
The hybrid will see significant amounts of fuel
savings.
City of Somerville, Massachusetts
53
Capital Improvement Plan FY2012‐2016
Title:Vehicle Purchases
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
232,000 ‐ 232,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 232,000 $ ‐ $ 232,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 232,000 $ ‐ $ 232,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 232,000 $ ‐ $ 232,000 $ ‐ $ ‐ $ ‐ $ ‐
Purchase 8 Ford Tauruses for use as police
cruisers.
The new vehicles are likely to cost much less in
repairs as the current vehicles are approaching
100,000 miles.
The average life of a marked front line police
cruiser is less than 2 years. The vehicles will be
utilized as follows: (5) Ford Taurus will be used as
front line vehicles to replace vehicles that have
exhausted their safety limitations, (2) Ford Taurus
will be used as Sector A & Sector B cars to augment
the fleet based on the expansion of 14 new police
officer's hired in FY2011. (1) Ford Taurus will be
used to replace the vehicle that was transferred to
T&P.
City of Somerville, Massachusetts
54
Capital Improvement Plan FY2012‐2016
Title:Vehicle Purchases
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
48,000 ‐ 48,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 48,000 $ ‐ $ 48,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 48,000 $ ‐ $ 48,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 48,000 $ ‐ $ 48,000 $ ‐ $ ‐ $ ‐ $ ‐
Purchase 2 Ford Escapses.
(2) Ford Escapes will be used as "soft cars" for the
narcotics and gang units. In the past, vehicles have
never been secured for specialized units.
Previoulsy, these units would use the left over
castoffs from the inventory of old front line
vehicles.
The new vehicles are likely to cost much less in
repairs than the current vehicles.
City of Somerville, Massachusetts
55
Capital Improvement Plan FY2012‐2016
Title:Vehicle Purchases
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
62,000 ‐ 62,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 62,000 $ ‐ $ 62,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 62,000 $ ‐ $ 62,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 62,000 $ ‐ $ 62,000 $ ‐ $ ‐ $ ‐ $ ‐
The new vehicles are likely to cost much less in
repairs than the current vehicles.
Purchase 2 Ford Explorers.
(2) Ford Explorers will be used to replace the 2002
and 2003 Chevy Tahoe's used in the traffic division
which have met their useful life.
City of Somerville, Massachusetts
56
Capital Improvement Plan FY2012‐2016
Title:Vehicle Purchases
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
45,000 ‐ 45,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 45,000 $ ‐ $ 45,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 45,000 $ ‐ $ 45,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 45,000 $ ‐ $ 45,000 $ ‐ $ ‐ $ ‐ $ ‐
Purchase 1 Ford 14‐Passenger Bus
(1) Ford Bus ‐ 14 Passenger vehicle will be used to
replace the 1999 community van used to transport
children and seniors to various activities. The bus
is much less likely to roll than a large passenger
van.
The new bus will require fewer repairs than the
current vans.
City of Somerville, Massachusetts
57
Capital Improvement Plan FY2012‐2016
Title:License Plate Reader System
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
30,000 ‐ 30,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 30,000 $ ‐ $ 30,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 30,000 $ ‐ $ 30,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 30,000 $ ‐ $ 30,000 $ ‐ $ ‐ $ ‐ $ ‐
The LPR that is being transferred to the T&P
Division will generate additional ticket revenue.
Purchase a License Plate Reader and laptop to
replace the system that was transferred to the
Traffic & Parking Department.
The LPR will help identify vehicles that are stolen,
wanted or revoked for any reason. It also identifies
vehicles registered to known sex offenders.
City of Somerville, Massachusetts
58
Capital Improvement Plan FY2012‐2016
Title:Mobile Surveillance Equipment
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
35,000 ‐ 35,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 35,000 $ ‐ $ 35,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 35,000 $ ‐ $ 35,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 35,000 $ ‐ $ 35,000 $ ‐ $ ‐ $ ‐ $ ‐
The Mobile Audio & Visual Surveillance Equipment
is a state of the art portable device that will enable
the Department to survey criminal activites 24
hours per day in any designated hotspot.
This device has the capacity to scan an area in a
360 degree rotation and will be used for narcotic
investigations as well as undercover work for any
ongoing criminal investigations.
Photo Not Available
There will be little to no operating cost impact due
to the surveillance equipment.
City of Somerville, Massachusetts
59
Capital Improvement Plan FY2012‐2016
Title:Portable and Mobile Radios
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
54,000 ‐ 54,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 54,000 $ ‐ $ 54,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 54,000 $ ‐ $ 54,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 54,000 $ ‐ $ 54,000 $ ‐ $ ‐ $ ‐ $ ‐
Purchase 10 handheld portable radios and 6
mobile radios.
The 10 handheld portable radios will replace non
working radios. The 6 Mobile Radios will be placed
in new vehicles.
The replacement radios will require no additional
maintenance than the current ones.
City of Somerville, Massachusetts
60
Capital Improvement Plan FY2012‐2016
Title:
Project Description:
Justification:
Photo Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
7,500 ‐ 7,500 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 7,500 $ ‐ $ 7,500 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 7,500 $ ‐ $ 7,500 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 7,500 $ ‐ $ 7,500 $ ‐ $ ‐ $ ‐ $ ‐
The language software has a state‐of‐the‐art voice‐
recognition capability that will enable an officer to
take reports in a victim/witness's native tongue
and have the report translated into English.
This software is useful whenever a language
barrier is involved and an intrepreter is not
available. This equipment will be useful in all
facets of police work.
There will be no operating cost impact.
5 Laptops with Language Software
City of Somerville, Massachusetts
61
Capital Improvement Plan FY2012‐2016
Title:
Project Description:
Justification:
Photo Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Project Address:
220 Washington Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
10,000 ‐ 10,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 10,000 $ ‐ $ 10,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 10,000 $ ‐ $ 10,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 10,000 $ ‐ $ 10,000 $ ‐ $ ‐ $ ‐ $ ‐
Severe leaks in the Public Safety Building roof have
ruined desks and chairs in the Traffic Bureau, three
executive chairs in the EOC and rusted out 25
lockers.
Some of this furniture was damaged on 7/10/10
(the day of the Public Safety Building flood), the
furniture was not covered by insurance since the
cause of the damage was deferred maintenance of
the roof.
Replacement of Furniture and Lockers in
Central Headquarters
The new equipment will not need any ongoing
maintenance.
City of Somerville, Massachusetts
62
Capital Improvement Plan FY2012‐2016
Title:Bullet‐Proof Vests
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
69,500 ‐ 69,500 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 69,500 $ ‐ $ 69,500 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 69,500 $ ‐ $ 69,500 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 69,500 $ ‐ $ 69,500 $ ‐ $ ‐ $ ‐ $ ‐
Purchase of 75 bullet‐proof vests and 100 liners.
Bullet‐proof vests are essential to the safety of
sworn officers. The life expectancy of these vests is
5 Years.
There will be no operating cost impact.
City of Somerville, Massachusetts
63
Capital Investment Plan FY2012‐2016
Title:ADA Sidewalk Improvements
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
1. Quality of Life
Project Address:
Multiple
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
50,000 ‐ 50,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 50,000 $ ‐ $ 50,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
50,000 ‐ 50,000 ‐ ‐ ‐ ‐
Total:
$ 50,000 $ ‐ $ 50,000 $ ‐ $ ‐ $ ‐ $ ‐
Install ADA improvements relating to sidewalks,
curb‐cuts, signage & signals, and other pedestrian
infrastructure City‐wide.
As ADA sidewalk requirements have become more
stringent with time, these funds will be used to
update sidewalks that currently do not meet ADA
standards.
Once installed, there are no maintenance needs for
these ADA improvements.
City of Somerville, Massachusetts
64
Capital Improvement Plan FY2012‐2016
Title: Fire Apparatus
Project Description:
Year
FY13
FY14
FY15
FY16
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
3,099,500 ‐ ‐ 830,000 504,000 528,000 1,237,500
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 3,099,500 $ ‐ $ ‐ $ 830,000 $ 504,000 $ 528,000 $ 1,237,500
Funding Sources:
Capital Stab Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
313,636 ‐ ‐ 16,600 26,680 113,323 157,033
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 313,636 $ ‐ $ ‐ $ 16,600 $ 26,680 $ 113,323 $ 157,033
480,000
$
504,000
$
528,000
$
1,237,500
$
The new apparatus will likely require less
maintenance and repairs than the existing
apparatus.
A replacement schedule has been developed to
ensure that all Fire apparatus is replaced within
industry standards. The next five years of this
schedule include:
Ladder #3 Overhaul
Engine #7
Engine #6
Engine #2
Approx. Price
Company
Ladder #3
350,000
$
City of Somerville, Massachusetts
65
Capital Improvement Plan FY2012‐2016
Title:Vehicle Purchases
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
1,600,000 ‐ ‐ 400,000 400,000 400,000 400,000
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 1,600,000 $ ‐ $ ‐ $ 400,000 $ 400,000 $ 400,000 $ 400,000
Funding Sources:
Capital Stab. Fund
$ 1,600,000 $ ‐ $ ‐ $ 400,000 $ 400,000 $ 400,000 $ 400,000
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 1,600,000 $ ‐ $ ‐ $ 400,000 $ 400,000 $ 400,000 $ 400,000
Purchase replacement police vehicles.
By continuously replacing worn vehicles the City
will save extensively on costly repairs to older
vehicles.
The Police Department must replace several
vehicles each year to maintain an adequate fleet.
Over the past several years, the Departmenthas
averaged $400,000 annually in police fleet needs.
In order to accommodate this need, $400,000 will
be penciled in each year in our Capital Stabilization
Fund.
City of Somerville, Massachusetts
66
Capital Improvement Plan FY2012‐2016
Title: Highland Ave Fire Station Roof Replacement
Project Description:
Justification:
Photo Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Project Address:
265 Highland Ave.
Total
Estimated
Cost
FY 2012
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
65,000 ‐ ‐ 65,000 ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 65,000 $ ‐ $ ‐ $ 65,000 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 65,000 $ ‐ $ ‐ $ 65,000 $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 65,000 $ ‐ $ ‐ $ 65,000 $ ‐ $ ‐
Replace the leaking roof at the Engine #7 Firehouse.
The roof leaks is several locations causing severe
water damage and a slipping hazard. Continued
water damage will lead to increased repair costs for
the interior of the building.
The repaired roof will eliminate the need for
ongoing patchwork on the interior.
City of Somerville, Massachusetts
67
Capital Improvement Plan FY2012‐2016
Title: Fire Administrative Command Vehicle
Project Description:
Justification:
Photo Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Total
Estimated
Cost
FY 2012
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
35,000 ‐ ‐ 35,000 ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 35,000 $ ‐ $ ‐ $ 35,000 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 35,000 $ ‐ $ ‐ $ 35,000 $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 35,000 $ ‐ $ ‐ $ 35,000 $ ‐ $ ‐
Replace the vehicle currently used by Chief of
Operations with a hybrid command vehicle.
The Chief of Operations responds to fires and
incidents during regular shifts and also during off
shifts. Current vehicle has proven to be too small
and compact for functions required. Hybrid will
reduce fuel costs.
The hybrid will see significant amounts of fuel
savings.
City of Somerville, Massachusetts
68
Capital Improvement Plan FY2012‐2016
Title:Powder House Square Traffic Signals
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Project Address:
Powder House Circle
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
300,000 ‐ ‐ ‐ 300,000 ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 300,000 $ ‐ $ ‐ $ ‐ $ 300,000 $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
300,000 ‐ ‐ ‐ 6,000 6,000 28,500
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 300,000 $ ‐ $ ‐ $ ‐ $ 6,000 $ 6,000 $ 28,500
This project will replace and upgrade the traffic
signal equipment at Powder House Square rotary.
The improved equipment would lead to a smoother
traffic flow around the rotary.
The new signal equipment will need less
maintenance than the current aged equipment.
City of Somerville, Massachusetts
69
Capital Improvement Plan FY2012‐2016
Title: Highland Ave Fire Station Renovation
Project Description:
Justification:
Photo Not Available
Operational Cost Impact:
Mayor's Goal:
2. Safe Neighborhoods
Project Address:
265 Highland Ave.
Total
Estimated
Cost
FY 2012
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
1,650,000 ‐ ‐ ‐ ‐ 1,650,000 ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 1,650,000 $ ‐ $ ‐ $ ‐ $ ‐ $ 1,650,000 $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
1,650,000 ‐ ‐ ‐ ‐ 33,000 33,000
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 1,650,000 $ ‐ $ ‐ $ ‐ $ ‐ $ 33,000 $ 33,000
Renovate the Fire Station to repair years of water
damage. Additionally, reconfigure the building for
better efficiencies in operations.
This firehouse is in the worst condition of all of the
Fire Department's buildings. A renovation of this
building would allow the building to be in service
for another 50 years.
A renovated building would significantly decrease
the routine repairs and maintenance.
City of Somerville, Massachusetts
70
Capital Improvement Plan FY2012‐2016
Title:High School Roof Sectional Replacement
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
4. Education
Project Address:
81 Highland Avenue
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
150,000 ‐ 150,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 150,000 $ ‐ $ 150,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
150,000 ‐ 3,000 3,000 14,250 13,912 13,575
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 150,000 $ ‐ $ 3,000 $ 3,000 $ 14,250 $ 13,912 $ 13,575
Replace the roof over the High School Field House
and Atrium.
The current roof is in very poor condition and
leaks heavily with even small amounts of rain.
The new roof will eliminate costly patchwork jobs
to the interior of the building.
City of Somerville, Massachusetts
71
Capital Improvement Plan FY2012‐2016
Title:High School Health Careers Suite
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
4. Education
Project Address:
81 Highland Avenue
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
40,000 ‐ 40,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 40,000 $ ‐ $ 40,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 40,000 $ ‐ $ 40,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 40,000 $ ‐ $ 40,000 $ ‐ $ ‐ $ ‐ $ ‐
Renovate and expand the health career suite by
moving to new classroom areas.
With the continued growth in the health‐related
job sector, more and more students are interested
in training in this area. The renovated health
careers suite will be able to train more students to
be valuable members of the health care workforce.
The expanded suite will not require any additional
maintenance than the current suite.
City of Somerville, Massachusetts
72
Capital Improvement Plan FY2012‐2016
Title:High School Weight and Training Rooms
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
4. Education
Project Address:
81 Highland Avenue
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
50,000 ‐ 50,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 50,000 $ ‐ $ 50,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 50,000 $ ‐ $ 50,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 50,000 $ ‐ $ 50,000 $ ‐ $ ‐ $ ‐ $ ‐
Renovate the existing High School weight and
training rooms and purchase new equipment.
The existing weight and training rooms are below
acceptable standards and need to be renovated and
their equipment replaced.
The new weight room will not require any
additional maintenance than the existing weight
room.
City of Somerville, Massachusetts
73
Capital Improvement Plan FY2012‐2016
Title:High School Various Repairs
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
4. Education
Project Address:
81 Highland Avenue
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
100,000 ‐ 100,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 100,000 $ ‐ $ 100,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 100,000 $ ‐ $ 100,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 100,000 $ ‐ $ 100,000 $ ‐ $ ‐ $ ‐ $ ‐
There are various repairs that need to be made to
the high school including painting classrooms and
replacing deteriorated floors.
As the high school continues to age additional
repairs are needed to keep students and staff safe.
The building conditions should not be a distraction
to learning.
The improvements will not alter any operating
costs.
City of Somerville, Massachusetts
74
Capital Investment Plan FY2012‐2016
Title:East Somerville Community School
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
4. Education
Project Address:
8 Bonair Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
38,309,249 ‐ 38,309,249 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 38,309,249 $ ‐ $ 38,309,249 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
13,000,000 ‐ 13,000,000 ‐ ‐ ‐ ‐
Insurance Reimb.
10,071,253 ‐ 10,071,253 ‐ ‐ ‐ ‐
MSBA
15,237,996 ‐ 15,237,996 ‐ ‐ ‐ ‐
Total:
$ 38,309,249 $ ‐ $ 38,309,249 $ ‐ $ ‐ $ ‐ $ ‐
There will be significant energy savings costs with
the upgraded HVAC and other "green" building
techniques employed in the school construction.
Reconstruct the portion of the East Somerville
Community School destroyed by fire in December
2007 and renovate the remaining portion of the
building.
The new school, which will cost over $38 million,
will be paid for from insurance receipts and a
reimbursement from the MSBA, with the remaining
balance of $13 million to be paid for by the City.
City of Somerville, Massachusetts
75
Capital Investment Plan FY2012‐2016
Title:
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
5. Economic Development & Community Vision
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
800,000 89,750 194,454 ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 800,000 $ 89,750 $ 194,454 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
284,204 89,750 194,454 ‐ ‐ ‐ ‐
To‐be‐determined
515,796 ‐ ‐ 515,796 ‐ ‐ ‐
Total:
$ 800,000 $ 89,750 $ 194,454 $ 515,796 $ ‐ $ ‐ $ ‐
This project includes environmental assessment,
financial feasibility, transportation and other
studies relating to the redevelopment of Union
Square.
Union Square Transportation and
Infrastructure Study
Transportation improvements at Union Square are
the lynchpin to capitalize on the new transit station
and promote significant private investment in the
Union Square area. CDBG Funds will most likely
fund the remainder of the project.
This study will have no operational cost impact.
Any implementation operating impacts will be
analyzed when the study is complete.
City of Somerville, Massachusetts
76
Capital Investment Plan FY2012‐2016
Title:Assembly Square DIF Projects
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
5. Economic Development
Project Address:
Assembly Square Drive
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
25,000,000 ‐ 15,000,000 ‐ 10,000,000 ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 25,000,000 $ ‐ $ 15,000,000 $ ‐ $ 10,000,000 $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Incremental Taxes
25,000,000 ‐ 353,656 707,130 1,205,778 1,685,440 1,685,090
Total:
$ 25,000,000 $ ‐ $ 353,656 $ 707,130 $ 1,205,778 $ 1,685,440 $ 1,685,090
The extension of Assembly Square Drive,
installation of a storm water conduit, and
construction of internal roadways in Assembly
Square. The city would pay back the bonds plus
interest using money from property tax increases
within the district that would result from
construction of Blocks 1, 3, and 4 by FRIT.
These infrastructure improvements will allow for
the continued development of Assembly Square.
The additional operational costs will be covered by
the increased property tax from the area.
City of Somerville, Massachusetts
77
Capital Investment Plan FY2012‐2016
Title:Acquire 161 Broadway
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
5. Economic Development
Project Address:
161 Broadway
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
1,500,000 ‐ ‐ 1,500,000 ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 1,500,000 $ ‐ $ ‐ $ 1,500,000 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Sec. 108 loans
1,500,000 ‐ ‐ 1,500,000 ‐ ‐ ‐
Total:
$ 1,500,000 $ ‐ $ ‐ $ 1,500,000 $ ‐ $ ‐ $ ‐
This project is to acquire the property at 161
Broadway and over time facilitate the construction
of a mixed use building that includes a senior
center, police substation, retail space and housing.
Funding will be for appraisal, title search, land
acquisition.
The operational impact of this project can not be
determined at this point in time.
Acquisition and redevelopment of a key site in East
Somerville and upgrading/updating existing City
facilities for seniors and the police.
City of Somerville, Massachusetts
78
Capital Investment Plan FY2012‐2016
Title:Acquire Union Square Post Office
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
5. Economic Development
Project Address:
237 Washington Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
2,575,000 ‐ ‐ ‐ ‐ ‐ 2,575,000
Construction
‐ ‐ ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 2,575,000 $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ 2,575,000
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
To‐be‐determined
2,575,000 ‐ ‐ ‐ ‐ ‐ 2,575,000
Total:
$ 2,575,000 $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ 2,575,000
This project consists of acquiring and repositioning
of the Union Square Post Office. The price includes
closing costs. The price may be negotiated via the
need for a new roof.
The operational impact of this project can not be
determined at this point in time.
This is a key site in Union Square, the
redevelopment of which will lead to greater
investment and increased tax revenues.
City of Somerville, Massachusetts
79
Capital Improvement Plan FY2012‐2016
Title:DPW Facility Roof
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Project Address:
1 Franey Road
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
50,000 ‐ 50,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 50,000 $ ‐ $ 50,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
50,000 ‐ 1,000 1,000 4,750 4,637 4,525
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 50,000 $ ‐ $ 1,000 $ 1,000 $ 4,750 $ 4,637 $ 4,525
The DPW roof leaks causing significant water
damage to the interior of the building.
With each rain storm the cost of repairs to the
interior of the building increase. Equipment,
including computers and desks, have been ruined
due to water damage.
The new roof will eliminate costly patchwork jobs
to the interior of the building.
City of Somerville, Massachusetts
80
Capital Improvement Plan FY2012‐2016
Title:Old Union Square Firehouse Repairs
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Project Address:
90 Union Square
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
30,000 ‐ 30,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 30,000 $ ‐ $ 30,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
30,000 ‐ 600 600 2,850 2,782 2,715
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 30,000 $ ‐ $ 600 $ 600 $ 2,850 $ 2,782 $ 2,715
The old firehouse that houses the Somerville
Community Access Television is in need of minor
repairs including the lower exterior windows,
paint, etc.
Making these minor improvements now will keep
the building from falling into further disrepair and
more costly improvements in the future.
The improvements will not require any additional
maintenance costs.
City of Somerville, Massachusetts
81
Capital Improvement Plan FY2012‐2016
Title:Public Safety Building Sally Port
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Project Address:
220 Washington Street
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
200,000 ‐ 200,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 200,000 $ ‐ $ 200,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
200,000 ‐ 4,000 4,000 19,000 18,550 18,100
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 200,000 $ ‐ $ 4,000 $ 4,000 $ 19,000 $ 18,550 $ 18,100
The Sally Port at the Public Safety Building is in
need of repairs. The sally port is the secured,
controlled entryway at the public safety building.
Without the repairs to the Public Safety Building's
sally port the City runs the risk of injury when
prisoners are being transported.
There will be no operating impact due to the
reconstructed sally port.
City of Somerville, Massachusetts
82
Capital Improvement Plan FY2012‐2016
Title:DPW Vehicles
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
3,500,000 ‐ 750,000 750,000 750,000 750,000 500,000
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 3,500,000 $ ‐ $ 750,000 $ 750,000 $ 750,000 $ 750,000 $ 500,000
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
3,500,000 ‐ 15,000 30,000 113,750 195,250 274,500
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 3,500,000 $ ‐ $ 15,000 $ 30,000 $ 113,750 $ 195,250 $ 274,500
As many of the current DPW vehicles are
consistently breaking down, the new vehicles will
save approximately $75,000‐$100,000 annually.
The Department of Public Works has an aging fleet
that, even though well maintained, has had
significant breakdowns. This will provide for the
purchase of new vehicles for the department as
prioritized by the DPW Commissioner.
The City strives to appropriate $750,000 each year
for continued replacement and renewal of the DPW
vehicle fleet. This will meet that obligation.
City of Somerville, Massachusetts
83
Capital Improvement Plan FY2012‐2016
Title:ISD Office Renovation
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Project Address:
1 Franey Road
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
150,000 ‐ 150,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 150,000 $ ‐ $ 150,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
150,000 ‐ 3,000 3,000 14,250 13,912 13,575
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 150,000 $ ‐ $ 3,000 $ 3,000 $ 14,250 $ 13,912 $ 13,575
This project will cover painting, flooring, new
furniture, upgraded HVAC system, and
replacement windows. A new conference room
and renovated public reception area will be
included as well.
The renovation will improve office efficiency and
productivity. It will also accomodate necessary
MUNIS equipment for staff, contractors and the
public to navigate the new electronic submittal and
processing of permits.
The upgraded HVAC system will save on some
energy costs.
City of Somerville, Massachusetts
84
Capital Improvement Plan FY2012‐2016
Title:Various City Building Improvements
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Project Address:
Multiple
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
100,000 ‐ 100,000 ‐ ‐ ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 100,000 $ ‐ $ 100,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
100,000 ‐ 2,000 2,000 9,500 9,275 9,050
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 100,000 $ ‐ $ 2,000 $ 2,000 $ 9,500 $ 9,275 $ 9,050
The improvements will not require any additional
maintenance costs.
This money will be used to paint classrooms in the
Edgerly School and repair various retractable
curtains in school buildings.
These improvement were requested by the
Superintendent's Office and confirmed by the DPW
Commissioner. The existing curtains are
malfunctioning and the Edgerly School continues
to house students from East Somerville Community
School.
City of Somerville, Massachusetts
85
Capital Improvement Plan FY2012‐2016
Title:Ice Rink Zamboni
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Project Address:
570 Somerville Ave
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
120,000 ‐ 120,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 120,000 $ ‐ $ 120,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 120,000 $ ‐ $ 120,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 120,000 $ ‐ $ 120,000 $ ‐ $ ‐ $ ‐ $ ‐
There will be minimal operating costs associated
with fuel and routine maintenance. These costs will
be offset by ice rink revenue.
Purchase a Zamboni 552 with snow and ice making
water tank. Constructed of high density
polyethylene. Total water capacity is 282 gallons.
The zamboni will be used on the new ice rink
constructed at Conway Park. The expected life is
20 years.
City of Somerville, Massachusetts
86
Capital Improvement Plan FY2012‐2016
Title:Recreation Vans
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
52,000 ‐ 52,000 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 52,000 $ ‐ $ 52,000 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 52,000 $ ‐ $ 52,000 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 52,000 $ ‐ $ 52,000 $ ‐ $ ‐ $ ‐ $ ‐
The new vehicles are likely to cost much less in
repairs than the current vehicles.
Purchase 2 Ford Club 15‐Passenger Vans.
The current vehicles used to transport youth to
their different programs have exceeded their
expected life. The vehicles are at a constant risk of
breaking down.
City of Somerville, Massachusetts
87
Capital Improvement Plan FY2012‐2016
Title:Ice Rink Security System
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Project Address:
570 Somerville Ave
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
17,460 ‐ 17,460 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 17,460 $ ‐ $ 17,460 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 17,460 $ ‐ $ 17,460 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 17,460 $ ‐ $ 17,460 $ ‐ $ ‐ $ ‐ $ ‐
There will be no operational cost impact due to the
security equipment.
Install a security system in the Veteran's Memorial
Ice Rink including an inside siren, motion detector,
and magnetic contacts for exterior doors.
With the increased city investment in the ice rink,
the city needs to protect its assets and secure the
building from vandalism.
City of Somerville, Massachusetts
88
Capital Improvement Plan FY2012‐2016
Title:City Hall Furniture
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Project Address:
93 Highland Avenue
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
11,600 ‐ 11,600 ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 11,600 $ ‐ $ 11,600 $ ‐ $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 11,600 $ ‐ $ 11,600 $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
‐ ‐ ‐ ‐ ‐ ‐ ‐
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 11,600 $ ‐ $ 11,600 $ ‐ $ ‐ $ ‐ $ ‐
Replace the existing chairs around the Aldermanic
Chambers horseshoe and the table and chairs in
the Aldermen's committee room.
The existing chairs are several years old and are
showing signs of substantial wear. The furniture is
used heavily by city staff and by the public as well.
There will be no operational cost impact due to the
new furniture.
City of Somerville, Massachusetts
89
Capital Improvement Plan FY2012‐2016
Title:City Hall Pointing and Exterior Painting
Project Description:
Justification:
Operational Cost Impact:
Mayor's Goal:
6. Accountability & Performance
Project Address:
93 Highland Ave.
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
500,000 ‐ ‐ ‐ 500,000 ‐ ‐
Equipment
‐ ‐ ‐ ‐ ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 500,000 $ ‐ $ ‐ $ ‐ $ 500,000 $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
500,000 ‐ ‐ ‐ 10,000 10,000 47,500
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 500,000 $ ‐ $ ‐ $ ‐ $ 10,000 $ 10,000 $ 47,500
This work will decrease the interior water leaks
and accompanying patch work.
Repoint the mortor and scrape, sand, prep and
paint the exterior of City Hall.
Somerville is a cutting‐edge progressive City, but
City Hall is in a dilapidated state. A fresh coat of
paint will greatly improve the appearance of the
building.
City of Somerville, Massachusetts
90
Capital Improvement Plan FY2012‐2016
Title:FCC Radio Conversion
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
10. Innovative and Responsive Workforce
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
255,000 ‐ 255,000 200,000 ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 255,000 $ ‐ $ 255,000 $ 200,000 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ 200,000 $ ‐ $ ‐ $ 200,000 $ ‐ $ ‐ $ ‐
GO Bonds
80,000 ‐ 1,600 1,600 16,000 16,000 16,000
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
175,000 ‐ 175,000 ‐ ‐ ‐ ‐
Total:
$ 455,000 $ ‐ $ 176,600 $ 201,600 $ 16,000 $ 16,000 $ 16,000
Replace all infrastrucutre and unit equipment
operated by all departments necessary to comply
with the FCC narrowband requirement.
The FCC has mandated that all licensees using 25
kHz radio systems migrate to narrowband 12.5
kHz channels by January 1, 2013.
There will be no operational cost impact.
City of Somerville, Massachusetts
91
Capital Improvement Plan FY2012‐2016
Title:Human Resources Information System (HRIS)
Project Description:
Justification:
Map Not Available
Operational Cost Impact:
Mayor's Goal:
10. Innovative and Responsive Workforce
Total
Estimated
Cost
Prior
Years
Funding
FY 2012
FY 2013
FY 2014
FY 2015
FY 2016
Capital Costs:
Preliminary
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
Design
‐ ‐ ‐ ‐ ‐ ‐ ‐
Land/ROW
‐ ‐ ‐ ‐ ‐ ‐ ‐
Construction
‐ ‐ ‐ ‐ ‐ ‐ ‐
Equipment
500,000 ‐ ‐ 500,000 ‐ ‐ ‐
Administration
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 500,000 $ ‐ $ ‐ $ 500,000 $ ‐ $ ‐ $ ‐
Funding Sources:
Capital Stab. Fund
$ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐ $ ‐
GO Bonds
500,000 ‐ ‐ 10,000 10,000 122,500 118,000
Special Assmnt.
‐ ‐ ‐ ‐ ‐ ‐ ‐
Grants
‐ ‐ ‐ ‐ ‐ ‐ ‐
Total:
$ 500,000 $ ‐ $ ‐ $ 10,000 $ 10,000 $ 122,500 $ 118,000
Although difficult to quantify, an HRIS system will
streamline many functions of the Personnel,
Payroll and Finance Departments.
HRIS is a software or online solution for the data
entry, data tracking, and data information needs of
the personnel, payroll, management, and
accounting functions for the City.
An HRIS System will significantly reduce data entry
and leave Personnel staff to focus on more
strategic HR functions.
City of Somerville, Massachusetts
92
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
APPENDICES
Appendix A: FY2012‐2016 Capital Projects by
Funding Source
Appendix B: Somerville Long‐Term Debt
Outstanding as of June 30, 2011
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
27
Appendix A: FY2012‐2016 Capital Projects by
Funding Source
FY20122016 Capital Project Summary
Funding Source
Item
Year
Project Cost
Debt Service
Assembly SQ
Stab
Capital
Stabilization
CDBG
State Funds
Federal
Funds
Other
Old Union Square Fire Station Remodel
FY12
30,000
$
30,000
$
DPW Roof
FY12
50,000
$
50,000
$
Fire HQ Apron Replacement
FY12
55,000
$
55,000
$
Other Building Improvements
FY12
100,000
$
100,000
$
High School Roof Replacement
FY12
150,000
$
150,000
$
ISD Building Renovation
FY12
150,000
$
150,000
$
Public Safety Building Sally Port
FY12
200,000
$
200,000
$
Radio Conversion
FY12
455,000
$
80,000
$
200,000
$
$ 175,000
Ladder Truck
FY12
1,125,000
$
1,125,000
$
East Somerville Community School
FY12
38,309,249
$
13,000,000
$
15,237,996
$
10,023,433
$
DPW Vehicles
FY12‐16
3,500,000
$
3,500,000
$
Human Resource Information System
FY13
500,000
$
500,000
$
Fire Apparatus
FY13‐16
3,099,500
$
3,099,500
$
Powder House Rotary Signal Equipment
FY14
300,000
$
300,000
$
City Hall Renovations
FY14
500,000
$
500,000
$
Engine 7 Renovation
FY15
1,650,000
$
1,650,000
$
West Branch Library Renovation
FY16
400,000
$
400,000
$
Lincoln Park Sports Complex
FY12‐14
2,040,000
$
1,940,000
$
100,000
$
Dickerman Park
FY12
425,720
$
$ 169,720
256,000
$
Morse Kelley Playground and Park
FY12
682,220
$
298,220
$
384,000
$
Quincy Street Park Renovation
FY12‐13
325,000
$
100,000
$
225,000
$
Pearl and Florence Street Park
FY12‐13
435,000
$
435,000
$
Harris Park Swap
FY12‐13
1,000,000
$
200,000
$
800,000
$
North Street Playground
FY12‐13
1,190,000
$
390,000
$
800,000
$
(5) Laptops with Language Software
FY12
7,500
$
7,500
$
Furniture/Computer Equip. Replacement
FY12
10,000
$
10,000
$
Ice rink security system
FY12
17,460
$
17,460
$
Aldermanic Chamber Furniture
FY12
19,600
$
19,600
$
(1) Mobile A/V Surveillance Equipment
FY12
20,000
$
20,000
$
Toyota Prius Fire Prevention
FY12
24,700
$
24,700
$
Benches & Barrels
FY12
25,000
$
25,000
$
Kenny Park Design
FY12
25,000
$
25,000
$
Winter Hill Play Area Design
FY12
25,000
$
25,000
$
(1) License Plate Reader
FY12
30,000
$
30,000
$
Bullet‐proof Vests
FY12
35,000
$
35,000
$
High School Careers Room
FY12
40,000
$
40,000
$
(1) Ford Van ‐ 14 Passenger
FY12
45,000
$
45,000
$
(2) Ford Escapes
FY12
48,000
$
48,000
$
Funding Source
Item
Year
Project Cost
Debt Service
Assembly SQ
Stab
Capital
Stabilization
CDBG
State Funds
Federal
Funds
Other
Breathing Air Compressor
FY12
48,500
$
48,500
$
Private Way Reconstruction
FY12
50,000
$
50,000
$
High School Weight Room
FY12
50,000
$
50,000
$
(2) 15 Passenger Vans
FY12
52,000
$
52,000
$
Police Radios
FY12
54,000
$
54,000
$
(2) Ford Explorers
FY12
62,000
$
62,000
$
High School Repairs
FY12
100,000
$
100,000
$
Zamboni
FY12
120,000
$
120,000
$
Christmas Decorations
FY12
150,000
$
150,000
$
Conway Ice Rink Locker Rooms
FY12
174,000
$
174,000
$
(8) Ford Taurus
FY12
232,000
$
232,000
$
Police Vehicles
FY13‐16
1,600,000
$
1,600,000
$
Conway 2nd Ice Rink
FY12
3,303,664
$
868,309
$
2,435,355
$
Bike Share Program
FY12, 13
244,905
$
244,905
$
Fire Administrative Command Vehicle
FY13
35,000
$
35,000
$
Engine 7 Roof Replacement
FY13
65,000
$
65,000
$
Boathouse Design
FY14
175,000
$
175,000
$
ADA Improvements
FY12
50,000
$
50,000
$
111 South Street Park Design
FY12
50,660
$
50,660
$
Ed Leathers Park Design
FY12
53,311
$
53,311
$
Union Square Transportation Study
FY12‐13
800,000
$
800,000
$
Road Resurfacing
FY12
1,119,718
$
1,119,718
$
Broadway Streetscape
FY12‐13
8,767,989
$
90,000
$
3,700,000
$
2,883,093
$
2,094,896
$
Community Path
FY12‐13
2,045,358
$
288,200
$
744,769
$
1,012,389
$
Beacon Street Reconstruction
FY12‐14
4,495,000
$
4,095,000
$
400,000
$
Acquire 161 Broadway
FY12‐13
1,500,000
$
$ 1,500,000
DIF Infrastructure Projects
FY12‐13
25,000,000
$
25,000,000
$
Acquire Union Square Post Office
TBD
2,575,000
$
2,575,000
$
Union Square Central Library
TBD
32,681,095
$
32,681,095
$
142,698,149
$
26,829,500
$
1,157,940
$
4,752,974
$
3,367,171
$
20,547,765
$
8,165,482
$
77,829,497
$
TOTAL
Capital Investment Plan FY2012‐2016
City of Somerville, Massachusetts
28
Appendix B: Somerville Long‐Term Debt
Outstanding as of June 30, 2011
City of Somerville, Massachusetts
Long-Term Debt Outstanding as of June 30, 2011
Aggregate Debt Service
Part 1 of 2
Date
Principal
Interest
Total P+I
06/30/2011
-
-
-
06/30/2012
9,224,577.18
2,752,670.53
11,977,247.71
06/30/2013
8,692,936.88
2,484,477.97
11,177,414.85
06/30/2014
8,648,131.58
2,216,940.85
10,865,072.43
06/30/2015
8,443,326.28
1,952,358.73
10,395,685.01
06/30/2016
7,463,520.98
1,674,170.39
9,137,691.37
06/30/2017
7,263,715.68
1,399,988.29
8,663,703.97
06/30/2018
5,463,910.38
1,145,118.69
6,609,029.07
06/30/2019
4,154,105.08
942,905.33
5,097,010.41
06/30/2020
3,569,105.08
785,504.48
4,354,609.56
06/30/2021
3,584,105.08
654,384.88
4,238,489.96
06/30/2022
3,649,105.08
520,196.52
4,169,301.60
06/30/2023
2,009,105.08
370,239.42
2,379,344.50
06/30/2024
1,834,105.08
300,507.32
2,134,612.40
06/30/2025
1,729,105.08
236,162.71
1,965,267.79
06/30/2026
1,359,105.08
175,652.44
1,534,757.52
06/30/2027
1,369,105.08
128,652.21
1,497,757.29
06/30/2028
1,154,105.08
85,142.61
1,239,247.69
06/30/2029
504,105.08
46,010.51
550,115.59
06/30/2030
464,105.08
33,128.41
497,233.49
06/30/2031
364,105.08
21,846.30
385,951.38
06/30/2032
364,105.08
14,564.20
378,669.28
06/30/2033
364,105.08
7,282.10
371,387.18
Total
$81,671,695.16
$17,947,904.89
$99,619,600.05
Par Amounts Of Selected Issues
February 15 2002 non called -Library (I)................................................................................................................................
40,000.00
February 15 2002 non called -Edgerly School (O).................................................................................................................
825,000.00
February 15 2002 non called -Edgerly School Land Acquisition (I).......................................................................................
95,000.00
February 15 2002 non called -Community Center (I).............................................................................................................
85,000.00
February 15 2002 non called -Kennedy School (O)...............................................................................................................
53,304.50
February 15 2002 non called -Healey School (O)..................................................................................................................
41,695.50
February 15 2002 non called -Sewer (I).................................................................................................................................
40,000.00
February 15 2002 non called -Building Renovations (I).........................................................................................................
15,000.00
February 15 2002 non called -Telephone Network Upgrade (I).............................................................................................
15,000.00
February 15 2002 non called -DPW Equipment (I)................................................................................................................
20,000.00
February 15 2002 non called -Fire Pumper 1 (I)....................................................................................................................
20,000.00
February 15 2002 non called -Fire Pumper 2 (I)....................................................................................................................
20,000.00
February 15 2002 non called -Fire/Police Dispatch System (I)..............................................................................................
5,000.00
February 15 2002 non called -Fire/Police Dispatch Consoles (I)...........................................................................................
10,000.00
February 15 2002 non called -Traffic Equipment (I)...............................................................................................................
10,000.00
February 15 2002 non called -Water Mains (O).....................................................................................................................
25,000.00
May 30 2002 MWRA Water (O)..............................................................................................................................................
94,805.30
May 29 2003 MWRA Water (O)..............................................................................................................................................
189,610.60
March 15 2004 -Adv Ref Nov 15 95 Cutler School (O)..........................................................................................................
2,802,142.83
March 15 2004 -Adv Ref Nov 15 95 Land Acquisition (I).......................................................................................................
221,551.21
March 15 2004 -Adv Ref Nov 15 95 Building Remodeling (I).................................................................................................
120,846.10
March 15 2004 -Adv Ref July 1 96 Water (O)........................................................................................................................
588,012.84
March 15 2004 -Adv Ref July 1 96 Sewer (I).........................................................................................................................
562,447.02
May 27 2004 MWRA Water (O)..............................................................................................................................................
284,415.90
August 19 2004 MWRA Water (O).........................................................................................................................................
379,221.20
August 25 2005 MWRA Water (O).........................................................................................................................................
474,026.50
August 15 2006 water broken out -Sewer Construction & Reconstruction 1 (I).....................................................................
960,000.00
August 15 2006 water broken out -Sewer Construction & Reconstruction 2 (I).....................................................................
610,000.00
August 15 2006 water broken out -Lincoln Park School (I)....................................................................................................
2,400,000.00
August 15 2006 water broken out -School Renovations (I)....................................................................................................
190,000.00
August 15 2006 water broken out -Electrical Upgrades and Improvements (I)......................................................................
320,000.00
August 15 2006 water broken out -Sidewalk & Signals (I).....................................................................................................
300,000.00
August 15 2006 water broken out -Water Street Repair (ISS)...............................................................................................
210,000.00
August 15 2006 water broken out -Sidewalks (I)....................................................................................................................
100,000.00
August 15 2006 water broken out -Homens Renovation (I)...................................................................................................
185,000.00
August 15 2006 water broken out -Equipment 2 (I)................................................................................................................
115,000.00
August 15 2006 water broken out -Equipment 3 (I)................................................................................................................
60,000.00
August 15 2006 water broken out -Powder House Building (I)..............................................................................................
540,000.00
August 15 2006 water broken out -Ladder Truck (I)...............................................................................................................
540,000.00
August 15 2006 water broken out -Water (O)........................................................................................................................
690,000.00
August 15 2006 Adv Ref 97 & 98 -Adv Ref Feb 15 97 Kennedy School (O).........................................................................
7,415,000.00
August 15 2006 Adv Ref 97 & 98 -Adv Ref of Feb 15 97 Healy School (I)............................................................................
150,000.00
August 15 2006 Adv Ref 97 & 98 -Adv Ref of Feb 15 97 Building Remodeling (I)................................................................
250,000.00
August 15 2006 Adv Ref 97 & 98 -Adv Ref of Feb 15 97 Land Acquisition (I).......................................................................
60,000.00
August 15 2006 Adv Ref 97 & 98 -Adv Ref April 1 98 Building Remodeling (I).....................................................................
580,000.00
File | Somerville after 10 refunding.sf | Aggregate
FirstSouthwest
Public Finance
Page 1
City of Somerville, Massachusetts
Long-Term Debt Outstanding as of June 30, 2011
Aggregate Debt Service
Part 2 of 2
Par Amounts Of Selected Issues
August 15 2006 Adv Ref 97 & 98 -Adv Ref April 1 98 Parks (I).....................................................................................
130,000.00
August 15 2006 Adv Ref 97 & 98 -Adv Ref April 1 98 Land Acquisition (I)....................................................................
1,055,000.00
August 15 2006 Adv Ref 97 & 98 -Adv Ref April 1 98 Healy School (O).......................................................................
6,230,000.00
November 16, 2006 MWRA Water (O)..........................................................................................................................
568,831.80
May 31 2007 MWRA Sewer (I)......................................................................................................................................
197,835.00
February 12 2008 MSBA School (I)...............................................................................................................................
8,010,311.76
June 12 2008 MWRA Water (O)....................................................................................................................................
663,637.10
February 1 2009 -Trum Field FH I (I).............................................................................................................................
425,000.00
February 1 2009 -Trum Field FH II (I)............................................................................................................................
350,000.00
February 1 2009 -Trum Field FH III (I)...........................................................................................................................
1,700,000.00
February 1 2009 -Computer (I)......................................................................................................................................
10,000.00
February 1 2009 -Fire Alarm (I).....................................................................................................................................
10,000.00
February 1 2009 -Dept Equipment (I)............................................................................................................................
1,405,000.00
December 15 2009 Water (OSS)...................................................................................................................................
3,910,000.00
February 15 2010 -Lincoln Park School (I)....................................................................................................................
2,330,000.00
February 15 2010 -Fire Department Equipment (I)........................................................................................................
90,000.00
February 15 2010 -Outdoor Rec. Facilities-Albion (I)....................................................................................................
46,000.00
February 15 2010 -Outdoor Rec. Facilities-Grimmons (I)..............................................................................................
46,000.00
February 15 2010 -Hodgkins Park & Ballfield (I)............................................................................................................
46,000.00
February 15 2010 -Central Hill Memorial Park (I)..........................................................................................................
46,000.00
February 15 2010 -School Construction (I)....................................................................................................................
90,000.00
February 15 2010 -Water (OSS)....................................................................................................................................
1,791,000.00
April 1 2010 -Library (I)..................................................................................................................................................
285,500.00
April 1 2010 -Edgerly School (O)*.................................................................................................................................. 11,120,000.00
April 1 2010 -Edgerly Land Acq (I)*...............................................................................................................................
1,270,000.00
April 1 2010 -Community Center (I)...............................................................................................................................
608,000.00
April 1 2010 -Kennedy School (O)**..............................................................................................................................
715,000.00
April 1 2010 -Healey School (O)**.................................................................................................................................
557,200.00
April 1 2010 -Sewer (I)...................................................................................................................................................
419,000.00
April 1 2010 -Building Renovations (I)...........................................................................................................................
116,500.00
April 1 2010 -Telephone Network Upgrade (I)...............................................................................................................
79,800.00
April 1 2010 -Fire Pumper 1 (I)......................................................................................................................................
101,000.00
April 1 2010 -Fire Pumper 2 (I)......................................................................................................................................
101,000.00
April 1 2010 -Water Mains (O).......................................................................................................................................
262,000.00
June 15 2010 (ISQ)........................................................................................................................................................
7,445,000.00
February 23 2011 -Water Meters (O).............................................................................................................................
424,000.00
February 23 2011 -School Construction (I)....................................................................................................................
445,000.00
February 23 2011 -Pumper Fire Truck (I)......................................................................................................................
440,000.00
February 23 2011 -Outdoor Rec. Facility Albion (I).......................................................................................................
345,000.00
February 23 2011 -Outdoor Rec. Facility Albion 2A (I)..................................................................................................
105,000.00
February 23 2011 -Outdoor Rec. Facility Albion 2B (I)..................................................................................................
575,000.00
February 23 2011 -Outdoor Rec. Facility Grimmons 1A (I)...........................................................................................
150,000.00
February 23 2011 -Outdoor Rec. Facility Grimmons 1B (I)...........................................................................................
195,000.00
February 23 2011 -Outdoor Rec. Facility Grimmons 2 (I)..............................................................................................
480,000.00
February 23 2011 -Hodgkins Park 1A (I).......................................................................................................................
244,000.00
February 23 2011 -Hodgkins Park 1B (I).......................................................................................................................
491,000.00
February 23 2011 -Hodgkins Park 2 (I)..........................................................................................................................
215,000.00
February 23 2011 -Computer 1A (I)...............................................................................................................................
1,526,165.00
February 23 2011 -Computer 1B (I)...............................................................................................................................
180,835.00
February 23 2011 -Departmental Equipment (I)............................................................................................................
625,000.00
February 23 2011 -Community Path Design and Improvement (I)................................................................................
288,000.00
TOTAL...........................................................................................................................................................................
81,671,695.16