Committee Report - Flood - 11-26-12 — File 194069
November 26, 2012
Flood Forum Special Committee
Page 1 of 2
Printed 12/10/2012
REPORT OF THE FLOOD FORUM SPECIAL COMMITTEE
Attendee Name
Title
Status
Arrived
Maryann M. Heuston
Chair
Present
William M. Roche
Vice Chair
Absent
Bruce M. Desmond
Alderman At Large
Absent
William A. White Jr.
Alderman At Large
Present
Sean T. O’Donovan
Ward Five Alderman
Present
Ginger Barrett
Water Supt.
Present
Rob King
City Engineer
Present
Stan Koty
DPW Commissioner
Present
Alderman O'Donovan was appointed to the committee, for this meeting only, to effectuate a
quorum.
192122 - That the Commissioner of Public Works conduct a study of Dane Avenue to
determine causes of excessive flooding during rain events.:
Mr. King told the members that the city is in final talks with the Union Square project contractor
and that the city wants to have work done on Cedar Street and Hall Avenue. It’s estimated that a
new sewer and drainage system will cost $3 million, not including Dane Street. A broader
solution needs to be devised to alleviate the Dane Street and Union Square flooding problems.
The city is waiting for a consultant’s report regarding other Ward 2 flooding problems, but Mr.
King noted that funding is limited at the present time. The city will explore the possibility of
funding that endeavor through the MWRA and the Water Enterprise Fund. The committee
discussed remediation to residents for damages caused by flooding and Ms. Barrett stated that
none is available.
The committee will follow-up on this matter in January.
RESULT:
KEPT IN COMMITTEE
193933 - That the City Engineer report to this Board the steps that are being taken to
mitigate flooding on streets that are regularly flooded, including Simpson Avenue.:
Committee Meeting
November 26, 2012
Flood Forum Special Committee
Page 2 of 2
Printed 12/10/2012
RESULT:
KEPT IN COMMITTEE