Matters ▸ Attachment
Committee Report - PUPW - 10-24-13 — File 195744
October 24, 2013
Public Utilities and Public Works Committee
Page 1 of 4
Printed 10/24/2013
REPORT OF THE PUBLIC UTILITIES AND PUBLIC WORKS COMMITTEE
Attendee Name
Title
Status
Arrived
Courtney O'Keefe
Chair
Present
Thomas F. Taylor
Vice Chair
Present
Maureen Bastardi
Ward One Alderman
Absent
John M Connolly
Alderman At Large
Present
Alderman Connolly was appointed to the Committee for this meeting only.
•
Update on street light repair contract performance
WORK COMPLETED
190763 - That the Commissioner of Public Works investigate the use of a brine solution to
treat public/private ways during inclement weather in winter.:
RESULT:
WORK COMPLETED
193750 - That the Commissioner of Public Works add the double poles at College Hill
Avenue, Raymond and North Streets, Conwell Ave (between Curtis and Hillsdale),
Chetwynd Road, Curtis Street and 9 Granite Street to his utility company “double pole”
list, and that the Superintendent of Lines and Lights appear at the September 19, 2012
meeting of the Public Utilities and Works Committee.:
RESULT:
KEPT IN COMMITTEE
194351 - That the Commissioner of Public Works place Beacon Terrace on the 2013 re-
paving list.:
RESULT:
WORK COMPLETED
194393 - That the Commissioner of Public Works, the City Arborist and the Director of
SPCD (Transportation and Infrastructure) evaluate the tree at 191 Cedar Street for safety
issues.:
Committee Meeting
October 24, 2013
Public Utilities and Public Works Committee
Page 2 of 4
Printed 10/24/2013
Chairman O'Keefe's motion that the tree at 191 Cedar Street be given special attention during
the reconstruction of Cedar Street, was approved.
RESULT:
WORK COMPLETED
195088 - That the Commissioner of Public Works report to this Board all of the trees taken
down this calendar year that have fallen under the category of imminent risk to public
safety, as well as a list of all the hearings that have occurred in advance of public shade tree
removal.:
RESULT:
WORK COMPLETED
195245 - That the Commissioner of Public Works provide this Board with a complete list of
new street trees planted in the city this year and how many were planted to replace trees
that have been removed without a hearing.:
RESULT:
WORK COMPLETED
195310 - DPW Commissioner responding to various Board Orders submitted this evening.:
Alderman Connolly's motion that the Commissioner of Public Works provide the Committee on
Public Utilities and Public Works with a year end report on the performance of the city's street
light repair vendor, including the number of lights repaired vs the number replaced, was
approved
RESULT:
WORK COMPLETED
195333 - That the City Engineer attend the next meeting of the Public Utilities and Works
Committee to provide an update and timeline on the Hinckley Street and Albion Street
construction projects.:
RESULT:
WORK COMPLETED
195357 - That the Commissioner of Public Works repair the sidewalk at 21 Belmont Street,
at the corner of Belmont Square.:
RESULT:
WORK COMPLETED
195359 - That the Commissioner of Public Works repair the raised sidewalk on Oxford
Street, at the corner of Central Street. (2nd request.):
RESULT:
WORK COMPLETED
Committee Meeting
October 24, 2013
Public Utilities and Public Works Committee
Page 3 of 4
Printed 10/24/2013
195361 - That the Commissioner of Public Works inform the MBTA to clean the property
at the corner of School and Avon Streets and place it on a regular maintenance schedule.:
RESULT:
WORK COMPLETED
195362 -
That the Administration name the baseball diamond, and install a
commemorative plaque, at Foss Park or Draw Seven Park in memory of former Alderman
and State Representative Joseph Mackey.:
Alderman Connolly's motion that the Administration file a Home Rule Petition to name the
baseball diamond, and install a commemorative plaque, at Foss Park or Draw Seven Park in
memory of former Alderman and State Representative Joseph K. Mackey, was approved.
RESULT:
WORK COMPLETED
195372 - That the City Engineer report back in writing to the Committee on Public Utilities
and Works and to the Ward 2 Alderman, regarding #194351, adding Beacon Terrace to the
2013 re-paving list.:
RESULT:
WORK COMPLETED
195469 - Representative Provost responding to #195274 and #193966 re: graffiti under the
Lowell St. Bridge.:
RESULT:
WORK COMPLETED
195498 - DPW Commissioner responding to various Board Orders submitted this evening.:
RESULT:
WORK COMPLETED
195521 - That the Commissioner of Public Works and the Director of SPCD (ISD)
implement a plan to address trash and code violations each May and September, when
student moves have the greatest impact on the City.:
RESULT:
KEPT IN COMMITTEE
195572 - DPW Commissioner responding to various Board Orders submitted this evening.:
RESULT:
WORK COMPLETED
195586 - That the Administration provide the Ward Aldermen with a timeline for all city-
sponsored construction prior to the beginning of said projects.:
Committee Meeting
October 24, 2013
Public Utilities and Public Works Committee
Page 4 of 4
Printed 10/24/2013
RESULT:
WORK COMPLETED
195589 - That Commissioner of Public Works inspect and improve upon the lighting at the
corner of Vernon and Lowell Streets, if necessary.:
RESULT:
WORK COMPLETED
195601 - That the Commissioner of Public Works notify the appropriate utility companies
to place the wires at the intersection of Broadway and Wisconsin Street underground, as
they originally were.:
RESULT:
WORK COMPLETED
195605 - That the Commissioner of Public Works replace the street lamps at the locations
herein named.:
RESULT:
WORK COMPLETED
195646 - DPW Commissioner responding to various Board Orders submitted this evening.:
RESULT:
WORK COMPLETED