REPORT OF THE HOUSING AND COMMUNITY DEVELOPMENT COMMITTEE
Attendee Name
Title
Status
Arrived
Mark Niedergang
Chair
Present
Tony Lafuente
Vice Chair
Present
Katjana Ballantyne
Ward Seven Alderman
Present
Robert J. McWatters
Ward Three Alderman
Present
John M. Connolly
Alderman At Large
Present
William A. White Jr.
Alderman At Large
Present
Mary Jo Rossetti
Alderman at Large
Absent
Maryann M. Heuston
Ward Two Alderman
Absent
Matthew McLaughlin
Ward One Alderman
Absent
Rebekah L. Gewirtz
Ward Six Alderman
Absent
Dennis M. Sullivan
Alderman At Large
Absent
The Committee met as a Committee of the Whole.
Others present: Omar Boukili, George Proakis, Amanda Maher, Ed O'Donnell, Michael Glavin,
Dana LeWinter, Eileen McGettigan
194361 - That the Director of SPCD prepare a written analysis for this Board comparing
the 2010 federal census with the 2000 census and highlighting the important changes and
potential impacts.:
RESULT:
KEPT IN COMMITTEE
195679 - That the Director of SPCD meet with this Board's Committee on Housing and
Community Development to discuss #195571, a proposed $500,000 bond to fund a major
plan change to the existing Assembly Square Urban Renewal Plan.:
Mr. Glavin and Mr. O'Donnell spoke about urban renewal areas and changes that occurred at
assembly Square. The request for $500,000 in item 195571, is to allow the city to proceed to the
next step in the overall project. Supporting documents were distributed and reviewed. This
matter is opportunity driven, and with the Orange Line opening this summer, it would be best to
take advantage of the circumstances as quickly as possible, hopefully within the next several
months. A plan change could take 6-9 months to complete.
Committee of the Whole
April 28, 2014
Housing and Community Development Committee
Page 2 of 3
Printed 5/6/2014
Mr. Glavin stated that SomerVision set out a plan and he believes that the Union Square launch
was deliberately timed to coincide with the expansion of the Green Line. Assyembly Square is
now realizing some growth and expectations and the Inner Belt & Brickbottom areas will follow
in the next 24-36 months. Mr. Glavin is confident that both the Union Square and Assembly
Square projects can be pursued at same time. Alderman Lafuente spoke about the past work of
the Mystic View Task Force (MVTF) and believes that they should be consulted about any plan
change.
Members asked about the plan containing recommendations for eminent domain takings and Mr.
Glavin stated that the plan would identify configurations of sites for the highest and best use of
those parcels, noting that plans could be pursued by property taking and/or negotiations with
property owners. Eileen McGettigan - outlined the steps needed for the plan to take effect, and
told members that until a plan is in place, the Somerville Redevelopment Authority (SRA) can't
take any property by eminent domain. She explained that in the case of Union Square, there was
a MOA to acquire property by May 2013 and the city could do it faster than the MBTA.
Members questioned:
• How a plan change fit with other city initiatives
• What revenue is being generated from Assembly Square, Boynton Yards
and Brickbottom
• The BOA’s loss of plan control, developer selection, etc., once a plan is
approved and turned over to the SRA.
Members of the public spoke on the subject.
Bill Shelton spoke about MVTF’s vision from 15 years ago and how they negotiated a series of
agreements with FRIT, some of which (although they have been not generally spoken about),
have taken place. He feels that the current advisory committee is missing members and that it
should be broader.
Tom Ross pointed out that there could be 50,000 people at Assembly Square, daily, yet there has
been no talk about public safety. The city needs to start thinking about putting a fire station in
Assembly Square and the other areas being developed. Also, consideration should be given to
how streets are reconstructed to allow for timely responses for public safety vehicles.
RESULT:
KEPT IN COMMITTEE
195248 - That the Director of SPCD appear before this Board to provide an update on the
status of the Union Square renewal plan and any transactions that have taken place.:
Mr. O’Donnell stated that the plan implementation is moving ahead and that the mayor
appointed an Advisory Committee to review the 9 developer respondents. Minutes of meetings
have been presented to the public. At this time, the SRA has received a preliminary report from
the Advisory Committee passing along 4 of the 9 respondents to the SRA for their final
selection. The city has an obligation to demolish buildings in the D2 site this summer, per the
MOA with the MBTA.
Committee of the Whole
April 28, 2014
Housing and Community Development Committee
Page 3 of 3
Printed 5/6/2014
Members of the public spoke and expressed concern that tenants were being left out of the
process. Mr. O’Donnell said that there have been a series of public meetings and that he is
available to speak to anyone who wants to do so.
RESULT:
KEPT IN COMMITTEE
195906 - That the Director of SPCD appear at this Board's next meeting on December 12 to
explain the Redevelopment Authority's procedure for designating a developer and taking
property for the Revitalization Plan for Union Square, and provide the members of this
Board with written information about the Plan's costs and funding sources by December
10.:
RESULT:
KEPT IN COMMITTEE
196050 - Director of SPCD responding to #195906 re: the redevelopment of Union Sq.:
RESULT:
KEPT IN COMMITTEE