Matters ▸ Attachment
Kennedy Playground -Cost — File 198615
Sheet1
Page 1
John F Kennedy School Playground
Somerville, MA
Cost Estimate
Prepared by CBA Landscape Architects LLC
Design Development
February 13, 2015
No.
Item
Quantity
Unit
Unit Price
Subtotal
Total
Demolition and Site Preparation
# 1
Mobilization / Logistics / Site Fencing
1
LS
$5,000.00
$5,000.00
# 2
Hardscape Removal & Disposal (Offsite)
5872
SF
$2.00
$11,744.00
# 3
Police Details, etc for sidewalk closures
30
DAY
$344.00
$10,320.00
# 4
Misc. Removals (Play Eq, Site Furnishings. etc)
1
LS
$2,500.00
$2,500.00
Subtotal
$29,564.00
Paving and Edging
# 1
Poured Concrete Pavement
274
SF
$10.00
$2,740.00
# 2
Poured-In-Place Rubber Surface/Tiles
5714
SF
$21.00
$119,994.00
# 3
Asphalt Path at Planting Beds
550
SF
$8.00
$4,400.00
# 4
New Color Coat on Asphalt
2161
SF
$1.50
$3,241.50
# 5
Aluminum Edging at Rubber Surface/Asphalt
90
LF
$5.50
$495.00
# 6
Plastic Timber for Planters, 6”x6”
1168
LF
$19.00
$22,192.00
(30” avg. ht. Retained, 12” buried; dividers)
Subtotal
$153,062.50
Furnishings, Fencing, and Restoration
# 1
Curved Bench
1
EA
$4,200.00
$4,200.00
# 2
6' Bench with Back
1
EA
$1,600.00
$1,600.00
# 3
6' High Black Chain Link Fence
108
LF
$40.00
$4,320.00
# 4
Decorative Element at Main Gateway
1
LS
$8,000.00
$8,000.00
Subtotal
$18,120.00
Playground Equipment
# 1
Swing Set with Basket, Adaptive, Belt Swings
1
EA
$16,200.00
$16,200.00
# 2
Rotating Net Structure
1
EA
$20,368.80
$20,368.80
# 3
LSI Eclipse Rope Climber
1
EA
$30,174.50
$30,174.50
# 4
Refurbish Existing Play Structure
1
EA
$15,000.00
$15,000.00
# 5
Climbing handholds on sloped rubber
75
SF
$9.00
$675.00
# 6
Reset/Relocate Existing Play Panels
1
LS
$2,500.00
$2,500.00
$84,918.30
Plantings, Pruning, and Topsoil
# 1
New Trees
6
EA
$1,200.00
$7,200.00
# 2
New Shrubs (3'-3.5' Ht avg.)
30
EA
$90.00
$2,700.00
# 3
Loam & Seeded Lawn
2500
SF
$0.75
$1,875.00
# 4
Topsoil for Planters
16
CY
$35.00
$560.00
Subtotal
$12,335.00
Subtotal for Demolition and Site Preparation through installation:
$297,999.80
2.5% Bond
$7,450.00
15% Overhead and Profit
$44,699.97
10% Allowance for Restricted Access costs
$29,799.98
10% Contingency / Misc. Expenses
$29,799.98
Total for Construction:
$409,749.73